Citation : 2011 Latest Caselaw 1797 Del
Judgement Date : 28 March, 2011
THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment Pronounced on: 28.03.2011
+ CS(OS) No.2223/2010
M/S. CAMCO MULTI METAL LTD. .....Plaintiff
- versus -
M/S. SHARIF METALS
INTERNATIONAL LLC & ORS. .....Defendants
Advocates who appeared in this case:
For the Plaintiff: Mr. Kunwar Pal Singh, Adv.
For the Defendants: None.
CORAM:-
HON'BLE MR JUSTICE V.K. JAIN
1. Whether Reporters of local papers may No.
be allowed to see the judgment?
2. To be referred to the Reporter or not? No.
3. Whether the judgment should be reported No.
in Digest?
V.K. JAIN, J. (ORAL)
1. This is a suit for specific performance of the
agreement dated 27.01.2009 or in the alternative for
recovery of Rs.21,80,500/-. The plaintiff has also sought an
injunction restraining defendant No.3 from transferring any
amount to defendants No.1 & 2 to the extent of
Rs.21,80,500/-. The plaintiff is an Indian Company,
whereas defendant No.1 is a company incorporated in UAE.
Defendant No.1 Company is engaged in the business of sale
of aluminium scraps and defendant No.2 is stated to be its
Director. It is alleged in the plaint that defendant No.1
offered to sell 100 MT of aluminium scraps as per ISRI
Tense to the plaintiff vide offer dated 27.01.2009. The offer
was accepted by the plaintiff and purchase order dated
28.01.2009 was issued accordingly for supply of 100 MT of
aluminium scraps as per ISRI Tense at the rate of US $
1,025.00 per metric ton. The shipment was to be done by
26.02.2009. A sum of US $ 20,500 was paid as an advance
to defendant No.1 on 04.02.2009. After several reminders
from the plaintiff, defendants No.1 & 2 informed the plaintiff
company that a shipment of two containers containing
20 MT each of material had been released by them and
would be received by the plaintiff. However, the defendants
later diverted shipment to defendant No.3 - M/s. Ashirwad
Steels. Defendants No.1 & 2 thereafter demanded increased
price for the material. The plaintiff agreed to increase the
price from US$ 1025 per metric ton to US $ 1045 per metric
ton and a revised purchase order dated 18.03.2009 was
accordingly issued. Initially, the goods were to be supplied
or shipped by defendants No.1 & 2 by 25.03.2009, but, the
date of delivery was later extended to 20.04.2009 on the
request of defendants No.1 & 2. It is alleged that despite
the plaintiff increasing the price, defendants No.1 & 2 failed
to supply the goods to the plaintiff. The plaintiff has sought
a decree for specific performance directing defendants No.1
& 2 to perform the contract by supplying 100 MT of
aluminium scraps as per ISRI Tense to it, and a decree for
recovery of Rs.21,80,500/- on account of the loss suffered
by it. The plaintiff has sought permanent injunction
restraining defendant No.3 from transferring any amount to
defendants No.1 & 2 to the extent of Rs.21,80,500/-.
2. The defendants were proceeded ex-parte on
10.01.2011.
3. The plaintiff has filed the affidavit of one of its
Directors Mr. Rajkamal Saraogi by way of ex-parte evidence.
In his affidavit, Mr. Saraogi has supported, on oath, the
case set up in the plaint and has stated that the offer dated
27.01.2009 sent by defendants 1 & 2 for supply of 100 MT
of aluminium scraps as per ISRI Tense was accepted by the
plaintiff and a purchase contract dated 28.01.2009 was
accordingly placed. He has further stated that advance
amount of US $ 20,500 was paid by the plaintiff on
04.02.2009. According to him, defendants No.1 & 2,
consequent to a number of reminders from them, informed
them about shipment of two containers containing 20MT
each of the material but later diverted that material to
defendant No.3 - M/s. Ashirwad Steels. He has further
stated that on account of demand of higher price by the
defendants, they had agreed to increase the purchase price
from US $ 1025 per metric ton to US $ 1045 per metric ton.
According to him, despite efforts made by them, defendants
No.1 & 2 have failed to perform the agreed contract.
4. Ex.PW-1/2 is a letter sent by defendant No.1-
M/s.Sharif Metals International LLC to the plaintiff
company on 27.01.2009, agreeing to sell 100MT of
aluminium scraps as per ISRI Tense at the rate of US $
1025 per metric ton. The material was to be loaded from
any Middle East Port was to be discharged at CIF Nhava
Sheva Port in Mumbai. 20% of the sale consideration was
to be paid in advance and the balance was payable in cash
against the documents through Axis Bank Ltd., Statesman
House, 148 Barakhamba Road, New Delhi. Ex.PW-1/3 is
the purchase order dated 28.01.2009 placed by the plaintiff
company on defendant No.1 company, for purchase of
100MT of aluminium scraps as per ISRI Tense at the rate of
US$ 1025 per metric ton. Ex.PW-1/7 is the revised
purchase order issued by the plaintiff company on
18.03.2009. The purchase price was revised to US $ 1045
per metric ton and the date of shipment was changed to
25.03.2009 vide this document.
5. Ex.PW-1/4 is the document evidencing transfer of
US$ 20,500 by Axis Bank Ltd. to JPMORGAN CHASE BANK
N.A., New York. The document shows that the money was
transferred on its behalf from the plaintiff company to
defendant No.1 - M/s.Sharif Metals International LLC.
6. The deposition of Mr. Rajkamal Saraogi coupled
with the documents filed by the plaintiff company shows
that the plaintiff had accepted the offer made by defendant
No.1 for sale of 100MT of aluminium scraps to it on US $
201045 per metric ton and a sum of Rs.20,500/- was
transferred by the plaintiff company to defendant No.1
towards advance money. The documents produced by the
plaintiff also show that defendant No.1 failed to supply the
goods to the plaintiff despite receipt of the advance money.
7. Since this was a contract for supply of material
and the plaintiff company can be adequately compensated
in terms of money on account of the non-performance of the
contract, specific performance of the contract cannot be
directed in view of the prohibition contained in Section
14(1)(a) of Specific Relief Act, 1963 and the only remedy
available to the plaintiff is to seek damages along with
refund of the advance money paid by it to defendant No.1.
8. The advance payment amounting to US$ 20,500
was paid by the plaintiff to defendant No.1. As regards
quantum of damages, the additional affidavit of Mr.
Rajkamal Saraogi shows that in the third week of April,
2009, the rate of the goods in question was US$ 1220 per
MT. A copy of another purchase order which the plaintiff
placed on record with M/s.DUNN BROSS(U.K.) for purchase
of the same material on 17.04.2009 has been referred as
Ex.PW-1/10 in the additional affidavit though the Joint
Registrar did not mark it as exhibited document. The
document is being read in the additional affidavit as Ex.PW-
1/10. The sale contract between the plaintiff and
M/s.Dunn Bross(U.K.) shows that the plaintiff company
agreed to purchase two containers of aluminium scraps
from M/s. DUNN BROSS(U.K.) at the rate of US $ 1220 per
MT.
I see no reason to disbelieve the additional affidavit
filed by Mr. Rajkamal Saraogi coupled with the document
evidencing the purchase contract between the plaintiff
company and M/s. Dunn Bross(U.K.) and, therefore, hold
that the price of the material which defendant No.1 had
agreed to sell to the plaintiff company was US$ 1220 per
MT, on the date defendant No.1 committed breach of the
contract with the plaintiff company by not supplying the
contracted material. The amount of damages, therefore,
comes to US $ 17500/-. The plaintiff is entitled to recover
US $ 20,500/- being the advance paid by it to defendant
No.1 and US $ 17,500 towards damages making a total sum
of US $ 38,000/-. The additional affidavit of Mr. Rajkamal
Saraoji also shows that the rate of US $ on 17.04.2009 was
Rs.50.180. The amount which the plaintiff can recover from
defendant No.1 as principal sum therefore comes to
Rs.19,06,840/-.
9. The plaintiff has also claimed a sum of
Rs.2,51,000/- as interest for the pre-suit period at the rate
of 15% per annum. Admittedly, there is no agreement
between the parties for payment of interest. No usage of
trade for payment of interest has been either pleaded or
proved. However, under Section 3 of Interest Act, 1978, the
Court can award interest at a rate not exceeding the current
rate of interest from the date mentioned in the written
notice given by the plaintiff to defendant No.1 provided,
claim for the interest has been made in the notice. A
perusal of the legal notice sent by the plaintiff to defendant
No.1 on June 2, 2010 which is Ex.PW-1/9 would show that
the plaintiff had claimed amount of US$ 20,500 which it
had paid as to defendant No.1 along with interest thereon at
the rate of 15% per annum, from the date of the payment.
Though the plaintiff also claimed US$ 70,000 towards
damages, there was no demand of interest on the damages.
I, therefore, hold that the plaintiff can be awarded interest
only on the amount of US$ 20,500 which it had paid as
advance money to defendant No.1. The amount of advance
money in Indian currency comes to Rs.10,28,690/-. Under
the facts and circumstances of the case, I award interest to
the plaintiff at the rate of 12% per annum from the date of
payment, on the aforesaid amount. The interest on the
aforesaid amount till the date of filing of this suit comes to
Rs.205053/-. The plaintiff is entitled to recover that
amount from defendant No.1 as interest.
10. For the reasons given in the preceding paragraph,
the decree for Rs.21,11,893/- with proportionate cost,
and pendente lite and future interest at the rate of 10% per
annum is hereby passed against defendant No.1.
11. Defendant No.2 who is director of defendant No.1
is not personally liable for the amount which defendant
No.1 company is required to pay to the plaintiff company
and is in fact an unnecessary party to the suit. The name of
defendant No.2 is, therefore, struck off from the array of
defendants. As against defendant No.3, the case of the
plaintiff is that this company is to make payment to
defendant No.1 for the material which defendant No.1 has
supplied to it. The plaintiff wants an injunction restraining
defendant No.3 from making any payment to defendant
No.1, to the extent of the decretal amount. However, there
being no privity of contract between the plaintiff and
defendant No.3 and the plaintiff company having no legal
right to claim any amount from defendant No.3, the decree
sought by it against defendant No.3 cannot be passed. The
appropriate remedy for the plaintiff company is to seek
execution of the decree which is being passed against
defendant No.1 and in the execution of that decree, it would
be open to plaintiff company to seek attachment of the
amount, if any, payable by defendant No.3 to defendant
No.1. Decree sheet be drawn accordingly.
(V.K. JAIN) JUDGE
MARCH 28, 2011 'sn'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!