Citation : 2011 Latest Caselaw 1791 Del
Judgement Date : 28 March, 2011
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ Date of Decision: 28.03.2011
% O.M.P. 623/2009
MUNICIPAL CORPORATION OF DELHI (MCD) ..... Petitioner
Through: Ms. Mini Pushkarna, Advocate
versus
NARESH KUMAR GUPTA &
COMPANY PVT. LTD. B+ ..... Respondent
Through: Mr. S.C. Singhal, Advocate
CORAM:
HON'BLE MR. JUSTICE VIPIN SANGHI
1. Whether the Reporters of local papers may
be allowed to see the judgment? : NO
2. To be referred to Reporter or not? : YES
3. Whether the judgment should be reported
in the Digest? : YES
VIPIN SANGHI, J. (Oral)
1. The petitioner, MCD has filed this petition under section 34 of
the Arbitration and Conciliation Act to assail the arbitral award dated
16.06.2009 passed by Shri Prem Kumar, the learned arbitrator,
whereby he has allowed claims no.1 (for refund of earnest money),
claim no.2 (for compensation of account of loss of profit due to breach
of contract), claim no.4 (towards interest), and claim no.6 (towards the
arbitration costs), amounting to ` 34,24,384/-. The learned arbitrator
has also awarded the amount of stamp duty, i.e. ` 3424/-. He has
further granted interest on ` 34,27,808/- @ 9% p.a. from the date of
the award till realization.
2. The respondent/contractor was awarded the work for
construction of pucca school building of MC primary school at New
Ashok Nagar, in AC-37/67 in Shahdara South, Delhi vide letter dated
11.03.2004. While the estimated cost put to tender was
Rs.2,49,14,000/-, the amount tendered by the respondent contractor,
and accepted by the petitioner was Rs.2,25,92,552/-. The respondent
was called upon to start the work at once. It was stated that the time
allowed to carry out the work shall be reckoned from tenth day of issue
of the work order to commence the work.
3. In the Notice Inviting Tender (NIT) issued by the petitioner,
clause 3 provided that the time allowed will be 24 months from the
tenth day after the date of written orders to commence the work, or
from the first day of handing over of the site, whichever is later, in
accordance with the phasing, if any, indicated in the tender
documents. Clause 4 of the NIT provided that the site will be fully
made available at the time of the work order.
4. The "Clauses of Contract", inter alia, prescribed in clause 5
the "Time and Extension for Delay". The same reads as follows:
"Clause 5
Time and Extension for Delay
The time allowed for execution of the works as specified in the Schedule 'F' or the extended time in accordance with these conditions shall be the essence of the Contract. The execution of the works shall commence from the 15th day or such time period as mentioned in Letter of Award after the date on which the Engineer-in- Charge issues written orders to commence the work of (or) sic from the date of handing over of the site whichever is later. If the Contractor commits default in commencing the execution of the work as aforesaid, Government shall without prejudice to any other right or remedy available in law, be at liberty to forfeit the earnest money absolutely". (emphasis supplied)
5. Clause 10C and 10CC provided for payment on account of
increase in prices/wages due to statutory order, and payment due to
increase/decrease in prices/wages after receipt of tender for works.
6. The work involved dismantling of the existing structures and cost
of the salvage was put at ` 1,70,626/-, which the respondent was
required to deposit. Vide communication dated 16.04.2004, the
petitioner called upon the respondent to execute the agreement within
three days and also to deposit the amount of ` 1,70,626/- as shown in
Part B of the work order before dismantling the old structure.
7. Undisputedly, the respondent contractor did not carry out any
work under the contract. Neither the contract document was signed;
nor the demolition work was carried out. The cost of salvage was also
not deposited. According to the respondent, the said cost was not
required to be deposited, and the same had to be adjusted from the
bills as and when raised by the respondent. The petitioner issued
various communications to the respondent to execute the contract
document and commence the works. The stand of the respondent was
that the work site was not made available in full, and the drawings
were not given to him. Eventually, the petitioner issued an show cause
notice dated 11.01.2005 and rescinded the contract on 04.02.2005.
8. The case of the petitioner before the arbitral tribunal was that
the respondent did not take any steps whatsoever in pursuance of the
award of work to execute the work. Neither the contract was executed
nor the amount of ` 1,70,626/- was deposited towards the salvage cost
before taking up the demolition work, nor the construction work was
carried out. On the other hand, the case of the respondent was that
the site was not made available to the respondent as there was a
running school and classes were going on. The said school was also
designated as an election centre. The respondent also contended that
the working drawings were not made available by the petitioner.
9. The respondent raised its claims, as aforesaid, for ` 1 lakh on
account of refund of earnest money; ` 24,91,400/- on account of loss of
profit due to breach of contract by the petitioner being 10% of the
value of the estimated value of the work; ` 15 lacs due to staff
remaining idle, establishment from T and P, shuttering and also mental
agony and goodwill on account of breach of contract by the petitioner,
interest @ 18%; and ` 1 lakh as arbitration costs. The petitioner, MCD
also raised its counter claims, inter alia, towards the cost of work
carried out by calling fresh tenders at the risk and costs of the
respondent, interest, and cost of arbitration.
10. The learned arbitrator returned a finding that it was the duty of
the petitioner to provide the complete work site in one go to the
respondent, to start the work. On account of the inability of the
petitioner to provide the same for various reasons, the respondent
could not be faulted for not starting the work at the site. The learned
arbitrator held that the recession of the contract after issuance of show
cause notice dated 11.01.2005 was not competent, and so was the
recession of the contract vide letter dated 04.02.2005 incompetent.
Consequently, the learned arbitrator held that the petitioner could not
forfeit the respondents security deposit of ` 1 lakh. The learned
arbitrator, by placing reliance on the various decisions, including the
decision in M/s. A.T. Brij Paul Singh & Bros. v. State of Gujarat; AIR
1984 SC 1703, held that the respondent was entitled to 10% of the
estimated cost put to tender as compensation for loss of profit, and
consequently awarded an amount of ` 24,91,100/-.
11. Claim no.3 made by the respondent for ` 15 lacs, as aforesaid,
was however rejected on the ground that the respondent had failed to
adduce any relevant or cogent evidence in support of the said claim.
12. Under claim no.4, the learned arbitrator awarded interest @ 9%
p.a. The pendente lite interest from March 2006 upto June 2009 on the
amount of ` 25,91,400/- was quantified at ` 7,57,984/- and awarded in
favour of the respondent. He also awarded ` 75,000/- towards
arbitration fee in favour of the respondent. All the counter claims of
the petitioner were rejected on the ground that the petitioner was
responsible for breach of the contract.
13. The submission of learned counsel for the petitioner is that
though the work site was not made fully available to the respondent
initially, the same was made fully available in December 2004. She
places reliance on the letter dated 23.12.2004 issued by the MCD to
the respondent, which recorded that "Now, it is to inform you that full
site is available for start of work". The respondent was requested to
start the work within seven days from the issue of letter, failing which
action as deemed fit would be initiated.
14. The respondent responded to this letter vide letter dated
12.01.2005. The respondent did not deny the fact that that the full site
was then available. It was stated by the respondent "You have now
admitted and confirmed vide your letter under reference that part site
was available in Aug. 2004 and the full site is available now to start the
work. We have already clarified about the availability of part site and
the work could not be started as intimated through our various
references as referred to above". In this communication, the
respondent sought increase of the rates by 30% to carry out the work
by quoting rates of materials such as cement, steel and bricks at the
time of tendering in October 2003, and the rates prevalent in August
2004.
15. It is evident from the reading of the award, and it is not disputed
that these two vital communications have not even been considered by
the learned arbitrator while returning the finding that the complete
work site was never made available to the respondent/contractor. The
finding returned by the learned arbitrator with regard to the full site
being not made available is in the teeth of the aforesaid two
communications.
16. The Supreme Court, in State of Rajasthan v. Puri
Construction Co. Ltd. & Anr., (1994) 6 SCC 485 has held as follows:
"In recent times, error in law and fact in basing an award has not given the wide immunity as enjoyed earlier, by expanding the import and implication of legal misconduct' of an arbitrator so that award by the arbitrator does not perpetrate gross miscarriage of justice and the same is not reduced to mockery of a fair decisions of the lis between the parties to arbitration. Precisely for the aforesaid reasons, the erroneous application of law constituting the very basis of the award and improper and incorrect findings of fact, which without closer and intrinsic scrutiny, are demonstrable on the face of the materials on record, have been held, very rightly, as legal misconduct rendering the award as invalid. It is necessary, however, to put a not of caution that in the anxiety to render justice to the party to arbitration, the court should not reappraise the evidence intrinsically with a close scrutiny for finding out that the conclusion drawn from some facts, by the arbitrator is, according to the understanding of the court, erroneous. Such exercise of power which can be exercised by an appellate court with power to reverse the finding of fact, is alien to scope and ambit of challenge of an award under the Arbitration Act. Where the error of finding of facts having a bearing on the award is patent and is easily demonstrable without the necessity of carefully weighing the various possible view points, the interference with award based on erroneous finding of fact is permissible. Similarly, if an award is based by applying a principle of law which is patently erroneous and but for such erroneous application of legal principle, the award could have been
made, such award is liable to be aside by holding that there has been legal misconduct on the part of the arbitrator. In ultimate analysis, it is a question of delicate balancing between the permissible limit of error of law and fact and patently erroneous finding easily demonstrable from the materials on record and application of principle of law forming the basis of the award which is patently erroneous. It may be indicated here that however objectively the problem may be viewed, the subjective element inherent in the judge deciding the problem, is bound to creep in and influence the decision. By long training in the art of dispassionate analysis, such subjective element is, however, reduced to minimum. Keeping the aforesaid principle in mind, the challenge to the validity of the impugned award is to be considered with reference to judicial decisions on the subject."
17. Since the learned arbitrator has failed to consider the relevant
evidence brought before him, the finding of fact returned by him is
clearly vitiated and cannot be sustained. He has completely ignored
the categorical case of the petitioner that the site was available when
the letter dated 23.12.2004 was issued by it, and the response thereto
given by the respondent. This error in the finding of fact, which has
vital bearing on the determination of the issue: which of the parties
was in breach of the contract, is patent and demonstrated on the plain
reading of the award.
18. A perusal of the contractual terms, as extracted hereinabove,
shows that the time for execution of the work was to be reckoned from
the 15th day mentioned in the letter of award, on which the engineer in
charge issues written orders to commence the work, or from the date
of handing over of the site, whichever is later. Therefore, the time for
execution of the work, even if the site was available in December
2004, would continue to have remained for two years and would have
commenced only upon taking over of the site in December 2004 by the
respondent. The respondent did not dispute that the full site was
available in December 2004. The reason given by him for not carrying
out the work was escalation in the rates of materials. This claim of the
respondent is sufficiently taken care of by clause 10C and 10CC of the
contract. The increase in rates, therefore, could not have provided a
good justification for the respondent not to commence the work.
Consequently, the finding that the breach of the contract was on the
part of the petitioner, and not on the part of the respondent also
appears to be patently erroneous.
19. Similarly, it is pointed out by learned counsel for the petitioner
that the learned arbitrator has not considered the communication
dated 02.06.2004, wherein the petitioner called upon the respondent
to collect the necessary drawings from the office of the Executive
Engineer, XXXI or from the concerned JE/AE II. In the face of this
communication, the finding of the arbitrator that the drawings were
not made available to the respondent cannot be sustained, as this
communication has not at all been taken note of at all.
20. I may observe that the learned arbitrator has displayed a casual
and perfunctory approach in deciding the reference. Even though the
actual tendered cost of the work was Rs.2,25,92,552/-, he has
computed the compensation @ 10% on the estimated cost put to
tender. Even if the claim for damages on account of loss of profit were
allowable (which cannot be allowed in view of the above discussion),
the same could have been computed only by reference to the tendered
amount and not the estimated cost put to tender. Similarly, the award
of interest from the date of the award @ 9% p.a. has been made on the
entire amount of Rs.34,27,808/-, which includes the pendente lite
interest awarded of Rs.7,57,984/-. The learned arbitrator could not
have awarded interest on interest as done by him, in any event.
21. In the light of the aforesaid, the impugned award suffers from
patent illegalities as the learned arbitrator completely ignored the
evidence brought on record, and the same is accordingly set aside in
its entirety. The parties are left to bear their respective costs.
VIPIN SANGHI, J
MARCH 28, 2011 sr
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!