Citation : 2011 Latest Caselaw 4774 Del
Judgement Date : 26 September, 2011
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ FAO No.120/2001
% 26th September, 2011
M/S. INDIAN HUME PIPE CO. LTD. ...... Appellant
Through: Mr. S.S. Ray, Advocate with
Mr. Rajan Tyagi, Advocate.
VERSUS
REGIONAL DIRECTOR, E.S.I.C. & ANR. ...... Respondents
Through: Mr.K. P. Mavi, Advocate.
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be allowed to see the judgment?
2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in the Digest?
VALMIKI J. MEHTA, J (ORAL)
1. The challenge by means of this First Appeal under Section
82 of the Employees‟ State Insurance Act, 1948 (hereinafter referred to
as „the Act‟) is to the impugned order of the ESI Court dated 8.12.2000
which dismissed the petition filed by the appellant herein under Section
75 of the Act.
2. The facts of the case are that the appellant is engaged in
the manufacture of large size pipes. The appellant was sent a notice
dated 24.11.1986 demanding payment of Rs.97,224.30/- for laying work
of the pipes. The appellant made a representation against the notice of
demand and produced certain documents whereafter the demand was
reduced from Rs.97,224.30/- to 12,207.65/- vide order dated 9.3.1987.
It was also held that no interest was payable by the appellant. The
appellant made a representation dated 9.4.1987 against the said
demand of Rs.12,207.65/- and followed it up by another representation
dated 30.4.1987. On account of the failure of the appellant to pay the
amount due, intimation was sent by the respondents to the Collector to
recover the subject demand alongwith interest.
3. The appellant challenged this action of the respondents by
means of filing of the subject petition under Section 75 of the Act. What
was contended on behalf of the appellant before the ESI Court was that
the work of laying of pipes was not the work of the appellant but was
the work of an independent contractor and which work therefore cannot
be said to be within the scope of the activities of the appellant and
accordingly for employees engaged in such work ESI contribution was
not to be paid.
4. After pleadings were complete, the ESI Court framed issues
and the main issue was issue No.2 as to the validity of the demand
raised.
5. In this regard, the ESI Court by the impugned judgment has
held that the appellant failed to file the necessary documents and show
that the work of laying of pipes was not given to the appellant but was
given to an independent contractor. The ESI Court found that the
specialized nature of the work was such that the work could not have
been done by an independent contractor. The ESI Court also referred to
the fact that if there was an independent contractor, the appellant
would have examined that independent contractor or the witnesses
from the Municipal Corporation of Delhi (for whom the work of laying the
pipes was done) to show that the work was done by an independent
contractor and not the appellant, however the same was not done.
Accordingly, ESI Court held that the work of laying of pipes was within
the scope of the activities of the appellant and therefore ESI
contribution was payable. The relevant observations of the Court below
in which the necessary findings and conclusions in this regard are given
in paras 16 and 17 which read as under:-
"16. It is clear from the discussion that an employer is liable to pay the contribution in respect of activities which form an integral part of its activities and are carried on under the supervision of the employer and the employer has no liability to pay the contributions in respect of work carried out by the independent contractors, or in respect of an activity which does not form an integral part of its activities.
17. In the instant case, it is the case of the petitioner that its main activity is pipe manufacturing. The pipes are heavy in weight and bulky in size. The laying work is not part and parcel of its manufacturing activity. The work was done far away from the factory at a site of M.C.D. However, the petitioner has not placed on the record any agreement to the effect that pipes would be laid by it at the site of M.C.D. When the pipes were laid at a site of MCD, which is a govt. body, the work could not have been done on oral request. There must have been some written agreement which the petitioner has failed to produce on the record. Secondly, it is the case of the petitioner that pipes are heavy in weight and are bulky in size. The natural consequences of this is that any ordinary person which includes a company also cannot lay them. Some specific qualifications must be required which only a person having some experience of the work can do. On the facts of the instant case, the petitioner is the best person to possess such experience. That is why they were called upon by the MCD to lay the pipes. A company which does not have specific expertise in laying
such heavy pipes cannot be called upon by any person including the MCD to lay the pipes when it is not sure of the expertise possessed by the laying company. Thirdly, no witness has been examined from the MCD Deptt. to say that the pipes were laid by independent contractors for them and not by the petitioner-company. Fourthly, no independent contractor has been examined in the witness box. Fifthly, from the document Ex.PA, which gives a record of the laying work, all the details have been mentioned. If the work was carried out by an independent contractor, there was no need for the petitioner to maintain such details record as it would have been suffice for them to maintain a record of the payments made by them. Sixthly, PW-1 Mr. G.K. Giotra has admitted in the cross-examination that he has not produced the ledger regarding the persons from whom they got the work done and there is no agreement in this regard. He took the excuse that they cannot produce the record as the matter is quite old. The excuse cannot be accepted. For these reasons, I do not agree with the petitioner that the pipe laying work is not an integral part of the work of the petitioner-company. The principal work of the company might be pipe manufacturing but on the facts of the instant case, they have failed to show that laying work was independent and separable work and was not an integral work connected with the work of the petitioner-company. As such, the authorities cited above by the ld. counsel for the petitioner showing the meaning of „factory‟ and the law regarding contract site are not applicable to the facts of the present case." (underlining added)
6. I do not find any illegality whatsoever in the aforesaid
findings and conclusions of the Court below. The appellant was guilty of
deliberately concealing documents and deliberately not leading the
necessary evidence. The ESI Court has therefore rightly held that the
work in question i.e. laying of pipes was very much part and parcel of
the activities of the appellant, and therefore, appellant was liable to pay
the ESI contribution with respect to the employees who did this work.
7. I may note that an appeal under Section 82 of the Act is
only entertained if there arises a substantial question of law. The
finding of facts contained in para 17 of the impugned judgment does
not raise any substantial question of law. There is therefore no merit in
the argument raising any substantial question of law with respect to the
finding of coverage of the appellant under the Act for contribution to be
made with respect to the employees for the work of laying out of the
pipes.
8. Learned counsel for the appellant firstly sought to argue
that the provision of Section 45A of the Act did not apply. Firstly, I find
that there is no reference to such an issue having been argued before
the Court below at the time of final argument inasmuch there is no
discussion whatsoever with respect to this issue in the impugned
judgment. Obviously, this point must have been given up and therefore
not argued. If really this point was argued and not pronounced upon it
was incumbent upon the appellant to immediately approach the ESI
Court after the impugned order was passed to bring to the notice of the
Court below that such a point was argued but was not pronounced
upon. Admittedly, this was not done and in fact no such application was
ever filed. Therefore, in accordance with the ratio of the judgment in
the case of State of Maharashtra Vs. Ramdas Srinivas Naik AIR
(1982) 2 SCC 463 I hold that the appellant ought not to be permitted
to raise this point in the appeal having given up the same before the ESI
Court. In any case, even on merits, I do not find any strength in this
argument because the original order which was passed by the
concerned authority was pursuant to the notice dated 24.11.1986,
which resulted in passing of an order reducing the demand from
Rs.97,224.30/- to Rs.12,207.65/-. The demand was therefore raised
after following the due procedure of law and which having not been paid
action was taken to recover the amount through the Collector.
9. The second point which was argued was that the concerned
authority which passed the impugned order was not a competent
authority. It was argued that the order was passed in the year 1987
and the notification which is relied upon by the Court below is of
29.7.1991. It is argued that an Assistant Regional Director has no
authority to pass an order. In my opinion, such hyper technical points
do not raise a substantial question of law. In the facts of the present
case for the appeal to be entertained under Section 82, considering that
existence of a substantial question of law is a sine qua non for
entertaining the appeal, I reject this technical argument urged on behalf
of the appellant.
10. The final argument as raised on behalf of the appellant was
that the demand in question pertained to the period from 1968 to 1971
and therefore the impugned demand raised in the year 1986 is barred
by limitation. Counsel for the appellant however agrees that no period
of limitation was provided under the Act during the relevant period of
time. Once that is so, I fail to understand as to how the ground of
limitation can be urged, more so when the appellant itself is guilty of
deliberately concealing facts and not producing the relevant record
before the ESI Court.
11. In view of the above, I find that there is no merit in the
appeal, which is accordingly dismissed, leaving the parties to bear their
own costs.
SEPTEMBER 26, 2011 VALMIKI J. MEHTA, J. Ne
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!