Citation : 2012 Latest Caselaw 64 Del
Judgement Date : 4 January, 2012
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Judgment delivered on: 04.01.2012
+ FAO(OS) NO.2/2012
M/S. DWARIKA PROJECTS PVT. LTD.
(formerly known as Raj & Associates Construction
Division) ..... Appellant
versus
M/S. BHANDARI ENGINEERS & BUILDERS PVT.
LTD. ..... Respondent
Advocates who appeared in this case:
For the Appellant : Mr. Sandeep Sharma For the Respondent : None
CORAM:
HON'BLE MR. JUSTICE SANJAY KISHAN KAUL HON'BLE MR. JUSTICE RAJIV SHAKDHER
RAJIV SHAKDHER, J (ORAL)
CM No.120/2012 (Exemption ) Allowed subject to just exceptions.
FAO(OS) NO.2/2012
1. This is a classic case where the advocate appearing for the appellant
for reasons best known to him, has been unable to inform us, as to the
relationship that the appellant i.e., M/s. Dwarika Projects Private Limited
has with M/s. Raj & Associates Construction Division. The reason why
we raised this query would become clear as we proceed further with the
narrative. Suffice it to say, in the captioned appeal, a challenge has been
laid to the judgment dated 23.11.2011 passed by the learned Single Judge
in OMP No.163/2006 and an order of even date i.e., 23.11.2011 passed in
OMP No.315/2003, based on which, the earlier OMP was rejected. To be
noted, OMP No.163/2006 was filed evidently by the appellant.
2. In order to appreciate the scope of the challenge and the
submissions made before us today, by the learned counsel for the
appellant, Mr.Sandeep Sharma, one would have to advert broadly to the
facts which gave rise to the award dated 10.01.2006 passed by the learned
Arbitrator, and the impugned judgment of the learned Single Judge,
whereby objections to the award preferred by the appellant, amongst
others, were rejected. The impugned judgment of the learned Single
Judge also disposed of, in addition, two petitions filed under section 9 of
the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the
Act).
BRIEF FACTS
3. It is averred by the appellant that two entities: one of which was a
private limited company, while the other was a partnership firm, agreed to
enter into a joint venture to enable the said entity to apply to the National
Highway Authority of India (in short, NHAI), for being declared eligible
in respect of projects to be executed by NHAI under what was known as
"Phase-II Programme of North- South and East-West Corridors Project"
4. It is important to note since the counsel was unable to tell us what
was the exact legal structure of the joint venture entity, what we have
been able to gather, is that, the joint venture entity was also a partnership
firm, which was given the name of Maharia-Raj JV. The said joint
venture entity, as indicated above, was formed by Maharia Re-surfacing
and Construction Private Ltd. and M/s. Raj & Associates Construction
Division.
5. It is not in dispute that eventually, the NHAI awarded a contract of
"eight- laning of KM 16.500 to KM 29.295 of NH-I in the State of Delhi
(known as Contract Package No.NS-18/DL)", in favour of the joint
venture entity i.e., Maharia Raj-JV. This agreement was entered on
31.05.2001, for a total price of Rs.60,68,53,375.80. The time frame
provided in the agreement for execution of the work was stipulated as 24
months. It is not in dispute that the joint venture entity i.e., Maharia Raj-
JV by an agreement dated 27.05.2002 sub-contracted a part of the work
pertaining to construction of "culverts, bridges and protective works", as
specified in Bill No.5 of the BOQ, forming part of a contract package
valued at Rs.6,84,29,312.80. The sub-contract was given to Bhandari
Engineers and Builders Pvt. Ltd. (in short BEPL), vide agreement dated
27.05.2002. It is not in dispute that NHAI's approval qua the sub-contract
was received by Maharia Raj-JV.
6. It appears that the work given to Maharia Raj-JV, under the main
contract; a part of which was to be executed by the sub-contractor i.e.,
BEPL got delayed purportedly on account of failure of Maharia Raj-JV to
hand over the site, with clearances and construction drawings, within an
appropriate time frame. BEPL having executed a part of the work sub
contracted to it claimed the requisite re-compense, in respect of the work
executed by it, from Maharia Raj-JV. One of the grounds for seeking
recompense was that, Maharia Raj-JV in turn had received payments on
its behalf from NHAI. Since disputes arose on this account, the matter
was referred to an Arbitral Tribunal. The Arbitral Tribunal, it appears,
passed two separate awards dated 28.12.2005 and 10.01.2006 in respect of
two separate contract packages. To be noted in the present appeal, the
appellant has assailed the award dated 10.01.2006.
7. In so far as award dated 10.01.2006 is concerned, Maharia Raj-JV
filed its objections vide OMP No.220/2006, while the appellant (i.e.,
M/s. Dwarika Projects Pvt. Ltd.) curiously, filed separate objections vide
OMP No.136/2006.
8. It is in this context, as indicated at the very outset by us, we had
put to Mr. Sandeep Sharma as to what was the legal relationship of the
appellant with M/s. Raj & Associates Construction Division which was
one of the entities instrumental in forming Maharia Raj-JV. Mr. Sharma
feigned complete ignorance as regards this crucial aspect.
8.1 Mr. Sharma, however, sought to argue before us only one singular
point, which was that, at the time of formation of the joint venture entity
i.e., Maharia Raj-JV, one of its constituent's i.e, Maharia Re-surfacing
and Construction Pvt. Ltd., had authorised its Director Sh. Vinod Goel
vide a resolution dated 02.09.2010 passed by its Board of Directors to
further finalise the terms of a joint venture agreement with the other
constituent i.e., M/s. Raj & Associates Construction Division. He further
contended that by virtue of the very same resolution of the Board of
Directors, it had been resolved by Maharia Re-resurfacing and
Construction Pvt. Ltd. that it would enter into a joint venture agreement in
the name and style of Maharia Raj-JV solely for the purpose of
participating in the pre-qualification exercise carried out by NHAI, and
for submitting a joint tender for "Phase-II Programme of North-South and
East-West Corridors Project of NHAI".
9. In substance, it was argued that the joint venture entity i.e., Maharia
Raj-JV was formed only for the pre-qualification exercise, and that, a
further agreement had to be entered into with the other constituent of
Maharia Raj-JV i.e., M/s. Raj & Associates Construction Division to take
the matter further. Mr. Sharma thus argued that since no authority had
been conferred on Sh. Vinod Goel to enter into a contract with NHAI, the
appellant, which was purportedly the avatar of M/s. Raj & Associates
Construction Division, could not be held liable qua the dues claimed by
the sub-contractor i.e., BEPL. More specifically it was contended that the
appellant could not be held liable for the dues claimed by BEPL either
under the sub-contract dated 27.05.2002 or those which arose from the
main contract dated 31.05.2001. Mr. Sharma contended that the learned
Single Judge had not addressed himself to these issues raised in the
objections filed by the appellant.
10. On a perusal of the impugned judgment in particular paragraph 26
and 27, we find that the argument of lack of authority of Mr.Vinod Goel
has been squarely addressed by the learned Single Judge. What was
perhaps not articulated before the learned Single Judge, in our view, as it
now transpires deliberately so, as to what was the legal relationship
between the appellant i.e., M/s. Dwarika Projects Pvt. Ltd. and M/s. Raj &
Associates Construction Division. Since this was not an issue raised, the
learned Single Judge in the impugned judgment accepted the arguments
made on behalf of the sub-contractor i.e., BEPL that the joint venture
entity i.e., Maharia Raj-JV having successfully bid for the contract could
not now through one of its JV partner's i.e., M/s. Raj & Associates
Construction Division seek to disown its liability. The learned Single
Judge also noted the fact, which is not disputed before us, that the
appellant chose not to appear before the Arbitral Tribunal. Therefore, this
submission made on behalf of the appellant was rejected.
11. Having perused the record, we are of the view that the learned
Single Judge has rightly rejected OMP No.163/2006 filed by the
appellant. According to us, both the objections filed by the appellant as
well as the instant appeal appears to be a gross abuse of the process of
court. The reasons of which are as follows :-
(i). In the cause title and memo of parties in the appeal filed before us, the
appellant has been described as follows :-
"M/s. Dwarika Projects Pvt. Ltd.
Formerly known as Raj & Associates ...Appellant
Versus
M/s. Bhandari Engineers & Builders Pvt. Ltd. ...Respondnet
MEMO OF PARTIES
M/s. Dwarika Projects Pvt. Ltd.
Formerly known as Raj & Associates Construction Division, Through its Director, Sh. Raj Kishore Verma, Maharia-Raj (JV), B-7, Sector-36, Noida - UP ...Appellant
Vs.
M/s. Bhandari Engineers & Builders Pvt. Ltd.
83, Bhandari House, 91, Nehru Place,
New Delhi. ...Respondent"
12. It was not the submission of Mr. Sharma that M/s. Raj &
Associates Construction Division has ceased to exist. We had specifically
put to Mr. Sharma as to whether it was case of change of name, or
amalgamation or takeover. Mr. Sahrma's answers seemed to suggest that
none of circumstances had arisen. Therefore, the description of the
appellant that it was formerly known as M/s. Raj & Associates
Construction Division could not be understood. Undoubtedly, the joint
venture entity i.e., Maharia Raj-JV had preferred objections under section
34 of the Act vide OMP No.220/2006, therefore, it is not understood as to
how the appellant, which has been unable to explain its legal relationship
with one of the constituent partners', i.e., M/s. Raj & Associates
Construction Division could maintain either objections under section 34
of the Act or the present appeal. The learned Single Judge appears to
have taken the cause title/memo of parties on its face value and
accordingly, dealt with the submissions raised as regards the lack of
authority of Mr.Vinod Goel to enter into the main contract dated
31.05.2001 or the sub-contract dated 27.05.2002. In our opinion, there is
a deliberate obfuscation of this vital fact. The inability of the counsel to
assist us in this regard appears to be contrived.
13. Apart from the above, we agree with the conclusion of the learned
Single Judge if, it is assumed (as the learned Judge appears to have
accepted) that the appellant and M/s. Raj & Associates Construction
Division is the same entity; that the sub-contractor could not have known
as to what was the limitation on the authority of Mr.Vinod Goel, as it was
dealing with the joint venture entity i.e., M/s. Maharia Raj-JV. The
purported lack of authority, if any, fell within the domain of the "indoor
management" of the joint venture entity i.e., M/s. Maharia Raj-JV. The
joint venture entity by its very conduct demonstrated to the world at large,
including the sub-contractor (i.e., BEPL) that it had the authority to
execute both the main contract dated 31.01.2001 with NHAI, and the sub-
contract dated 27.05.2002 with BEPL. As noted by the learned Single
Judge, what makes matter worse for the appellant is that it chose not to
appear before the Arbitral Tribunal. To our minds, this folly is
compounded by the fact that a specific ground has been taken in the
appeal that the Arbitral Tribunal ought to have perused the record on its
own and come to a conclusion in its favour. We are unable to accept the
stand taken by the appellant in this regard. An Arbitrator is not blessed
with prescience so as to be in a position to anticipate the submission that a
litigant would make based on the documents on record. A party which
chose not to appear does so at its own peril.
14. We are thus of the view that the appeal deserves to be dismissed
with exemplary costs but we desist from doing so as none appears for the
respondent. Before we conclude, we may place on record that no other
submission was raised before us by the learned counsel for the appellant.
SANJAY KISHAN KAUL,J
RAJIV SHAKDHER, J JANUARY 04, 2012 yg
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!