Citation : 2012 Latest Caselaw 1077 Del
Judgement Date : 16 February, 2012
IN THE HIGH COURT OF DELHI AT NEW DELHI
O.M.P. 482/2009
Reserved on: December 14, 2011
Decision on: February 16, 2012
M/S NATIONAL HIGHWAYS
AUTHORITY OF INDIA ..... Petitioner
Through: Mr. Yaman Kumar, Advocate.
versus
M/S TANTIA-TBL (JV) ..... Respondent
Through: Mr. George Thomas with
Mr. Amit George, Advocates.
CORAM: JUSTICE S. MURALIDHAR
JUDGMENT
16.02.2012
1. The Petitioner, National Highways Authority of India ('NHAI'), in this
petition under Section 34 of the Arbitration and Conciliation Act, 1996
('Act'), challenges an Award dated 5th May 2009 passed by the Arbitral
Tribunal ('Tribunal') arising out of the disputes between the Petitioner and
the Respondent M/s. Tantia-TBL (JV) pertaining to the contract for the
work of four laning of km 332.600 to km 316.00 (Aluva-Angamaly section)
of NH-47 in the State of Kerala (Contract Package No. NS-28/KL). The
contract dated 14th June 2001 was entered into between the NHAI and the
Respondent for the contract price of Rs. 66,45,73,827/-. The date of
commencement was 31st August 2001 and the intended date of completion
was 30th August 2003. The first extension of intended completion date
granted by the NHAI was up to 30th April 2004 and the second extension
was granted up to 31st May 2004 which is the actual date of completion.
The NHAI took over the project on 7th August 2004. The defect liability
completion certificate was issued on 7th February 2006. The contract price
was increased to Rs. 71,40,52,826/- (by 7.45%). M/s. Sai Consulting
Engineers Private Limited [formerly known as Sheladia Associates &
Consultants (India) Private Limited] was appointed by the NHAI as the
"Engineer" for the project in terms of the contract.
2. In terms of Clause 24.1 of the contract if the contractor believes that a
decision taken by the Engineer was either outside the authority or was
wrongly taken, the decision will be, at the first instance, referred to a
Dispute Review Expert ('DRE'). The decision of the DRE is final and
binding if neither party referred the dispute for arbitration under Clause
25.2.
3. The disputes between the parties were referred by the contractor to the
DRE by its letter dated 9th November 2005. However, the DRE by its letter
dated 24th November 2005 communicated its inability to adjudicate the
matter as the tenure of the DRE had come to an end and the NHAI had not
extended it. The Respondent contractor then referred the disputes to the
Tribunal in terms of Clause 25.
4. A preliminary objection raised before the Tribunal by the NHAI was that
the Respondent ought to have approached the Indian Road Congress
('IRC') under Clause 26.1 for designating another DRE. The Tribunal
observed that contingencies envisaged under Clause 26.1 of the contract,
i.e., resignation/death of the DRE or failure to fulfill its functions, were not
attracted. The DRE was willing to continue however the NHAI did not
extend its tenure.
5. Mr. Yaman Kumar, learned counsel appearing for the NHAI reiterated
the same objection that the Respondent was under obligation in terms of
Clause 26.1 to approach the IRC. He further submitted that merely because
the NHAI at that stage did not object to the appointment of the Tribunal it
could not be held to have waived its objection.
6. This Court is unable to appreciate the above submission. Clause 26.1 was
clearly not attracted in the instant case. The DRE did not show its
unwillingness to act. The DRE in fact, by its letter dated 24th November
2005, pointed out that it was unable to continue due to expiry of its term as
DRE. The NHAI was expected to extend its tenure, which it failed to do. In
the circumstances, the Respondent was justified in approaching the
Tribunal. The objection as regards the jurisdiction raised by the NHAI has
been correctly rejected by the Tribunal.
7. There were 15 items of claims filed by the Respondent before the
Tribunal. During the course of oral submissions before the Tribunal, the
Respondent withdrew four claims, i.e., Claim Nos. 7, 8, 12 and 14, thus
leaving 11 claims for adjudication by the Tribunal. Out of these 11 claims,
Claim Nos. 1, 2, 4, 6, 9, 10 and 15 were allowed in favour of the
Respondent whereas Claim Nos. 3, 5, 11 and 13 were rejected. To the
extent that seven of the claims made by the Respondent were allowed by
the impugned Award dated 5th May 2009 of the Tribunal, the present
petition has been filed by the NHAI.
8. Claim No. 1 is for loss suffered due to idling and under utilization of
machinery and equipments on account of compensation events. The claim
is for a sum of Rs. 5,24,12,282/- where the Tribunal awarded Rs.
2,62,01,141/-. Although the claim as regards idling of machinery of the
Respondent was for a period of fifteen months, the Tribunal allowed it for
eight months.
9. The case of the Petitioner is that the Respondent was also responsible for
the delay in completion of the contract and it had not carried out the work
in terms of the Work Programme as envisaged in Clause 27 of the contract.
It is submitted that Clause 44.1 (g) should not be read to include ordering of
variations as a compensation event. Secondly, the Tribunal had accepted
the basis of computation as given by the Respondent without going into the
veracity of the details mentioned in the cross reference of the said
document. Thirdly, there was no finding with regard to the documents
produced by the Respondent. Reliance is placed on the decision of this
Court in Delhi Development Authority v. Sunder Lal Khatri & Sons
(2009)1 Arb LR 240 (Del) (DB).
10. Countering the above submissions, Mr. George Thomas, learned
counsel for the Respondent pointed out that the monthly progress report of
the NHAI itself acknowledged the equipments deployed at the site and the
cost of machinery deployed. There was no objection raised as regards the
quantification placed on the value of the machinery by the Respondent
before the Tribunal. Apart from filing its evidence by way of affidavit, the
Respondent also demonstrated that the compensation was worked out not
on the basis of owning cost method but by adopting the formula fixed by
the Ministry of Surface Transport ('MOST'), Government of India.
Reliance is placed on the decision in Anant Raj Agencies v. Delhi
Development Authority 91 (2001) DLT 273.
11. It is seen that the Respondent had before the Tribunal limited the
number of months of extended deployment to the extent of documentary
proof available in the exhibits. The Respondent also restricted the number
of months of extended deployment for the Bituminous Concrete
Equipments. The Respondent placed before the Tribunal copies of progress
reports and invoices showing the total investments on all the machines. The
Tribunal has, in paras 21 to 39, analysed the relevant provisions of the
contract in this regard. It was noticed that Clause 44 of the Contract
stipulated that certain events were 'compensation events' unless they were
caused by the contractor. The Engineer was empowered under the said
provision to assess 'compensation events'. Clause 44.1 (g) qualified
variation as a 'compensation event'. Clause 40.4 of the GCC also permitted
variation to be treated as a 'compensation event'. The Engineer has, in the
present case, certified 365 days of compensation events. The documents on
record before the Tribunal showed that 'early warning' notices had been
issued by the Respondent to the NHAI and while seeking extension of time
the Respondent had notified such 'compensation events'. In the
circumstances, the Tribunal held that the Respondent herein has not
committed a breach of contract and the certificate issued by the Engineer
regarding compensation events was after being satisfied that there was no
breach of contract on the part of the Respondent. Further, the
'compensation events' were not considered in the price adjustment payment
or Clause 47 debarring the contractor from claiming additional cost for
'compensation events'.
12. The criticism of learned counsel for the NHAI to the impugned Award
as regards Claim No. 1 is not justified. The Tribunal analysed the
documents and the evidence placed on record and concluded that the delay
was attributable to NHAI. It was not reasonable to contend that since some
stretches were handed over, the Respondent ought to have completed the
work on those stretches. In para 37 of the Award the Tribunal held as
under:
"37. From the facts which have come on record, it is clear that claimant was asked to stop work on the above stretches by the Respondent on 17th November 2001 (Ex. C-5) and again vide letter dated 29th November 2001 (Ex. C-6). Claimant was asked to start the work on the same stretches. Once again vide letter dated 17th January 2002 (Ex.C-9) claimant was asked to stop work from 316.000 km to 319.000 km. Respondent was contemplating to provide elevated highway for Angamali Town portion. Matter did not end here. Respondent again vide letter dated 22nd March 2002 (Ex.C-10) asked the claimant to proceed with work on this stretch. Therefore, it is apparent that work of the complainant got prolonged because of indecisiveness on the part of the Respondent. It would be wrong on the part of the Respondent to contend that this indecisiveness of such stoppage of work did not actually cause any loss or damage to the claimant. The Engineer has admitted that the claimant brought machinery and equipments at site as per the programme and if that machinery could not be utilized because of indecisiveness of the Respondent claimant had obviously suffered loss."
13. This Court is unable to be persuaded to interfere with the finding of the
learned Tribunal as regards Claim No. 1.
14. Claim No. 2 was for infrastructure overhead expenses suffered on
account of compensation events which resulted in prolongation of the
contract. As against the claim of Rs. 1,83,93,690/- the Tribunal awarded to
the Respondent a sum of Rs. 1,38,86,131/-. The Respondent claimed
expenses for 9 months but the Tribunal reduced it to 8 months.
15. The criticism of learned counsel for the NHAI that the Respondent did
not substantiate it claim by producing the accounts book does not appear to
be justified. Since the delay was held to be on the part of NHAI, it was
held that the Respondent was not entitled to infrastructure overhead
expenses on the staff and infrastructure at site as well as at the Head Office.
The said decision of the Tribunal cannot be said to be contrary to law or to
the contractual provisions.
16. Claim No. 4 pertained to the loss suffered on account of financial
charges and insurance in the prolonged period of execution of completion
of work. As against the claim of Rs. 37,06,084/- the Tribunal awarded Rs.
32,11,242/-. The Tribunal noted that the Respondent admittedly extended
the bank guarantee for the additional period of execution and completion of
the work. Since the Respondent was required to keep the bank guarantee
alive till the end of the defect liability period, it would be entitled to extra
costs incurred on that score. The Respondent had set out the details of
expenses incurred in Annexure CA-4. However, the Tribunal, in the
absence of documentary evidence, disallowed the claim for financial
charges and reduced the amount. Its findings were based on an appreciation
of evidence.
17. Claim No. 6 was for losses incurred on account of variation and change
in specification of DBM (BOQ Item No. 4.04). The objection of learned
counsel for the Petitioner is that the said claim was barred by limitation and
also barred by the principle of constructive res judicata. A similar plea was
rejected by the Tribunal. The present claim was not covered by the earlier
arbitral Award dated 27th December 2004. It was for a subsequent period. It
is seen from the record that the Respondent submitted its rate to the NHAI
on 26th April 2003 in terms of Clause 38 of the contract. However, the
NHAI failed to submit any counter rate analysis. The NHAI also did not
challenge the rate analysis submitted by the Respondent. It is not in dispute
that reduction of work was more than 25% and more than 1% of BOQ
rates. Since the claim of the Respondent was to be paid unit rate wise units
got reduced as a result thereof. Further, no decision had been taken by the
Engineer. Therefore, Clause 40.2 was not attracted. The Engineer did not
find the quotation submitted by the Respondent to be unreasonable or
excessive. In the circumstances, no fault can be found with the impugned
Award as regards Claim No. 6.
18. Claim No. 9 pertained to compensation due to reduction in length of the
road and deletion of bridge from the original scope of work. Against the
claim of Rs. 2,80,33,280/- the Tribunal awarded in favour of the
Respondent a sum of Rs. 88,06,715/-. There was adequate evidence
produced by the Respondent which has been analysed by the Tribunal
which found that out of the total length the work reduced, 15% work was
over. The work of the bridge was also reduced from both sides. Since the
deletion of work was not covered under Clause 40 of the contract, the
Respondent was entitled to damages under Section 73 of the Contract Act.
The Tribunal held that the Respondent was entitled only to BOQ rates and
not damages. The decision as regards Claim No. 9 was based on
appreciation of evidence and cannot be held to be contrary to law.
19. Claim No. 10 was for compensation for loss suffered due to changes in
design of Mangalapuzha bridge. A perusal of the impugned Award shows
that due to the order of the High Court, the elevated portion on the Trichur
side had to be retained. Consequently, the Engineer decided to increase the
proposed road level by three meters. This change led to change of
methodology for the construction of Mangalapuzha bridge. The Respondent
had to procure steel, fabricate and erect the spans for supporting girder
leading to additional expenditure. The Respondent was compelled to do the
construction of girders in all the three spans as cast-in-cast type of
construction. The Tribunal held that the NHAI was held to be responsible
for change in the design that resulted in additional costs. It also held that
the NHAI had not denied the additional cost incurred by the Respondent.
Again the decision is based on an appreciation of evidence and cannot be
said to be perverse or illegal.
20. As regards Claim No. 15, the award of interest @ 12% per annum
cannot be held to be unreasonable or arbitrary. The law in this regard has
been explained by the Supreme Court in State of Rajasthan v. M/s. Ferro
Concrete Construction 2009 (3) Arb LR 140 SC.
21. No grounds have been made out for interference with the impugned
Award dated 5th May 2009 of the Tribunal. The petition is dismissed with
costs of Rs. 10,000/- which will be paid by the Petitioner to the Respondent
within a period of four weeks.
FEBRUARY 16, 2012 S. MURALIDHAR, J. RK
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!