Citation : 2012 Latest Caselaw 4058 Del
Judgement Date : 11 July, 2012
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of Decision: 11.07.2012
+ CS (OS) 1530 of 2003
Dr.(Ms.) V.L. Bhargava and Anr. ... Plaintiffs
versus
Shri Balwant Singh and Anr. ... Defendants
Advocates who appeared in this case:
For the Plaintiffs : Mr.Sudhanshu Batra, Sr. Advocate with
Mr.Bhuvan Gugnani, Advocate,
For the Defendants : Mr. Harish Gupta, Advocate
AND
+ CS (OS) 1173 of 2004
(Earlier suit No. 209 of 2003 before transfer)
Shri Balwant Singh ...Plaintiff
versus
Dr.(Ms.) V.L. Bhargava and Anr. ...Defendants
Advocates who appeared in this case:
For the Plaintiff : Mr. Harish Gupta, Advocate
For the Defendants : Mr.Sudhanshu Batra, Sr. Advocate
with Mr.Bhuvan Gugnani, Advocate,
CORAM:
HON'BLE MR. JUSTICE ANIL KUMAR
CS(OS) 1530/2003 and CS(OS) 1173/2004 Page 1 of 35
ANIL KUMAR, J.
*
This judgment shall dispose of the suit of Dr. Bhargava & Anr.,
hereinafter referred to as „owner's‟/Plaintiff; suit for recovery of
Rs.22,69,894.50 with pendente lite and future interest at the rate of
18% per annum and the cross suit of Balwant Singh, hereinafter
referred to as „Builder‟/Defendants for recovery of Rs.2,67,150/- with
pendent lite and future interest at the rate of 24 % per annum on the
principal amount from 1.5.2003 till the decision of the suit.
CS(OS) No.1530/2003
1. The owners contended that plaintiff No.1 is a well known
gynecologist and plaintiff No.2 is a retired Army Officer and brother of
plaintiff No.1. They jointly purchased a land measuring 743.15
sq.mtrs. bearing No.49 on Pine Drive in Malibu Town, District Gurgaon,
Haryana, by a registered sale deed dated 29th March, 2000. The
physical possession of the plot was handed over on 5th May, 2000.
After getting the possession, the plaintiffs contemplated the
construction of a residential house on the said plot and, therefore, they
arranged for a loan to the tune of Rs.27,00,000/- from HDFC Limited.
2. For the purposes of construction, a contractor was also required
and since defendant No.1, Shri Balwant Singh, had been doing contract
job for Sita Ram Bhartia Institute of Science and Research where
plaintiff No.1 was working as a Senior Consultant, he was asked to
quote his rates for material and labor, so that the construction could be
carried out. According to the owners, the builder/defendant No.1 gave
an item-wise list of rates for construction of structure of the proposed
house. The rates quoted by the defendant No.1 were accepted and he
also promised to complete the construction by April 2002. The
defendant No.2, is the son of defendant No.1 and he also works with
him and he also acted as an agent of defendant No.1, his father, from
time to time.
3. The plans for the construction of house were sanctioned on/or
about 19th June, 2000 and initial working drawings were handed over
to defendant No.1 on 27th June, 2000. On 17th July, 2000, the plaintiff
had requested for the advance payment for purchase of stores and,
therefore, a sum of Rs.4,00,000/- was paid by an account payee cheque
drawn on HDFC Bank, New Delhi. The structural drawings for the
basement were submitted to the defendants by M/s. Space Combine
on/or about 15th August, 2000 and excavation was completed by the
defendants for construction in the first week of October, 2000.
4. During the construction, defendant No.1 requested for more
funds and consequently the amounts were paid in three installments by
cheques dated 12th January, 2001; 18th January, 2001 and 20th
February, 2001 for Rs.2,00,000/-, Rs.3,00,000/- and Rs.4,00,000/-
respectively. The plaintiffs had already paid a sum of Rs.4,00,000/- on
17th July, 2000 and, therefore, by 20th February, 2001, the defendant
No.1 had been paid Rs.13,00,000/-.
5. In March 2001, the basement structure foundation walls and
pillars were near completion and, therefore, defendant No.1 demanded
more money and he was asked to submit a written bill. The defendant
No.1, therefore, submitted a bill of Rs.10,59,798/- for the work done till
March 2001. After the said bill, the defendant No.1 claimed a further
sum of Rs.2,00,000/- in advance towards the estimated costs for the
construction of a backside boundary wall. The defendants represented
that in case the advance demanded by them is not paid, they would be
unable to speed up the work. Consequently, in the interest of work and
without verifying the actual measurements at the site and in good faith,
the owners gave a sum of Rs.1,00,000/- in cash to defendant No.2 and
another sum of Rs.1,00,000/- was paid in cash to defendant No.2 on
9th April, 2001 as „on account‟ payment.
6. So that the work could be completed within time, the plaintiffs
continued to make payments from time to time and by 12th January,
2002, the plaintiffs had paid a sum of Rs.48,00,000/- though the
defendants had raised only outer walls of the first floor rear portion and
had laid the roof slab, while the plastering of the basement and the
ground floor was still under progress.
7. The owners contended that they had asked their Architect, Mr.
Paschim Tiwari, to ascertain whether the payments made by the
plaintiffs commensurate with the actual work done by the builder, the
defendants. However, the Architect could not do so as the bills had not
been submitted by the defendants to him. The owners had to appoint
another Architect, Mr. Khushroo Kalyanwala, in the first week of
January 2002 as the earlier Architect of the plaintiff, Ms. Garela had to
leave for London. The subsequent Architect visited the premises on/or
about 14/15th January, 2002. The defendant No.1 was requested to be
present at the site and the Architect had asked the defendant No.1 to
prepare a bill of quantities for the floor-wise total structure constructed
untill then. However, the defendant No.1 did not prepare the bill till the
middle of February 2002, and rather he demanded another sum of
Rs.5,00,000/- from the plaintiffs. The defendant No.1 ultimately
handed over a bill to the Architect of the plaintiff, Mr.Khushroo, on 12th
February, 2002 in an essay form. The Architect of the plaintiffs,
therefore, asked the defendant No.1 to submit the bill in an appropriate
format. The defendant No.1 did not submit the bill in the appropriate
format and rather had showed lump sum charges, which were not in
consonance with the rates which had been quoted by the defendant
No.1 before the commencement of the construction.
8. In these circumstances, it is contended by the plaintiffs that they
appointed M/s. Inderjeet Maitra (hereinafter referred to as „IMA‟) as yet
another Architect for evaluating the construction of the building and to
prepare a bill of quantities. On perusing the bill prepared by IMA, it
transpired that the work executed at the site was only for the sum of
Rs.29,00,000/- though an amount of Rs.48,00,000/- had been paid to
the defendant No.1. Defendant No.1 was, therefore, contacted and the
plaintiffs had three meetings between March 2002 to June 2002 with
the representatives of IMA and two meetings at the site for joint
assessment of the quantity of work executed.
9. In the bill which was prepared by IMA at the instance of the
plaintiffs, defendant No.1 pointed out only the discrepancy about the
kota stone used. It is asserted that since the said item related to
execution of hidden items, IMA accepted the quantities proposed by
defendant No.1 of the said item and corrected his abstracts of the bill of
quantities. The plaintiffs contended that thereafter defendants
submitted fresh bills on 4th March, 2002; 9th May, 2002; 26th June,
2002 and 4th July, 2002. The bills submitted by the defendants were
an attempt to justify the excess payment received by the defendants
and the rates quoted in the bills were at variance with the rates which
were given by the defendant to the plaintiff. Even in these bills
submitted by the defendants, certain items were quoted on lump sum
basis. Therefore, plaintiff no.2 sent a letter to defendant No.2 to clarify
the discrepancies/hidden cost. The letter of 9th July, 2002 was replied
by defendant No.1 by letter dated 17th July, 2002, however, till August
2002 no response was given to the bill of quantities and cost prepared
by IMA despite various requests by the plaintiffs.
10. In order to minimize the disputes and resolve them, the plaintiffs
appointed yet another surveyor, Mr. Ankur Aggarwal, registered
Architect with Haryana Urban Development Authority to assess the
extent of construction carried out. The defendant No.1, however,
refused to be present at the time of joint inspection.
11. The plaintiffs contended that the assessment done by Mr. Ankur
Aggarwal, was almost the same as the bill of quantities which was
assessed by IMA.
12. On examining the bills of quantities that was prepared by
assessors appointed by the plaintiffs, it transpired that the defendants
had misappropriated about Rs.16,00,000/-.
13. According to the bill of Shri Ankur Aggarwal, a sum of
Rs.32,70,778/- was payable by the plaintiffs to the defendants for the
work done by the defendants, however, the defendants were paid a sum
of Rs.48,00,000/-. When defendant No.1 was confronted with the bill,
he represented to submit a fresh bill and consequently in October 2002
another bill was submitted which was, however, also based on per
sq.mtr. cost rather item-wise agreed upon at the time of awarding the
contract. In the end of November, it is asserted that another bill was
given which gave some details of quantities for the basement, however,
again the demand was for lump sum payment for the work of ground
floor and first floor executed by the defendants. The bills submitted by
the defendants also had glaring discrepancies as per the plaintiffs.
14. The plaintiffs also asserted that the defendants had constructed a
building only up to the first floor, with the work of plastering and
flooring still remaining incomplete and thereafter, he abandoned the
work, due to which reason the construction work had come to a
complete standstill. Therefore, the plaintiffs demanded the amount paid
in excess to the defendants by a legal notice dated 23rd November, 2002
and also the damages which were caused to the plaintiffs on account of
the non-execution of the work.
15. The plaintiff pleaded that defendant No.1, thereafter, filed a
fraudulent suit for recovery of Rs.2,67,150/- being suit No.209 of 2003
before in the District Court. The plaintiffs also contended that they
were left with no option but to engage another agency to complete the
construction of work at the risk and cost of the defendant and
thereafter, they too filed a suit for recovery, of the amount of
Rs.15,82,715/- with interest at the rate of 18% amounting to
Rs.4,74,814.50 and thus they filed the present suit for recovery of
Rs.22,69,894.50 along with pendente lite and future interest at the rate
of 18% per annum.
16. The suit is contested by the defendants. The defendants
contended that the rate list filed by the plaintiffs is not the rate list
given by the defendants to the plaintiffs. According to them, the said
list was never prepared by the defendants and given to the plaintiffs. It
was contended that the rate list had been fabricated by the plaintiffs
and the defendants had not even signed the said rate list. The
defendants denied that they had represented to complete the work up to
2002. It was also contended that it was agreed with the plaintiffs that
that the defendants would carry out construction on the basis of lump
sum rates mutually agreed between the parties. The defendants
asserted that the Architects of the plaintiffs gave different drawings for
different works at different times and the plan was changed frequently.
It is contended that two different plans were given to the defendants of
the basement. The structure drawing prepared by M/s. Space Combine
which is filed in the court, was stated to be incorrect and fake than
what was given to the defendants. It was also asserted that the
plaintiffs and their Architects used to visit regularly and apprise the
work and only after proper appraisal, the demands were released by the
plaintiffs to the defendants from time to time. Defendants denied that
the demands were made "on account" basis or that the plaintiffs made
the payments without verifying the actual measurement and it was
instead contended that the demands were made only after physically
verifying the actual measurements. The defendants, however, admitted
that a total sum of Rs.48,00,000/- had been paid to the defendants by
the plaintiffs up to 12th January, 2002. It was also contended that Shri
Paschim Tiwari regularly visited the site and checked the construction
and that neither the plaintiffs nor Mr. Tiwari had ever asked for any
bills from the defendants.
17. The defendants further disclosed that they received Rs.33 lakhs
from 9th April, 2001 to 12th January, 2002 as claimed by the
petitioners. It is asserted that the payments were made only after seeing
the construction (both quality and quantity). The defendant asserted
that the payments were made by the plaintiffs on floor wise basis and
after finishing different phases of constructions which had been
mutually agreed between them. In the circumstances, it is contended
that the payments were after the plaintiff/architect/agent had visited
the site and had appraised the construction. Thus, it is urged that the
payments were directly co-related to the progress of work.
18. The defendant alleged that Mr. Khushroo Kalyanwala wanted to
make some illogical changes in the already constructed building against
the site plan. The defendant had not agreed to the changes suggested
by Mr.Khushroo Kalyanwala, since the proposed changes were in
complete violation of the site plan and Municipal bye-laws and also
since the changes proposed would have increased the cost of the
construction for which the plaintiff would have never agreed. The
defendants asserted that they refused to oblige Mr.Khushroo
Kalyanwala who wanted the cost of construction to increase as his fees
was based on the cost of construction. Suggestion given by
Mr.Khushroo Kalyanwala would have enhanced the cost of Rs.12/-
lakhs to Rs.15/- lakhs as per the defendants. As the defendants did not
agree to Mr.Khushroo Kalyanwala‟s proposal, it is contended that
perhaps at his instance the work was stopped and it was he who sowed
the seeds of discontents between the plaintiffs and the defendants.
19. The defendant contended that they had submitted a bill dated
12th February, 2002 which was based on the mutually agreed lump
sum rate floor wise and extra item/work/expenses which were incurred
by the defendant, on the oral assurance of the plaintiffs. Payments were
also received by the defendants on the basis of the said bill. Since, it
was not agreed to carry out the construction on the basis of the rate list
therefore, the bills submitted by the defendant could not be on the
basis of the same, but instead it was on the basis of mutually agreed
lump sum rate floor wise. The defendant denied the report of the valuer,
Ms.Inderjit Maitra, (IMA), since according to them the report was false
and on the basis of concocted measurements multiplied by impossible
and improper rate and the report was therefore, factually and
technically incorrect. According to the defendant the alleged report
takes the rate from a tender which does not exist. The defendant
emphasized that even according to the plaintiff the report had taken
wrong measurements with regard to the Kota stone and a wrong extract
of cost was made, which was later on corrected. The defendant also
denied the meeting between them and the valuer, Ms.Inderjit Maitra.
20. The defendants also denied that they had raised four different
bills dated 4th March, 2002, 9th May, 2002, 26th June, 2002 and 4th
July, 2002. According to the defendants they had raised bill dated 4th
March, 2002 which was with regard to the construction in the
basement and the ground floor and it was not with regard to the first
floor and certain other constructions and expenses, which had already
been incurred by the defendant and it was also argued that the
plaintiffs in principle had agreed to them to the defendant. According to
the defendant the bills produced by the plaintiffs are false and
fabricated/tempered. The defendant also highlighted the differences in
the revalue rate of the plaintiffs‟ valuer inasmuch Ms.Indrajit Maitra
had assessed the bill amounting to Rs.29/- lakhs, whereas, valuation
by Mr. Ankur Agarwal was of Rs.32,70,000/-. Thus, there was a
difference of more than Rs.3,70,000/-. The defendant had, however,
raised bills on the covered area basis i.e. per square fit and not per
square meter. The defendant also denied that they gave any
handwritten bill to the plaintiff. The defendant also contended that in
the construction business termite treatment is generally called
"Aldrine". According to the defendant 98% of the work entrusted to the
defendant was completed i.e. structural work. It was also urged that the
charges framed by the plaintiff is incorrect and that the rates taken by
the plaintiff are not according to the rate list supplied by the defendant
before starting the work. The defendant, however, agreed that the so far
as the covered area bill was concerned, the measurements agreed in the
site plan signed by both the parties on 29th March, 2003 is correct. In
the circumstances, the defendant denied that any amount is due to
plaintiff from the defendant. The defendant also denied that they are
liable to pay interest and the salary of Chowkidar, Electricity Bill, fees of
Architect, rent amount and cost of termite treatment.
21. The plaintiff filed the replication dated 17th December, 2003 and
denied the pleas and contentions of the defendant and the allegations
made by the defendant against the plaintiff.
CS(OS) 1173 of 2004
22. Before the plaintiffs had filed their suit for recovery of Rs.22,
69,894.50/-, the defendant, Sh. Balwant Singh had filed a suit for
recovery of Rs.2, 67,150/- in the Court of District Judge on 27th May,
2003 contending, inter-alia that 98% of the total work of structural
construction had been completed by the defendant and the work was
stopped on account of Mr.Khushroo Kalyanwala, employed by the
plaintiff, who had wanted to enhance the cost of construction as his
fees was based on percentage basis on the total cost of construction,
which is why, he also wanted to bring his own contractors.
23. The defendant, Sh.Balwant Singh, contended in his suit that as
he had completed 98% of the work, he raised a bill of Rs.53,05000/- as
on 11th February, 2002. According to the said defendant an amount of
Rs.5,05,000/- is outstanding and as the matter could not be resolved
and the plaintiff asked for a bill only for the basement, ground floor,
Chhajja and boundary wall, therefore, the defendant raised a new bill
dated 4th March, 2002 which did not include the construction on the
first floor and certain other construction/work.
24. According to the defendant, Sh. Balwant Singh in October, 2002,
a meeting was held at the residence of the Colonel S.N.Bhargava,
plaintiff No.2, and it was decided that the defendants would raise a bill
on the basis of the covered area and rate per square ft. Consequently a
bill dated 19th October, 2002 for Rs.50,67,150/- only was raised out of
which Rs.2,67,150/- has remained due to the defendants. Since the
plaintiffs/owners failed to pay the amount, a notice was given and
thereafter, the suit for recovery of Rs.2,67,150/- was filed. The
plaintiffs/owners filed the written statement dated 9th September, 2003
in the suit filed by the defendant/builder, reiterating all the pleas and
contentions which were raised by them later on in the suits filed by the
owners against the builder for recovery of Rs.22,69,894.50/-.
25. The suit of the defendant-Sh.Balwant Singh for recovery of
Rs.2,67,150/- was transferred from the District Court to High Court
and was renumbered as CS(OS) No.1173/2004.
26. On the basis of the pleadings the following issues were framed on
18th November, 2004:-
1. Whether the suit is barred by limitation? OPP
2. Whether the contract between the parties was on item wise/lump sum basis and/or rate list? OP Parties
3. Whether the parties had exchanged any rate list and if so which one? OP Parties
4. Whether excess payments have been made by the Plaintiffs for work down by the Defendants? OPP
5. Whether the Defendant is entitled to recover a sum of Rs.2,67,150/-? OPD
6. Whether the Defendant had given the Bill for Rs.10,59,798/- for the basement? OPP
7. Whether the Defendant had completed 98 per cent of the contracted work? OPD
8. Whether Dr. V.L. Bhargav had agreed to pay Shri Balwant Singh Bill dated 19.10.2002? OPD (Balwant Singh)
9. Relief?
27. Later on an additional issue was also framed by this Court on
15th December, 2004.
Whether the plaintiffs are entitled to recover a sum of Rs.22,69,894.50/- together with interest and at what rate? OPP.
28. During the trial, the plaintiff examined Dr.(Mrs.)
V.L.Bhargava, PW1; Sh.Satindra Nath Bhargava, PW2; Ms.Veena
Garella, PW3; Sh.Arvind Deshraj, PW4; Sh.Ankur Aggarwal, PW5;
Sh.Khushroo Kalyanwala, PW6; Sh.Anil Kumar Joshi, PW7 and Sh.Brij
Pal, PW8.
29. The builder/contractor examined Sh.Hardeep Singh, DW1;
Sh.Balwant Singh, DW2 and Sh.Dhanwant Singh, DW3.
30. This Court has heard the learned counsel for the parties and has
perused the pleadings, documents and evidence produced by both the
parties. For adjudicating the controversies the findings on different
issues are as under:
Issue No.1
31. The contract for the house was awarded to the contractor/builder
allegedly on the basis of the photocopy of the rate list on 3rd May, 2000
and the contractor had commenced the work on or after 27th June,
2000, when, according to the owners, the initial work drawings were
submitted to the builder, for excavation through their architect. A sum
of Rs.4/- lakhs was given as advance on 17th July, 2000. The structural
drawings were given to the builder/contractor on 15th August, 2000,
thereafter, the amounts were paid to the builder/contractor from time
to time and by 12th January, 2002 the builder/contractor were paid a
sum of Rs.48/- lakhs. According to the owners, since the
builder/contractor had not raised any bill of the work done, they had
demanded to submit a bill, pursuant to which a handwritten bill for
Rs.10,59,798/- for the work done till March, 2001 (Ex. PW1/31) was
given.
32. According to the plaintiffs though the work done till March, 2001
was worth Rs.10/- lakhs, however, the builder/contractor had been
paid Rs.13/-lakhs and since the builder/contractor had pleaded for
more amount, more advance was given up till 12th January, 2002
amounting to Rs.48/-lakhs. Since the builder/contractor delayed in
preparing the bill of quantity and had allegedly submitted a bill dated
12th February, 2002 in SA form (Ex. PW4) which was also incorrect and
showed the rate on lump sum basis which was not agreed to by the
parties, therefore, Mr.Khushroo Kalyanwala had given a format for
preparation of bill to the builder/contractor which is Ex. PW3, however,
the builder/contractor did not prepare the bill in the said format.
33. According to the plaintiffs, the disputes arose between the parties
in relation to the work done and excess payment made in January,
2002, and thereafter a notice was sent by plaintiffs/owners dated 23rd
November, 2002 and the reply was received from the defendants
through their lawyer dated 10th December, 2002.
34. Relying on AIR 1996 Delhi 198 titled as „State of Haryana v.
Bharat Steel Tube Ltd.‟, learned counsel for the plaintiffs has contended
that the time for suit will begin to run from when the opposite party
refused to pay the claim. In this case, since the claim was declined by
the builder/contractor by their lawyer‟s reply dated 10th December,
2002, therefore, the time will start from that point and as the suit was
filed in July, 2003, and the limitation started running from 10th
December, 2002, therefore, the suit is well within the time. The issue
No.1 is, therefore, decided in favor of the plaintiffs and against the
defendants. It is held that the suit is within time.
Issue No.2.
35. This is the most crucial and relevant issue. The plea of the
learned counsel for the defendants is that the plaintiffs ought to have
mentioned in the plaint that the rate list which was allegedly given by
the defendants to the plaintiffs was in fact a photocopy of the rate list
and not the original rate list. Learned counsel has contended that a
photocopy of the alleged rate list, which was marked as X-1 and later on
exhibited as Ex. PW1/31 was annexed with a list of documents filed
with the plaint, however, this document was described as original at the
time of filing of documents in the said list of documents. Learned
counsel for the defendants relied on Order 7 Rule 14 read with Order 13
Rule 1 of Code of Civil Procedure to contend that it was incumbent
upon the plaintiffs to have stated either in the plaint or in the list of
documents filed along with the plaint in compliance of Rule 14 of CPC
that the plaintiffs had not filed the original rate list, but a photocopy of
the rate list.
36. Learned counsel for the defendants has relied on Delhi High
Court (Original Side) Rules, 1997, specially, Chapter-II dealing with
Institution of Suits, Rule 8 Sub rule (x) contemplates that when a party
sues on the basis of documents in his possession or powers then the
documents must be produced along with the plaint with a proper list
thereof. Rule 8 Sub rule (x) is as under:-
"(x) Whether the document or documents on which the plaintiff sues or the documents in his possession or powers are produced along with the plaintiff and with a per list thereof."
37. Learned counsel has also relied on Rule 9 of Chapter II
stipulating that it was necessary for the plaintiffs to verify the list of
documents produced along with the plaint. Chapter II Rule 9 of the
Delhi High Court (Original Side) Rules, 1967 is as under:-
"9. While examining the plaint, it is also necessary to (a) verify the list of documents produced along with the plaint;
(b) ascertain the correctness of the concise statements, if any, (Order VII, Rule 9); (c) whether a copy of the plaint has been filed for the purpose of drawing up of a decree at the relevant stage; (d) check whether as many copies of the plaint or concise statements on plain paper as there are
defendants have been furnished (Order VII, rule 9); (e) compare with the original any copy of account book produced under Order VII, rule 17 and mark the relevant entries therein; (f) get a true copy of the entry together with its translation either in English or in the language of the Court, supported by an affidavit of the person who translated it where such entry is in a language other than English or the language of the Court; and (g) check whether the plaintiff has paid the requisite fee for the service of summons on the defendants, (Order VII, rule 9).
The officer should also see that for every India date mentioned in the plaint, the corresponding date according to the Gregorian Calendar has been given."
38. Learned counsel has further relied on Part-C Direction regarding
the examination of the plaint (Part-C 1(vii) & (x) and 2(e)) to contend
that the plaintiffs ought to have disclosed that they are filing the
photocopy of the rate list and not the original rate list. Part C Direction,
regarding examination of the plaint as relied on by the defendant is as
under:-
"1. (vii) Whether the documents attached to the plaint (if any) are accompanied by lists in the prescribed form and are in order;
(x) Whether the plaintiff has stated in his plaint regarding the documents, on which he relates his claim and, are not in his possession and a statement in whose possession or power they are:
2. (e) It is not necessary to set out the whole or any part of a document unless the precise words thereof are necessary. It is sufficient to state the effect of the document as briefly as possible (Order VI, Rule 9)."
39. Learned counsel referred to the statement of PW1, Dr. Ms. V.L.
Bhargava, wherein she admitted that rough estimate was given of the
total Electricity, Wood Work, etc. which amounted to Rs.17 Lakh for
basement, Rs.20 Lakh for ground floor and Rs.11 Lakh for first floor
and the statement given by the PW2 Satyendra Nath Bhargava wherein
he stated that he had the rate list so he did not ask the defendants
about the rough estimate of the total cost of construction before
awarding the contract and contended that both the witnesses have
contradicted themselves as PW1 had categorically submitted that rough
cost of construction was given to him while, PW2 has deposed that a
rough estimate of total cost of construction was not disclosed before
awarding the contract or before commencement of the construction.
40. The learned counsel for the plaintiffs has contended that the
writer of the bill Exhibit PW-1/3 is the same as the writer of exhibit PW-
7/2 which is a bill dated 5th November, 2002 which was submitted by
Sh.Balwant Singh to Sita Ram Bhartia Institute. According to him
Exhibit PW-1/3 though has been denied by the defendants, however,
comparison of the handwriting especially some of the characteristics of
some of the letters demonstrates unequivocally that the writer of these
two bills is the same person namely Sh.Hardeep Singh. Learned counsel
has also relied on the testimony of Sh.Balwant Singh as DW-2, who
deposed that PW-7/2 is in the handwriting of his son Sh.Hardeep
Singh, however, the said bill is signed by him and he did not identify
the handwriting of the bill Exhibit PW1/3 which was allegedly given to
the plaintiffs. On behalf of plaintiffs‟ a specific suggestion was also given
that PW1/3 is not being identified by him deliberately and intentionally
and in fact it is in the handwriting of Sh.Hardeep Singh. The learned
counsel has also pointed out the testimony of DW-1 Sh.Hardeep Singh
who has rather deposed that PW7/2 is in the handwriting of
Sh.Balwant Singh. The said witness DW1 rather denied the suggestion
that the writer of documents exhibit PW1/3 and PW7/2 are the same.
The learned counsel has emphatically contended that there can be no
dispute as to in whose handwriting PW7/1, PW7/2 and PW1/3 are
written, since if one takes into consideration the signatures on PW7/1
to PW7/5 which are admitted by DW2 Sh.Balwant Singh to be in his
handwriting and if the said signatures on PW7/1 to PW7/5 are
compared with the photocopies of the signatures on PW1/31, it would
be apparent that the signatures on PW1/31 are by the same person
who has signed the Exhibit PW7/1 to PW7/5 i.e. Mr.Balwant Singh.
The learned counsel has also drawn the attention of this Court to the
signatures of Sh. Balwant Singh on exhibit PW4, the bill dated 12th
February, 2002. It was also allegedly submitted by the defendants to
the plaintiff, Sh.V.L.Bhargava that the bill dated 4th March, 2002 is also
a bill which is signed by Sh.Balwant Singh, DW2 which is Exhibited as
PW.5 and the signatures on exhibit PW5 are the same as the signatures
on PW7/1 to PW7/5. Similarly, Exhibit P7 bears the signatures of
Sh.Balwant Singh at point D6 which is admitted by DW2, which is
same as the signatures on Exhibit P8 which is a bill dated 19th October,
2002 submitted to the plaintiff.
41. The learned counsel has contended that though the bills which
were submitted by the defendants were not signed, however, the letters
written by the plaintiff in respect of those bills were acknowledged by
the defendants. Attention has been drawn to the letter dated 9th July,
2002 which was addressed to Sh.Balwant Singh on behalf of the
plaintiff by Sh.Satyendra Nath Bhargava which has been exhibited as
P6 which were admitted by the defendants as well. In reply to letter
dated 9th July, 2002 the defendant had sent a letter dated 17th July,
2002 which has also been admitted by the defendants and is marked as
Exhibit P7.
42. The learned counsel for the plaintiff has contended that in reply
to communication dated 9th July, 2002 on behalf of plaintiffs, a reply
dated 17th July, 2002 was received which refers to the surveyor‟s
reports exhibit PW1/4 and PW1/4A. In the cross examination of DW2,
Sh.Balwant Singh it was admitted by him that Exhibit P6 letter dated
9th July, 2002 was received by him after an abstract cost which are
exhibits PW1/4 and PW1/4A. In the circumstances it is asserted that
even if it has not been categorically admitted by the defendants that
PW1/4 and PW1/4A were received by them, however, a conjoint reading
of P6 and P7 will make it amply clear that the defendants have
acknowledged the knowledge of PW1/4 and PW1/4A which were the
cost of the surveyor. The learned senior counsel, Mr.Batra has
contended that the rates which were given as abstract cost by Smt.
Madhuri Shah of M/s. Inderjeet Maitra were not denied by the
defendants in their response to the letter, Exhibit P6, which is exhibit
P7. The learned counsel for the plaintiff has also relied on the
deposition of plaintiff No.1 by way of affidavit dated 13th December,
2004 specifically stipulating the rates which according to her were
agreed with the defendants. It is submitted on behalf of plaintiff that the
rates which were disclosed in the deposition have not been categorically
denied by the defendants in their depositions by way of affidavits. He
contended that on perusal of the deposition of defendant No.2
Mr.Hardeep Singh on affidavit dated 27th January, 2005 and of
defendant No.1 dated 27th January, 2005 it is apparent that the rates
deposed by the plaintiffs have not been specifically denied by either of
the defendants. He contends that even in the cross examination no
suggestion has been given to the plaintiff No.1 that the rates given by
her in deposition were incorrect or were not the rates which were agreed
between the plaintiff and the defendants. The learned counsel in the
circumstances contended that the rates deposed by the plaintiff no.1 in
her affidavit, are the rates which tally with the rate list given by the
defendants, a photocopy of which is produced by the plaintiffs which is
Exhibit PW1/31. On behalf of the plaintiffs, reliance has also been
placed on the deposition of Mrs.Veena Garella, PW3 who was the earlier
architect of plaintiffs who had deposed that the rate list, a photocopy of
which is PW1/31 is the rate list which was given to the plaintiff no.1,
Dr. Bharagva in her presence by the defendants. Even no suggestion
has been given to Mrs.Garella in the cross examination that the rate list
exhibit PW1/31 was not given to the plaintiffs by the defendants in her
presence.
43. The primary dispute on which all the issues will also depend is
whether the parties had been in ad-idem in respect of the construction
of the house, to be calculated on the rate wise basis or on the lump sum
basis. The plaintiff has produced a photocopy of the rate list which was
allegedly handed over to plaintiff No.1, Dr.(Ms.) V.L.Bhargava by
Sh.Balwant Singh, DW2. Later on, that document was exhibited as Ex.
PW1/31. PW2 has also deposed that Ex. PW1/31 was given by
Sh.Balwant Singh to Dr.(Mrs.) V.L.Bhargava. Though Mr.Garella, who
was examined as PW3 has also deposed that a photocopy of the rate list
was given by Sh.Balwant Singh, DW2 to Dr.(Ms.)V.L.Bhargava, PW1
and the original of the rate list was not supplied, however, considering
the testimonies of the various witnesses it cannot be inferred on the
basis of even preponderance of probability that the photocopy of the
rate list Ex. PW1/31 was given by Sh.Balwant Singh to plaintiff-
Dr.(Ms.) V.L.Bhargava. This is more so because the parties have failed
to discharge their respective onus to prove or disprove the hand writing
on the alleged photocopy of the rate list Ex. PW1/31. Learned counsel
for the plaintiffs has also not been able to explain specifically as to why
the measurements were carried out, if the work was awarded according
to the builder/contractor on lump sum basis.
44. In the plaint which was filed by the owners, it was not disclosed
that they were only given a photocopy of the rate list and the original
was not given to them, rather what was stated was that they had been
given the price list submitted by the builder/contractor. This is not in
consonance with the various provision noted hereinabove. PW1,
Dr.(Ms.) V.L.Bhargava rather deposed that she does know the
differences between the quotation and the rate list. She also admitted
that the alleged rate list Ex. PW1/31 does not bear the property number
of the owner or their name.
45. The said witness had admitted that earlier they had planned to
add a small basement and later on it was decided to extend the same,
therefore, two plans were given to the builder/contractor. In her cross-
examination the said witness had admitted that she was given a rough
estimate which included the electricity, wood work, etc. which was
around Rs.17/- lakhs for basement, Rs.20/- lakhs for ground floor and
Rs.11/-lakhs for the first floor. She also agreed that the alleged rate list
Ex.PW1/31 did not specify the rate for the wood work and sanitary and
the alleged rate list is only for the basic structure including the door
frames. Learned counsel for the builder/contractor has pointed out
that this fact is also corroborated by the reply to the notice dated 10th
December, 2002.
46. Though the alleged rate list, allegedly given by the
builder/contractor to the plaintiff/owners is on a plain paper, however
PW6, Sh.Khushroo Kalyawala had rather deposed in his cross-
examination that the rate list which was given to the plaintiffs was on
the letter head of the builder/contractor and was also signed by the
builder/contractor. The plaintiffs witness has thus refuted their own
plea that the rate list was given on a plain paper which is also the
photocopy. The plaintiffs have not explained as to why the photocopy
was accepted by them and they did not insist for rate list duly signed by
the defendants. The plaintiffs have not even explained the
circumstances under which they accepted only a photocopy of the rate
list not duly signed by the defendants especially since no written
agreement stipulating the terms of construction of the building was
executed between the parties. It is unbelievable that for construction of
a house involving lakhs of rupees, the plaintiffs would not insist for a
proper rate list duly signed by the defendants.
47. In the circumstances, in order to prove whether the rate list
produced by the plaintiffs which has been exhibited as Ex.PW1/31
incorporates the rates which were agreed between the parties, it was
incumbent upon the owners to have proved the rates stipulated in the
alleged rate list, as the whole basis for the transaction seems to be that
the builder/contractor had carried out the construction in the hospital
where the plaintiff Dr.(Ms.) V.L.Bhargava was working. Though the
record was summoned from Sita Ram Bhartia Institute and Mr.Anil
Kumar, Account In-charge, had produced the documents, for
contending that the signatures and the writing of the defendants which
were exhibited as Ex.PW7/1 and PW7/5, which is alleged to be the
same as the signature on Ex PW1/31, however, the said witness also
deposed that he could not identify the handwriting of the defendants
even on PW1/3, which is allegedly in the handwriting of the defendants.
In the circumstances the plaintiffs should have got the expert opinion of
a handwriting expert whether the signatures on PW 1/3 are of the same
person who had signed the letters PW 7/1 and Pw 7/5. The plaintiffs
have failed to discharge their onus properly in the facts and
circumstances.
48. Though, the learned counsel for the plaintiffs had emphatically
emphasized that if Ex.PW1/3 is read with PW1/31 it would be evident
that the builder/contractor had agreed to carry out the work on the
basis of the rate list, which is the photocopy, Ex.PW1/31. However, it is
apparent that Ex.PW1/3 has not been proved. The Account Official of
the Sita Ram Bhartia Institute has not proved Ex.PW1/3, nor has the
plaintiffs taken any steps to take a specimen of the signatures of the
defendant and got them compared with the disputed signatures of the
defendant on Ex.PW1/3.
49. The learned counsel for the plaintiff has tried to draw inferences
on the basis of the other documents i.e. the valuation report prepared
by the plaintiffs‟ valuer, however, that will not establish the fact that
Ex.PW1/31, the photocopy of the rate list which is not signed, and
which does not bear the name of the plaintiff, or any address, was given
by the builder/contractor and that these rates were agreed to by the
defendants.
50. The learned counsel for the defendants had argued that there was
no written agreement between the parties for the construction by
builder/contractor. However, it is not necessary to have a written
agreement on which the parties should have put their signatures to the
documents, which embodied the terms of the agreement. What is to be
seen and inferred is as to on what term the parties were ad-idem in
respect of the terms of the construction which was to be carried out by
the defendants at the plot of the plaintiffs. Primary dispute, therefore,
remains whether the rate list Ex.PW1/31 was given by the
builder/contractor to plaintiffs or not and the construction had to be
carried out on the basis of those rates? On perusal of the entire
evidence and on the basis of the preponderance of probability, it cannot
be inferred that the rate list Ex.PW1/31 was given by the defendants to
the plaintiffs and the parties had agreed to construction of the building
of the plaintiffs on those rates.
51. On the basis of the evidence led by the parties even the
builder/contractor has failed to establish by reliable evidence that he is
entitled for Rs.2,67,150/- and he had agreed to construct the building
of the owners on lump sum basis.
52. The onus of issue No.2 was on both the parties to prove
respectively that agreement for construction of building was on rate
basis or on lump sum basis. On the basis of preponderance of
probability, it cannot be inferred that the parties have been able to
establish whether agreed rates were on ratewise basis or on lump sum
basis. Consequently, the issue is decided against the owners and the
builder/contractor.
Issue No.3.
53. On the basis of the evidence led by the parties and as has been
discussed in issue No.2, both the parties have failed to establish as to
which rate lists had been exchanged between the parties on the basis of
which the construction was carried out by the builder/contractor. The
onus of the said issue was on both the parties and consequently, the
said issue is also decided against both the parties.
Issue No.4
54. The onus of this issue was on the plaintiff. The plaintiffs could
have established that the excess payments have been made by the
plaintiffs to the defendants. Had the plaintiffs established that the
agreement between the parties was on ratewise basis? Since the
plaintiffs have failed to establish that the agreement was on the
ratewise basis, which is the basis of the plaintiffs to claim that the
excess payments have been made by the plaintiffs to the defendants.
Therefore, this has not been established that the plaintiffs made excess
payments to the defendants for the work done by them. Issue, therefore,
is decided against the plaintiffs.
Issue No.5
55. Since the defendant-Balwant Singh also failed to establish that
the agreement was on the lump sum basis and therefore, on the said
basis he is entitled for Rs.2,67,150/-. The defendant therefore, is also
not entitled for Rs.2,67,150/- in the facts and circumstances, and issue
is decided against the defendant accordingly.
Issue No.6
56. On the basis of the evidence led by the parties and as has been
discussed in detail while deciding the issue No.2, it is apparent that the
plaintiffs have failed to establish that the defendant had given the bill
for Rs.10,59,798/- for the work done. The issue is accordingly decided
against the plaintiff.
Issue No.7
57. The onus of this issue was on the contractor/builder that they
had completed 98% of the work. What was exact term for the
construction of the building has not been established by both the
parties. Consequently, it has also not been established that the
defendant had completed 98% of the contracted work because the terms
and conditions and the extent of work which was to carried out by the
defendants has not been established. The issue is therefore, decided
against the defendant.
Issue No.8
58. The Onus of this issue was on the defendant. From the evidence
led by the parties, the defendant-Balwant Singh has failed to lead
cogent evidence on the basis of which the inferences can be drawn that
the plaintiff had agreed to pay Sh.Balwant Singh his alleged bill dated
19th October, 2002. The said issue is therefore, also decided against the
defendant-Sh.Balwant Singh.
Additional Issue and Relief
59. In the circumstances, neither the owners are entitled for a decree
for a sum of Rs.22,69,894.50/- and interest 80% per annum on the
said amount in suit CS(OS) No.1530/2003 against the
defendants/builder/contractor, nor the builder/contractor Sh.Balwant
Singh is entitled for Rs.2,67,150/- claimed by the builder/contractor in
suit CS(OS) No.1173/2004 against the owner of the building.
60. Consequently, the suit CS(OS) No.1530/2003 of the plaintiffs-
Dr.(Mrs.) V.L.Bhargava & Anr. v. Balwant Singh & Anr. is dismissed.
The suit CS(OS) No.1173/2004 of the defendant, Sh.Balwant Singh v.
Dr.(Ms.) V.L.Bhargava and Anr. is also dismissed. The parties are,
however, left to bear their own costs in the facts and circumstances.
July 11, 2012 ANIL KUMAR, J. 'k/vk'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!