Citation : 2012 Latest Caselaw 4073 Del
Judgement Date : 11 July, 2012
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CRIMINAL L.P. No.599 of 2011
Decided on : 11th July , 2012
TELESTRA TRADE PLACE PVT LTD ..... Petitioner
Through: Mr. Ashutosh Dubey, Advocate.
versus
JAGDAMBAY BUILDERS PVT LTD ..... Respondent
Through: None.
WITH
+ CRIMINAL L.P. No.600 of 2011
POLAR SECURITY & FINANCE PVT LTD ..... Petitioner
Through: Mr. Ashutosh Dubey, Advocate.
versus
JAGDAMBAY BUILDERS PVT LTD ..... Respondent
Through: None.
WITH
+ CRIMINAL L.P. No.601 of 2011
POLAR SECURITY & FINANCE PVT LTD ..... Petitioner
Through: Mr. Ashutosh Dubey, Advocate.
Versus
SANJEEV CHANNA ..... Respondent
Through: None.
CORAM:
HON'BLE MR. JUSTICE V.K. SHALI
Crl. L.P. Nos.599, 600, 601/2011 Page 1 of 8
V.K. SHALI, J. (ORAL)
Crl. M.A. No.19792/2011 (for delay) in Crl. L.P. No.599/2011 Crl. M.A. No.19809/2011 (for delay) in Crl. L.P. No.600/2011 Crl. M.A. No.19811/2011 (for delay) in Crl. L.P. No.601/2011
1. The aforesaid three leave to appeal petitions are filed
against the impugned order dated 3.11.2010 and 15.2.2011
by virtue of which the learned trial court had dismissed the
complaint of the petitioner/complainant in default on account
of non-appearance of the complainant and also for non-
prosecution.
2. Briefly stated the facts of the case are that the
petitioner/complainant is claiming itself to be a company
registered under Companies Act, 1956 and one Pramod Mishra
was appointed as an authorized representative to file the
complaint vide Resolution dated 29.5.2009. On account of
three separate cheques having been dishonoured, which were
purportedly issued by the respondents, three separate
complaints were filed. These cheques were for an amount of
Rs.29 lacs, Rs.12 lacs and Rs.36 lacs. It was alleged in the
complaint that these cheques were issued by the respondent-
company to the petitioner/complainant in discharge of its legal
liability but as they were dishonoured, after compliance with
the statutory provision of serving a demand notice, action by
way of three complaints was initiated. All these three
complaints have been dismissed vide impugned order.
3. The present three leave to appeal petitions have been
filed along with application under Section 5 of the Limitation
Act seeking condonation of 345 days' delay in filing the
Criminal L.P. Nos.599 and 600 of 2011 and 240 days' delay in
filing the Criminal L.P. No.601 of 2011. The reasons given for
the delay in filing the leave to appeal, as stated in the
application, are that in the month of April, 2011, there arose
some dispute between the authorized representative and the
company as a consequence of which, the authorized
representative left the company and he did not inform the
status of the cases. The petitioner/complainant appointed a
new authorized representative, who appeared in some other
case than these three cases against the accused persons in
Dwarka courts on 1.12.2011. The accused is alleged to have
filed an application seeking cancellation of the proclamation
purported to have been issued against him under Section 82
Cr.P.C. where allegedly the accused/respondent purportedly
made a wrong statement that the three other cases have been
compromised with the petitioner. It is stated that this was a
wrong statement and upon checking, it was found that these
three complaints, in respect of which the present leave to
appeal petitions have been filed, were actually dismissed for
non-prosecution. It is stated that this was the reason that
there was a delay in filing the leave to appeal petitions.
4. I have considered the submissions made by the learned
counsel and have gone through the record and the applications
seeking condonation of delay. There is no dispute about the
fact that law regarding condonation of delay in filing the
appeal has been diluted by the Hon'ble Supreme Court with
the passage of time starting from the case of Ramlal, Motilal
And Chhotelal vs Rewa Coalfields Ltd.; 1962 SCR (3) 762 to
the latest trend so as to hold that each day's delay is not to be
explained by the party seeking condonation of delay but he
has to give some cogent, convincing and pragmatic reasons for
non-appearance and further the bona fides of the party have
to be seen. It has also been held that quantum of delay may
not be relevant in such cases.
5. Keeping in view these broad parameters, a pragmatic
approach has to be taken. In the instant case, the bona fides
of the explanation given by the petitioner/complainant itself
seems to be suspicious. The complaints have been admittedly
dismissed on 3.11.2010 and 15.2.2011 by the learned
Magistrate despite keeping it pending till 4 p.m. when nobody
cared to appear. The petitioner/complainant says that dispute
between the company and the authorized representative arose
only in the month of April, 2011. If that be so, it could well be
presumed that the authorized representative himself had
recorded the date as 3.11.2010 correctly or he would have
checked the date immediately thereafter, which does not seem
to have been done.
6. In addition to this, the petitioner- company cannot thrust
everything on to authorized representative. The authorized
representative was appointed only for the purpose of filing the
complaint and following it up. It was essentially for the
Secretary of the company or the legal department or the
Managing Director to have obtained the report regarding the
progress of the complaint cases filed by them. It is
unacceptable and unbelievable that after appointing the
authorized representative, the company is not interested to
find out as to what has happened to its cases. If it does not do
so, then obviously it is grossly negligent which cannot be said
to be constituting sufficient cause. Further, the explanation
which has been given by the petitioner/complainant is that
they learnt about the dismissal of the complaint only through
another case between them and the accused, where the
accused approached Dwarka District Court for cancellation of
proclamation. It is very strange that a company which is filing
cases under Section 138 of Negotiable Instruments Act and
that too of huge amount of Rs.29 lacs, 12 lacs and so, would
not follow it up and if they do not do it, they do so at their own
peril. It has been noticed in Delhi courts that there are nearly
seven lacs cases as on date which are pending adjudication in
the courts of Magistrates. This is only on account of the fact
that the companies like the petitioner's company, after filing
the complaints, feel their job has been done and do not follow
it up effectively, as a consequence of which, every day
pendency of these cases keeps on piling up.
7. Keeping in view the aforesaid facts, I feel that in the
instant case also, the petitioner/complainant, after filing of the
complaint against the respondent had been grossly negligent
in not following it up timely and if they were so, it cannot be
said to be constituting a sufficient cause which can be
condoned.
8. Accordingly, I feel that in these leave to appeal petitions,
the petitioners have not been able to show 'sufficient cause'
for condonation of delay. Accordingly the applications seeking
condonation of delay are dismissed. Since the applications for
condonation of delay itself has been dismissed, therefore,
leave to appeal petitions also stands dismissed.
V.K. SHALI, J.
JULY 11, 2012 'AA'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!