Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Flora Exports vs Impex-Trading Gmbh & Anr.
2012 Latest Caselaw 4480 Del

Citation : 2012 Latest Caselaw 4480 Del
Judgement Date : 30 July, 2012

Delhi High Court
Flora Exports vs Impex-Trading Gmbh & Anr. on 30 July, 2012
Author: Vipin Sanghi
17
*     IN THE HIGH COURT OF DELHI AT NEW DELHI

+                   Date of Decision: 30.07.2012

%                           FAO(OS) 337/2012

      FLORA EXPORTS                                 .....  Appellant
                        Through:    Mr. Dhruv Mehta, Sr. Adv. with Mr.
                                    Jeevesh Nagrath and Mr. Sameer
                                    Abhyankar, Advocates


                   versus

      IMPEX-TRADING GmbH & ANR.                        .....   Respondents
                     Through:

      CORAM:
      HON'BLE MR. JUSTICE SANJAY KISHAN KAUL
      HON'BLE MR. JUSTICE VIPIN SANGHI

VIPIN SANGHI, J. (Oral)

C.M. No. 12818/2012 (Exemption)

Exemption allowed, subject to all just exceptions.

FAO(OS) 337/2012

1. The appellant, in this appeal under Section 37 of the

Arbitration and Conciliation Act, 1996 (the Act) assails the judgment

dated 13.04.2012 passed by the learned Single Judge in O.M.P.

No.559/2010 on 13.04.2012, whereby the appellants objections to the

arbitral award dated 16.06.2010 under Section 34 of the Act have been

dismissed.

2. The parties entered into Contract No.PJN-1119/06, whereunder

the appellant agreed to supply 56,712 pieces of 100% cotton throws in

9,452 boxes from its plant situated at Panipat to the respondent

situated in Germany. The date of the start of the contract was

02.02.2006. The dispute arose as, according to the

respondent/claimant, the appellant had short supplied the goods which

were discovered upon receipt of the goods in Germany.

Consequently, the respondent sought refund of the excess amount

realized by the appellant for the consignment along with interest.

3. The said dispute was referred to arbitration, registered as Case

No.1544. The arbitration was conducted in accordance with the rules

of Indian Council of Arbitration in terms of the agreement of the

parties. The primary issue of fact which arose for determination by

the arbitral tribunal, was as to who was responsible for the shortage of

goods. Under the contract, the aforesaid supply was to be made by

30.04.2006 ex-Bombay Port on CFR basis. The goods were to be

transported by a sea going vessel from Bombay to Rotterdam through

Maersk Line (India) Pvt. Ltd. Further, the goods were to be taken by

container trucks from Rotterdam to the warehouse of the respondent

at Greven, Germany under the supervision of Vat-Logistic Company,

the agent of the respondent.

4. The first consignment of four containers was delivered by the

appellant to the respondent without any complaint. The second

consignment of four containers, after inspection by the respondent's

authorized representative, left the factory premises at Panipat. The

appellant claims that after the containers were stuffed, they were

sealed by the officers of the excise department by a lead seal piler and

a report was prepared on the spot. The blue seal of the shipping line

was also put on the containers. The appellant also locked the

container with an iron strip and a lock. The container was then sent to

Inland Container Depot (ICD) at Tughlakabad in Delhi. While two of the

containers left the factory premises of the appellant on 09.05.2006 and

reached ICD at Tughlakabad on 11.05.2006, the third left the factory

on 12.05.2006 and reached ICD on 15.05.2006. The fourth container

left the factory on 13.05.2006 and reached ICD on 15.05.2006.

5. The said containers were further sealed with a white coloured

customs seal. The containers were then sent to Bombay Port, where

they were inspected, loaded and checked by the customs officers.

They were then loaded on to the vessel for onward sailing to

Rotterdam. The vessel reached Rotterdam on 12.06.2006 and the

containers ultimately reached the warehouse of the respondent of the

respondent at Greven, Germany on 22.06.2006. The appellant claims

that all the four containers comprising the second consignment with all

seals intact were received by the respondent at its warehouse at

Greven, Germany on 22.06.2006.

6. The respondent complained shortage of cartons. It was

claimed that in three out of the four containers, as opposed to 3504

cartons, only 1186 cartons were found, and 2318 cartons were

missing.

7. In the light of the aforesaid, the primary dispute which arose

between the parties was purely a factual dispute, i.e. the

determination of the place where the goods had been lost in transit. If

the goods had been lost in transit in India, the appellant was

responsible, whereas, if the goods had been lost after reaching the

port at Rotterdam, the respondent would have been responsible.

8. The learned arbitrator took into account the evidence led

before him and arrived at the conclusion that the shortage/theft, if any,

had taken place while the goods were in transit in India between

Panipat and ICD Tughlakabad. This finding of the learned arbitrator

was founded upon, inter alia, the following evidence:

i) The FIR lodged at police station Kalkaji by the appellant

indicated the time of occurrence between 9th and 15th May,

2006. In this complaint made by Atlas Shipping Services Pvt.

Ltd. engaged by the appellant, the total quantity stated to be

missing in each container was, as indicated by the

respondent in its e-mail to the appellant. The FIR recorded

the suspicion of the appellant on the driver of M/s. Ravi

Roadways of his having stolen the goods in transit to ICD,

Tughlakabad.

ii) The modus operandi of theft taking place between Panipat

and ICD, Tughlakabad was brought on record by the evidence

of Sunder Lal, Sub-Inspector. He affirmed the complaint

received from Atlas Shipping Services, which named the

driver Guddu as the main culprit.

iii) The Sub-Inspector confirmed that there were complaints of

goods being stolen between Panipat and ICD, Delhi.

iv) The respondent relied upon the news reports of 4th July and

29th August, 2006 to this effect.

v) The distance between Panipat and Delhi should not have

taken three days for the containers to reach ICD Delhi from

Panipat.

vi) The incident of theft of goods regularly taking place between

Panipat and Delhi was known to exporters of textiles.

vii) The modus operandi of committing theft from sealed

containers had been disclosed by the police authorities in

their press release. The rivet of doors which are fixed to the

container from one side, and are held together by locks and

other closing mechanism at centre are removed, and after the

goods are removed, the door is then riveted again. In this

style of opening of the container doors, the seals affixed on

the container doors are not affected at all and gives a false

impression that the container doors have not been tampered

with.

viii) The transit time of the container trucks from Rotterdam port

to works site of the respondent at Greven was within the

normal time of three hours, making it almost impossible to

tamper with the container and steal the goods.

ix) The appellant itself informed the respondent that they had

suffered similar loss of goods during container movement in

2005 against different supply orders of some other firms in

Panipat.

9. The appellant, for the first time, raised the issue that the

goods had been stolen while they were in transit from Rotterdam port

to the respondent's facility at Greven, Germany in their objection

petition. It was contended that the goods had reached the Rotterdam

port on 12.06.2006 and not on 22.06.2006, as assumed by the learned

arbitrator. Therefore, according to the appellant, there was sufficient

time for the theft to take place while the goods were in transit from

Rotterdam to Greven. It was argued by the appellant that since the

tribunal had proceeded on a fundamentally wrong premise that the

time of transit was only three hours (whereas it was over ten days), the

finding that the goods could not have been lost between Rotterdam

and Greven was patently erroneous, thereby rendering the award

patently illegal and liable to be set aside.

10. The learned Single Judge has examined this plea of the

appellant squarely in the impugned judgment. The learned Single

Judge observed that this issue was never raised by the appellant

before the arbitral tribunal. It was not the case of the appellant that

the theft had taken place while the goods were in transit after reaching

Rotterdam port. The submission of the appellant before the learned

Single Judge was, and even before us is, that the learned arbitrator

should have himself noticed the fact that the consignment in question

had reached Rotterdam port on 12.06.2006 and not on 22.06.2006.

The contention of the appellant was, and continues to be, that there

was sufficient time for the goods to be stolen after they had reached

Rotterdam.

11. The learned Single Judge noticed that it was the learned

arbitrator who put the question to the surveyor of the respondent on

the issue whether the theft could have taken place at Rotterdam. It

was not even the appellants case that the goods could have been

stolen at Rotterdam. The learned Single Judge, as aforesaid, has rightly

rejected the said submission of the appellant.

12. Before proceeding further, we may notice a patent infirmity in

the appellants submission. Though the goods appear to have reached

the Rotterdam port on 12.06.2006, as contended by the appellant, it

appears that the same were got released from the customs at

Rotterdam port by the respondent only on 21.06.2006, as customs

duty was paid on that date. Therefore, it is wrong for the appellant to

contend that the goods were available with the respondent or its agent

from 12.06.2006 itself. The goods were in the custody of customs at

Rotterdam upto atleast 21.06.2006. Pertinently, it was not even the

appellants case that the goods had been stolen while they were in the

custody of the customs department at Rotterdam port.

13. As rightly observed by the learned Single Judge, the learned

arbitrator was required to return a finding on a pure question of fact

based on the evidence led before him and on the basis of

preponderance of probabilities. It is well settled that findings of fact

returned by the arbitrator which are founded upon evidence cannot be

interfered with by the Court while hearing objections to the award as

the Court does not sit in appeal over the arbitral award.

14. The learned Single Judge has set out the reasoning given by

the learned arbitrator for arriving at his conclusion on facts that the

theft, in all probability, had taken place while the goods were in transit

from Panipat to ICD, Tughlakabad. We consider it appropriate to set

out the said reasoning, as the same clearly shows that the learned

arbitrator has analysed the evidence before him in a reasonable way

and the conclusion drawn by him is plausible and highly probable. The

conclusion reached by the learned arbitrator reads as follows:

" That there was shortfall of cartons after 3 disputed containers were opened is supported by the surveyor appointed by the Claimants in Germany.

It therefore, clearly needs to be established that if the Respondents have dispatched 9452 cartons (containing 56,712 pieces) and the Claimants have not received all the goods obviously the containers have been tampered and the goods have been removed/stolen.

Based on sequence of events from the Respondents works site at Panipat till the receipt of goods at the Claimants site at Germany, the probability of containers being tampered with and the missing goods removed is highest between Panipat to ICD, Delhi route. This contention is supported strongly by the fact that 3 disputed containers took 41-42 hrs. to cover the distance which is normally covered in 10-12 hrs.

In all probabilities, therefore, it is strongly established that the containers when en route to Delhi from Panipat have been tampered with and the missing goods removed i.e. stolen from the containers. This has been obviously done in collision with freight forwarder and his sub agent M/s. Ravi Road Ways including the drivers of the trucks who were moving the containers.

That there is occurrence of this possibility is strengthened by the police officials statement that there were occasions when FIRS were lodged indicating the export containers are being tampered with while moving from Panipat to ICD, New Delhi and goods stolen. Further the Respondent upon being

informed by Claimants of shortage of goods also suspected that the goods were stolen between Panipat & Delhi they directed the freight forwarder to lodge FIR for missing goods.

Police authorities in their press release have confirmed that the rivets of doors which are fixed with the container from one side and are held together by locks and other closing mechanism at centre and gets fully opened when the rivets are removed and after the goods are removed, the door is then riveted again. In this style of opening of the container doors it can be observed that the seals affixed on the container doors are not affected at all i.e. the seals remain intact. This gives false impression that the container doors have not been tampered with. Thus the submission by the Respondents that the seals were intact is not tenable to say that the container doors have not been tampered with.

As stated earlier the transit time of the container trucks from Rotterdam port to works site of the Claimants at Greven was within the normal time of 3 hrs. only making its almost 'nil' possible to tamper the container and steal the goods.

In view of the above it is well established that if the Respondents have dispatched goods as per purchase order and the claimants have received the short supply of 13,908 pieces it is a strong possibility that the containers were tampered with and the goods have been removed from the containers".

It also seems that the Respondent is either not aware or is aware but has chosen to ignore the fact that the containers on journey from Panipat to ICD, Delhi are being tampered with and goods are stolen. It is also interesting to note that the Claimants did inform the Respondents that they had suffered similar loss of goods during the container movement in 2005 against the different material ordered by the Claimants on some other firm in Panipat. In that case the Panipat Firm established that the goods were stolen in connivance with driver of the truck. The Indian firm then replenished the quantity of missing goods.

Based on the evidence provided by the Respondents that the excise official stuffed the containers in their presence and issued examination reports it is clear that no. of cartons as

per Invoice were stuffed i.e. requisite no. of pieces have been loaded in respective containers at the works site of the Respondents.

Thus considering various reasons as stated above I conclude that the containers have been tampered with and goods to the extent of 13,908 pieces have been removed/stolen during the journey of containers from Respondent's work site at Panipat to ICD, Delhi. In view of the conclusion that the 13,908 pieces have been removed/stolen during transit from Panipat to ICD, Delhi the Claimants have received short supply of 13,908 pieces at Greven in Germany."

15. Accordingly, we find no merit in this appeal and dismiss the

same.

C.M. No. 12817/2012 (Stay)

Since we have dismissed the first appeal, this application does

not survive. Application stands disposed of.

VIPIN SANGHI, J.

SANJAY KISHAN KAUL, J.

JULY 30, 2012 sr

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter