Citation : 2012 Latest Caselaw 3809 Del
Judgement Date : 2 July, 2012
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS (OS) No.572/1991
% 2nd July, 2012
M/S ARYA SHAMLAL JAIPALMAL PVT. LTD. AND ORS. .... Plaintiffs
Through: Mr. Om Parkash Sharma, Advocate.
VERSUS
THE DELHI DEVELOPMENT AUTHORITY ...... Defendant
Through: Mr. Rajiv Bansal, Advocate with Mr.
Rahul Bhandari, Advocate.
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
To be referred to the Reporter or not?
VALMIKI J. MEHTA, J (ORAL)
1.
The plaintiffs have filed this suit for recovery of ` 35 lacs
alongwith pendente lite and future interest @ 24% per annum. The break-up
of this amount of ` 35 lacs is given in para 31 of the plaint as under:-
"31. That the plaintiffs are entitled to the following amounts:
i) Refund of penalty ` 8,25,000/-
ii) Interest on ` 8,25,000/- ` 14,00,000/-
from the date of payment till the date of the suit.
iii) Loss of earnings and damages caused ` 45,00,000/-
on account of high cost of construction on account of delay in delivery of possession The plaintiffs are thus entitled to a total sum of over ` 67 lakhs but confine their claim to ` 35 lakhs (rupees thirty-five lakhs only)."
2. The plaintiff Nos.1 to 3 were the successful bidders in an
auction conducted by the defendant/Delhi Development Authority (DDA) on
5.2.1981. The bid was given with respect to plot No.13, L.S.C., „J‟ Block
Saket, New Delhi admeasuring 205-30 sq. yds. The bid price was `
16,50,000/-. The plaintiff Nos.1 to 3 at the fall of the hammer deposited `
4,12,500/- being 25% of the bid amount. The balance amount as per terms
and conditions of the auction [clause 2(vi)] was payable on the Vice
Chairman of the defendant accepting the bid and this being so informed to
the plaintiffs. I may state that the plaintiff No.4 is a company which was
proposed to be incorporated after the submission of the bid by the plaintiff
Nos.1 to 3. As per the plaintiffs, they never received the letter dated
13.4.1981 of the defendant (Ex.RW1/1) with respect to acceptance of the bid
after approval of the Vice Chairman. The plaintiffs claimed that they came
to know of the acceptance of the bid for the first time when defendant
informed them by the letter dated 30.6.1981 (Ex.P2), by inviting reference to
the letter dated 13.4.1981, and stating that since the balance amount was not
deposited, the bid stood cancelled. There is a chain of correspondence
thereafter from 1981 to 1987 between the parties, and details of all of which
need not be given, however, the position which emerged is that the
defendant refused to relent. Firstly, the defendant issued its letter of
restoration of cancellation subject to payment of penalty/restoration charges
as also interest charges and then subsequently for cancellation. The letter of
the defendant stating that the plot would be restored only subject to payment
of restoration and interest charge is the letter dated 26.11.1985 (Ex. P13),
and the letter dated 3.9.1987 (Ex.P18) of the defendant to the plaintiffs is the
letter that in view of the non-payment by the plaintiffs of the
restoration/penalty charges, the bid stood cancelled and the earnest money
stood forfeited. The plaintiffs thereafter sent to the defendant their letter
dated 14.10.1987 (Ex.PW1/29) in para 7 whereof it was stated that when the
Commissioner (Lands) on 19/20.4.1987 informed verbally that penalty
cannot be reduced at that stage, thus, the plaintiffs deposited the penalty
amount of ` 6.60 lacs on 21.4.1987 vide challan No.20214 dated 21.4.1987.
There is no dispute that at the time of deposit of this amount there was no
covering letter that this amount is being deposited under protest or without
prejudice or any other language signifying that the issue has been left alive.
Even thereafter the plaintiffs however continued to correspond seeking
refund of the penalty, however, nothing came out of it. In fact, the plaintiffs
in furtherance of the deposit took possession of the plot on 10.11.1987, after
the defendant wrote its letter dated 9.11.1987 to the plaintiffs that possession
of the plot in question be taken. The plaintiffs however continued to
correspond with the defendant seeking refund of the penalty/restoration
amount, and, on account of failure of the defendant to do so, the subject suit
ultimately came to be filed.
3. The following issues were framed in this case on 7.2.1997:-
"1. Whether the plaint has been signed and verified by a duly authorized person?
2. Whether Notice Under Section 53-A of Delhi Development Act was not served upon the defendant? If so, what is its effect?
3. Whether the plaintiffs are stopped from filing the instant suit in view of the fact that plaintiff had made payments towards the penalty, interest etc.?
4. Whether the imposition of restoration penalty by the defendant was legal?
5. Whether the defendant was entitled to charge interest from the plaintiff on the restoration penalty and other charges?
6. Whether the plaintiff suffered damages on account of delay on the part of the defendant? If so, to what extent and upto what period?
7. Whether the plaintiff is entitled to claim interest on the amount paid to the defendant on account of restoration penalty and interest and at what rate?
8. Relief."
Issue No.1
4. Counsel for the defendant does not press this issue. This issue
is therefore answered in favour of the plaintiffs.
Issue No.2
5. Counsel for the defendant also does not press this issue and
therefore this issue is also answered in favour of the plaintiffs.
6. All these issues can be taken up and disposed of together for the
reason that if the defendant succeeds in establishing that the plaintiffs have
accepted the penalty amount without any protest, by unconditionally making
such payment, and in fact have taken benefit by receiving possession
thereafter, the plaintiffs would be estopped from filing the instant suit. In
fact, in my opinion, the issue besides being one of estoppel, is also one of
acquiescence and the novation of the contract between the parties.
7. At the outset, I would dispose of issue No.5 inasmuch as though
this issue has been framed, there is no such cause of action laid out in the
plaint that the defendant has illegally claimed interest on the
restoration/penalty charges. In fact, I may note that even in the
correspondence which is entered into prior to the filing of the suit, the
plaintiffs had stressed only with respect to the illegality of the
penalty/restoration charges and there is no correspondence which could be
pointed out to the Court by which the plaintiffs had raised a grievance that
the defendant was wrongly claiming interest on the penalty/restoration
charges. This issue is therefore answered in favour of the defendant
inasmuch as no amount of evidence can be looked into once there is no such
pleadings. In any case, I may state that this issue will also be answered in
accordance with the decision of issue No.3, being the principal issue and
which requires consideration, and which I will now take up.
8. So far as issue No.3 is concerned, the following undisputed
facts emerge from the record:-
(i) The plaintiffs never challenged the cancellation of the plot by
the defendant and the forfeiture of the earnest money and as informed to the
plaintiffs vide the defendant‟s letter dated 3.9.1987 (Ex.P18). In case, the
plaintiffs had any grievance they were entitled to approach a Court of law,
initiate appropriate proceedings, whether the same be a suit or a writ
petition, however, at no point of time the cancellation intimated vide letter
dated 3.9.1987 (Ex.P18) was ever challenged.
(ii) The amount of penalty charges on the contrary were in fact
deposited by the plaintiffs on 21.4.1987, and admittedly this deposit was not
accompanied by any letter stating that the amount deposited was under
protest or was without prejudice to the rights of the plaintiffs to challenge
the claim towards penalty charges or the interest charges.
(iii) No doubt remains of the plaintiffs not seeking to challenge the
action of the defendant inasmuch as the plaintiffs vide their letter dated
14.10.1987 (para 7) have categorically accepted the factum of defendant‟s
decision that penalty amount cannot be waived.
(iv) Unconditional benefit of deposit of the penalty charges was
taken when possession was taken by the plaintiffs on 10.11.1987 pursuant to
the defendant‟s letter dated 9.11.1987 (Ex.P20), and, even at this stage the
plaintiffs did not take up the stand that they are accepting the possession
under protest and without prejudice to their rights to recover the penalty
amount and the interest paid thereon.
9. In view of the aforesaid undisputed position which has emerged
on record, I have no hesitation to come to the conclusion that though
plaintiffs had tried to cause the defendant to withdraw the penalty charges,
however, they were not successful and consequently they deposited the
disputed penalty charges. That this deposit was an unconditional deposit
becomes clear from the letter of the plaintiffs to the defendant dated
14.10.1987 (Ex.PW1/29), and para 7 of which reads as under:-
"7.When no reply was received, another letter dated 1.4.87 was addressed by Shri Deep Chand Sharma to the Commissioner (L). When we met the Commissioner (L) on 19/20.4.87 he informed verbally that he had examined the case and penalty cannot be reduced at this stage. We immediately arranged the amount which was amounting to ` 6.60 lakhs, and deposited the same on 21.4.87 vide challan No.20214 dated 21.4.87." (underlining added) A reference to this aforesaid para in the letter dated 14.10.1987
clearly shows that the plaintiffs, for whatever reasons, gave up their
challenge and accepted their liability to pay the penalty charges. This para
specifically refers to the fact that the Commissioner (Lands) of the defendant
had on reconsideration of the case found that penalty charges could not be
reduced and therefore the plaintiffs deposited the penalty charges.
In my opinion, the aforesaid shows clear cut acquiescence, and
if not acquiescence, surely at least an estoppel preventing any challenge by
the plaintiffs to the claim of the penalty charges by the defendant. In fact, in
my opinion, the actions of the plaintiffs show that there is in fact a novation
of contract inasmuch as the plaintiffs by making payment of the penalty
charges without protest thus agreed to take the plot in question at a higher
price. Once the contract is novated it is not permissible for the parties to
contend otherwise. I therefore hold issue No.3 in favour of the defendant
and against the plaintiffs.
10. So far as issue No.4 is concerned, this issue becomes irrelevant
because even assuming that the claim of restoration charges against the
plaintiffs by the defendant was illegal, it is not open to the plaintiffs now to
claim and urge refund of such penalty inasmuch as when the amount was
deposited there was never any issue raised that the amount is being
deposited under protest or without prejudice. In fact, I have already
reproduced para 7 of the Ex.PW1/29 dated 14.10.1987 which shows a clear
cut acceptance on behalf of the plaintiffs to the penalty charges imposed by
the defendant.
11. Once it is held that the plaintiffs acquiesced to the additional
price i.e. penalty charges and the interest claimed, there does not arise an
issue of the plaintiffs having been caused loss by delay in handing over
possession of the subject plot. As already stated above, the penalty charges
were deposited on 21.4.1987, and thereafter, the plaintiffs themselves acted
by taking benefit of the amount deposited as they came forward and took
take possession of the plot. Therefore, I do not find that there is any delay in
handing over possession by the defendant to the plaintiffs, more so even as
late as on 14.10.1987 (Ex.PW1/29) plaintiffs were corresponding on the
issues in question.
12. A resume of the above facts shows that though the defendant
failed to prove the sending of letter Ex. RW1/1, possibly, the plaintiffs knew
that they had either received the letter or in any case they wanted to give
quietus to the dispute inasmuch as they wanted to take benefit of the
possession of the plot for making construction thereon. One more reason
could also be that the plot would have become much more valuable than the
original bid amount plus the restoration and the interest charges, and
therefore the plaintiffs possibly realizing this and wanting a quietus, agreed
to pay the additional amount which was claimed by the defendant. Having
thus taken benefit of payments made by them including by taking possession
of the plot and making construction thereon, the plaintiffs now cannot turn
turtle and allege that the defendant wrongly claimed the penalty amount.
13. Once there is no cause of action of the plaintiffs to claim back
the restoration/penalty charges, obviously there does not arise the issue of
payment of interest to the plaintiffs.
14. In view of the aforesaid, issue Nos. 3 to 7 are answered against
the plaintiffs and in favour of the defendant.
15. Learned counsel for the plaintiffs sought to place reliance upon
a decision of a Division Bench of this Court in the case of Indian Instt. of
Public Opinion Pvt. Ltd. Vs. Life Insurance Corporation of India in LPA
No.9/2012 decided on 11.5.2012 for the proposition that defendant cannot
claim an amount against their own policy. In my opinion, this judgment has
no application in the facts of the present case because the issue in the present
case turns more on the aspects of acquiescence, estoppel and novation of the
contract inasmuch as if the claim of the defendant was illegal the plaintiffs
could have challenged such an alleged illegal claim, but having failed to do
so, they cannot now contend that the claim of restoration/penalty charges on
behalf of the defendant was illegal being against their policies. Reasoning
on issue No.4 given above in para 10 deals and rejects this argument raised
by the plaintiffs.
Relief
16. In view of the aforesaid discussion, the suit of the plaintiffs is
dismissed leaving the parties to bear their own costs.
JULY 02, 2012 VALMIKI J. MEHTA, J. Ne
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!