Citation : 2011 Latest Caselaw 4566 Del
Judgement Date : 16 September, 2011
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ RFA No.236/2001
% 16th September, 2011
DELHI CANTT. BOARD ...... Appellant
Through: Mr. Sunil Satyarthi, Adv.
VERSUS
M/S. QUARTS CONTROL COMMUNICATION & SYSTEM
...... Respondent
Through: Mr. R.K.Sharma, Adv.
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be
allowed to see the judgment?
2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in the Digest?
VALMIKI J. MEHTA, J (ORAL)
1. The challenge by means of this First Appeal under Section
39 of the Arbitration and Conciliation Act, 1940 is to the impugned order
of the Court below dated 8.3.2001 which dismissed objections of the
appellant herein filed under Section 30 and 33 of the Act to the Award.
2. The disputes between the parties pertain to work orders
awarded to the respondent by the appellant pertaining to repairs of
electrification of different CF properties and for which purpose a
contract was entered into between the parties on 20.7.1987. On
RFA No.236/2001 Page 1 of 6
disputes and differences having arisen, the respondent invoked
arbitration proceedings and filed its claims before the Arbitrator who
published his Award dated 27.5.98, awarding certain claims.
3. The dispute between the parties so far as the present
appeal is concerned, pertains to claim nos. 2, 3 and 4.
4. Claim no.2 was the claim for payment with respect to the
value of work done under work order no.5(ii). The respondent/contractor
claimed a sum of Rs.22,594.35 against the original quotation of
Rs.16,000/-. The work was actually done for which the bill was
submitted as per measurement for Rs.22,594.35. The defence of the
appellant was that the work was defective and therefore payment was
not to be made to the respondent. In this regard, the Arbitrator has
observed that he directed the appellant to produce the list of specific
defects/incomplete work and the concerned measurement book/site
order book, but the same were not produced. The Arbitrator therefore
held that since the appellant could not produce any document to prove
that the defects existed and work was done by any other agency, an
amount of Rs.21,000/- was awarded to the respondent. The Arbitrator
has arrived at a finding of fact and unless the finding of fact is perverse,
a Court hearing objections cannot interfere with the Award. I do not find
RFA No.236/2001 Page 2 of 6
any perversity in view of the failure of the respondent to point out the
defects and also file the measurement books.
5. Claim no.3 was the claim for the balance amount of the
work done for work order no. 5(iii). The Arbitrator has observed that
total payments made against the bill amount of Rs.1,69,152.35 was
Rs.1,22,638.35, The original value of the work order was Rs.1,48,000/-.
Once again the Arbitrator while dealing with this claim has observed
that the respondent could not produce the measurement book to show
the measurements recorded and could not also prove by any
documentary evidence, alleged expenses incurred for rectifying the
defects, though the same were directed to be produced for
consideration by the Arbitrator. Considering all the facts, the Arbitrator
allowed deduction of Rs.6,000/- from the balance amount and
accordingly awarded a sum of Rs.40,514/- to the respondent. Once
again this is a finding of fact and I feel that in fact the Arbitrator has
been liberal towards the appellant because in spite of defects being not
proved, yet, a sum of Rs.6,000/- was directed to be deducted. There is
therefore no perversity in the Award with respect to this claim no.3 for
this Court to interfere with the same and that too in appeal against an
order dismissing the objections.
RFA No.236/2001 Page 3 of 6
6. Claim no.4 was the claim with respect to value of the work
order no.5(iv) for Rs.55,000/-. The original value of the work order was
Rs.52,186.36. Even with regard to this claim, the Arbitrator has noted
that the relevant measurement book was not produced stating that the
same is misplaced. The appellant also could not produce any expense
vouchers to show incurring of costs for rectifying the defects. The
Arbitrator referred to the fact that he had already allowed deduction
from claim no.3 for Rs.6,000/- and accordingly he allowed a deduction of
Rs.2,000/- with respect to claim no.4. Once again this finding of fact
need not be interfered with as there is no perversity in the same.
7. I may note that the Arbitration was conducted by the
Superintendent Engineer, who is a technical person, and such technical
persons are allowed certain leeway as they are normally conversant
with such type of works.
8. Though the impugned order does not discuss the claim as
this Court had done, I note that the impugned order refers to the fact
that a Court hearing objections does not sit in an appeal over the Award
and it is not possible to substitute the Court's evaluation for the
conclusions of the fact as arrived at by the Arbitrator. This is a correct
position of law.
RFA No.236/2001 Page 4 of 6
9. Though, the counsel for the appellant has not argued one
issue, I find that the issue of interest granted by the Award at 16% per
annum simple from 1.3.1989 is an aspect which requires interference .
The Supreme Court in its recent chain of judgments in Rajendra
Construction Co. v. Maharashtra Housing & Area Development
Authority and others, 2005 (6) SCC 678, McDermott
International Inc. v. Burn Standard Co. Ltd. and others, 2006
(11) SCC 181, Rajasthan State Road Transport Corporation v.
Indag Rubber Ltd., (2006) 7 SCC 700, Krishna Bhagya Jala
Nigam Ltd. v. G.Harischandra, 2007 (2) SCC 720 & State of
Rajasthan Vs. Ferro Concrete Construction Pvt. Ltd (2009) 3
Arb. LR 140 (SC) has mandated the Courts to reduce the high rates of
interest, accordingly, in the facts and circumstance of the case, I direct
that instead of interest at 16% per annum, interest should be awarded
at 10% per annum simple. I however clarify that since the respondent
has already been harassed and has not received the amount under the
Award which has been passed over 13 years back, accordingly, the
concession in rate of interest by reducing the interest from 16% to 10%
per annum simple will only operate, if payment under today's judgment
is made by the appellant to the respondent within a period of 3 months
from today. In case this payment is not made in this period of three
RFA No.236/2001 Page 5 of 6
months then considering that the respondent has been very patiently
waiting for payment of its amount from 1998, the interest will otherwise
continue to be 16% per annum simple as directed by the Award.
10. The appeal is accordingly disposed of in terms of the above
observations.
11. Trial Court record be sent back.
SEPTEMBER 16, 2011 VALMIKI J. MEHTA, J.
ak
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!