Citation : 2011 Latest Caselaw 1516 Del
Judgement Date : 16 March, 2011
THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment Pronounced on: March 16, 2011
+ CS(OS) No. 1459/2006
SHYAM BIHARI SINGHAL .....Plaintiff
- versus -
BSES YAMUNA POWER LTD. .....Defendant
Advocates who appeared in this case:
For the Plaintiff: Mr. Fanish K. Jain, Adv.
For the Defendant: Mr. K. Datta with Mr. Diggaj Pathak,
Advs.
CORAM:-
HON'BLE MR JUSTICE V.K. JAIN
1.
Whether Reporters of local papers may Yes be allowed to see the judgment? 2. To be referred to the Reporter or not? Yes 3. Whether the judgment should be reported Yes in Digest? V.K. JAIN, J (ORAL) 1. This is a suit for declaration and permanent injunction. The plaintiff is a consumer of the defendant in
respect of connection no. K 623-1321193-IP installed at his
business premises being B-14/7, Jhilmil Industrial Area,
Shahdara, Delhi.
2. The plaintiff had initially got sanctioned load of 17.92
KW but, he later appealed for its enhancement to 50 HP.
Under a voluntary disclosure scheme floated by the defendant,
the plaintiff declared his tampered meter and also deposited
the relevant charges on 26.4.1999. His meter was then
changed in May, 1999. The case of the plaintiff is that the
meter was not sealed by the defendant at the time it was
changed in May, 1999. According to the plaintiff, only paper
seals were put on the meter but they were not properly pasted.
It was claimed by the defendant that at the time of inspection
by its officials on 14th July, 1999, one paper seal was found
uprooted. This however is controverted by the plaintiff whose
case is that in fact, the paper seal was not properly pasted and
it was uprooted at the time of inspection by the officials of the
defendant.
3. It is alleged that during an inspection carried out by
the defendant on 15th May, 1999, the load was found to be
16.608 KW. An inspection was thereafter carried out on 14 th
July, 1999 by the officials of the defendant. According to the
plaintiff, the load found at that time was within the sanctioned
limit but was wrongly shown as 150.643 KW in the inspection
report, without verifying the factual position.
4. It is further stated that a provisional bill of Rs.
48,83,927/- was issued to the plaintiff demanding electricity
charges @ Rs. 4.30 per unit, though it should have been raised
@ Rs. 3.00 per unit. Neither any show cause notice was issued
to the plaintiff before issuing the aforesaid demand notice nor
was he given an opportunity of personal hearing. The plaintiff
has sought a declaration that the inspection report and MT
report dated 14th July, 1999 as also the bill raised by the
defendant are null and void. He has also sought injunction
restraining the defendant from disconnecting electricity supply
o the basis of non-payment of the aforesaid bill.
5. The defendant did not file any written statement and
the right to file its written statement was closed vide order
dated 13th November, 2007.
6. The plaintiff has filed his own affidavit by way of
evidence in which he has supported on oath the case set up in
the plaint. He has stated that on 15th May, 1999, an inspection
was carried out by the officials of the defendant in his presence
and at that time, the connected load was found to be 16.608
KW as would be evident from the report dated 15 th May, 1999.
The report was referred in the affidavit as Exhibit PW-1/9,
though the learned Joint Registrar did not put exhibit mark on
the documents, presumably on account of its being a
photocopy. He has further stated that another inspection was
carried out on 14th July, 1999 and it was alleged by the officials
of the defendant, without verifying the factual position, that the
connected load was 150.643 KW. He has claimed that the
cable installed in his premises cannot bear the load of 150.643
KW. He has further stated that the paper seal on the meter
was exactly in the same position as was left by the officials of
the defendant at the time of inspection, though the officials of
the defendant tried to disturb the seal at the time of inspection
on 14th July, 1999. The plaintiff was cross-examined by the
defendant, but, nothing worthwhile mentioning came out in the
cross examination.
7. Vide order dated 3rd August, 1999, the learned Civil
Judge before whom the matter was pending at that time,
directed the defendant to restore the supply to the premises of
the plaintiff subject to the payment of Rs. 6 lakhs in
installments. The aforesaid amount is stated to have been
deposited and the electricity supply stands restored in terms of
the aforesaid order.
8. Since the defendant has not filed any written
statement controverting the averments made in the plaint, I see
no reason to disbelieve the unrebutted testimony of the
plaintiff. The deposition of the plaintiff coupled with the
perusal of the inspection report dated 15th May, 1999 would
show that at the time of inspection carried out on 15 th May,
1999, the connected load was found to be 16.608 KW which is
well within the limits of the sanctioned load of 17.92 KW.
9. The plaintiff has placed on record the photocopies of
two inspection reports both dated 14th July, 1999. The first
report pertains to the load which was found connected at the
time of inspection and the other is the report of status of the
meter installed in the premises of the plaintiff.
10. Though the inspection report dated 14th July, 1999
indicates the connected load of 16.608 KW, there is absolutely
no evidence on record to prove that the load found connected
on that date was more than the load which was sanctioned to
the plaintiff. The case of the plaintiff, as stated earlier, is that
the officials of the defendant recorded connected load of
150.643 KW without factual verification and the cable provided
on his premises cannot bear that much load. The onus was on
the defendant to prove, by leading evidence or by admission of
the plaintiff, that the load found actually connected on 14 th
July, 1999 was 150.643 KW. In the absence of any such
evidence or admission, I see no reason to disbelieve the
deposition of the plaintiff in this regard and held that
connected load on 14th July, 1999 was not 150.643 KW.
11. A perusal of the inspection report dated 14th July,
1999 also indicates that the paper seals passed by the zonal
staff on 21st May, 1999 on middle of the MS box of CT and CT
meter was found removed from the meter side. It further
indicates that on account of removal of the aforesaid paper
seal, the doors of CT and CT meter box are easily openable
without harming the paper seal and hence the CT as well as
process wire were accessible. No evidence has been led by the
defendant to prove the alleged removal of the paper seals.
According to the plaintiff, at the time of inspection on 14 th July,
1999, the paper seals were in the same condition in which they
were put by the officials of the defendant. In the absence of
any rebuttal by way of evidence from the defendant, I see no
reason to disbelieve the testimony of the plaintiff in this regard
and hold that the defendant has failed to prove that the
plaintiff had removed the paper seal from meter site as
recorded in the inspection report dated 14th July, 1999.
12. Even if it is assumed that the paper seal on the meter
box was removed by the plaintiff, as claimed in the inspection
report dated 14th July, 1999, that by itself and without
anything more does not prove any unlawful extraction of energy
by the plaintiff since no evidence of actual tampering with the
meter or even removal of the meter seal was found. This is also
not the case of the defendant that the wire supplying electricity
through the meter had been snapped before it reached the
meter and thus, the electricity was being consumed directly
without routing it through the meter. There is no allegation
that the meter glass was found broken or damaged. In fact,
there is no allegation of any artificial device having been used
at any point of time.
13. In order to prove the alleged unlawful abstraction of
energy, it was not sufficient for the defendant to prove that the
paper seals fixed by its officials were found removed by the
consumer. The defendant was required to prove by some other
evidence such as use of a check meter that the consumption
being recorded by the meter was found to be less than the
actual energy consumed by him. One possible method of theft
of electricity can be by tampering with the meter or its
mechanism so as to slow down the recording of consumption
by it. Another method can be to use an external device, which
enables abstraction of electricity, in such a manner that the
supply is not routed through the meter. Yet another method
can be abstracting energy directly from the main lines. Of
course, these methods of unlawful abstraction of energy are
only illustrative and not exhaustive the lawful abstraction of
energy can in certain cases be also indicated by study and
analysis of consumption pattern of the consumer. In a given
case, it can be shown that the consumption found recorded by
the meter was much less than what it ought to have been,
considering the capacity of the equipments installed and being
used by the plaintiff in his premises and the working days and
working hours for which these equipments were used, provided
that it is not a case of the meter being defective. No such
attempt was however made by the officials of the defendant at
the time of inspection on 14th July, 1999 or even thereafter.
14. In a case where no tampering with the meter or the
seals affixed on it is found and no external device is found
being used by the consumer, mere removal of the paper seal
fixed on the meter box would not, in my view, be sufficient to
prove unlawful abstraction of energy and in any case would not
disclose the quantum of the energy actually stolen.
15. In Jagarnath Singh v. H. Krishna Murthy & Anr.,
AIR 1967 SC 947, which was a case of prosecution under
Section 39, Indian Electricity Act, 1910, Supreme Court was
considering a case where the meter was installed in a dark
corner and passage to the meter had certain obstructions. It
was also found that by inserting a wire through the stud hole,
the movement of the meter which registers the consumption of
electric energy could be affected in a way as to either totally
prevent the rotating or slow down its movement, as a result of
which, there could be consumption of electric energy without
payment for the same. Supreme Court held that existence of
such tampered meter does not amount to such artificial means
for abstraction of electricity so as to make it an offence under
Section 39 of the Act. The Court also referred to its earlier
decision in Jagannath Singh v. Ramaswamy AIR 1966 SC
849, wherein it was observed that a meter with an exposed
stud hole was not a perfected instrument for unauthorized
taking of energy and could not be regarded as an artificial
means for its abstraction.
In the case before this Court, no artificial device for
abstraction of energy was found installed at the time of
inspection on 14th July, 1999 and no gap was found in the
meter whereby a wire/some other device could be inserted
inside, so as to obstruct the functioning of the rotator.
17. In Ramesh Chander v. State, 1997 (42) DRJ, which
again was a case for prosecution under Section 39 of the
Electricity Act, this Court observed that mere existence of
tampered meter is not enough to attract the provisions of
Section 39 of the Act and there was no presumption of
dishonest abstraction, consumption or use of electric energy on
discovery of tampered meters. The Court was of the view that
the presumption under Section 39 will arise if artificial means
were employed to abstract, consume or use energy. In taking
this view, this Court relied upon the decision of the Supreme
Court in Ram Chandra Prasad Sharma and others v. State
of Bihar and another AIR 1967 SC 349, wherein it was held
that the presence of a perfected artificial means which would
render abstraction of energy possible has to be established by
the prosecuting agency.
18. In Swaran Dhawan v. State (NCT of Delhi), 99
(2002) DLT 416, which was also a case for prosecution under
Section 39 of the Electricity Act, it was found that half seal on
the meter was fictitious. It was held that this by itself does not
lead to an inference that the electricity was being stolen from
the meter. It was held that the burden was on the licensee i.e.
Delhi Vidyut Board to prove that the electricity was being
abstracted, consumed and used by the consumer and the
consumer had dishonest intention to do so, though in the event
an artificial means or device is found which is used or
facilitates abstraction, consumption of energy which is not
authorized by DVB for drawing electricity, the burden of proof
shifts on the consumer to prove to the contrary.
19. In Jagdish Narayan vs. North Delhi Power Ltd. &
Anr., 140 (2007) DLT 307, this Court relying upon the
decision of the Supreme Court in Jagannath Singh (supra) held
that automatic presumption of DAE on the basis of the external
symptoms of tampering together with the analysis of the
consumption pattern would not be a safe and error free method
and some other tangible evince must be shown to exist. This
Court was of the view that an accu check meter can be
deployed to find out if the meter is in fact recording lesser units
and that analysis of the consumption pattern being merely
corroborative, would not by itself be substantive evidence.
In the case before this court, the defendant did not
make an attempt even to study the consumption pattern of the
plaintiff to find out whether consumption of electricity by him,
after restoration of electricity pursuant to the interim order
passed on 3rd August, 1999, had increased. Had that been
done and had the consumption being found substantially
higher, that could have given some indication that the meter
was not correctly recording the consumption of electricity at the
time of inspection on 14th July, 1999, though that by itself
would not have been a clinching factor and would have only
been one of the circumstances indicating possibility of unlawful
abstraction of energy.
20. In Udham Singh v. BSES Rajdhani Power Ltd., 136
(2007) DLT 500, during the course of inspection, it was found
that CT and meter box combined seals were found missing. On
6.10.2002, the petitioner's premises were inspected and it was
found that the paper seals which were pasted on the Meter box
were intact. It was endorsed that the paper seals which were
pasted on the meter box had been removed and the fresh seals
were duly signed. Those seals were removed by the staff of the
licensee and were replaced by fresh seals. No irregularity was,
however, found. Another inspection was carried out on 24 th
March, 2004. At that time, the meter was running in the right
direction, the meter half seals were observed to be unnumbered
and it was reported that the meter was running fast by 5.30%.
A third inspection was held on 1.12.2004. On this occasion,
the inspection team stated that the CT and Meter Box
combined seals were found missing. After giving show cause
notice to the consumer, an order was passed by the AO of
BSES on 17th December, 2004, referring to the inspection dated
1st December, 2004, the consumption pattern indicated that
average recorded consumption to be 1119.84 units per month,
which was found to be 19.95% of the assessed consumption.
Holding the consumption to be low, dishonest abstract of
energy was held to be established.
During the course of judgment it was observed by this
court that the mere circumstance that CT box meter was
missing itself could not lead to conclusive proof of tampering or
dishonest abstraction of energy. With respect to consumption
pattern, considering the explanation given by the consumer, it
was observed that the consumption pattern being derivative,
and not on the basis of the actual consumption by use of
scientific principles or better tools, more accurately deducing
the actual consumption of electricity led to the inference that
the meter was slow but the meter was not checked for accuracy
or defects nor were any material disclosed to that effect. The
Court was of the view that in absence of any collateral
materials or conclusive proof about the dishonest abstraction of
energy, mere existence of an irregular seal could not have
justified such findings.
22. In Bhasin Motors (I) P. Ltd. v. NDPL, 142 (2007)
DLT 116, it was found during inspection that the upper seal of
the meter box had been tampered. The cover seals were found
to be missing. The court was of the view that the aforesaid
signs are best helpful to suspect the dishonest abstraction of
energy but cannot be taken to be conclusive evidence.
23. In order to succeed, the defendant was required to
establish that the actual consumption of electricity by the
plaintiff was more than what was recorded in the meter and it
was further required to prove on the basis of some rationale
and scientific formula the amount of energy consumed by the
plaintiff without its being recorded in the meter. For the
reasons given in the preceding paragraphs, I have no hesitation
in holding that since the defendant has failed to produce any
evidence to prove that the actual connected load on 14 th July,
1999 was 150.643 KW has not at all established any unlawful
abstraction of energy and further has also failed to show how
and on what basis the demand raised in the bill marked as
Exhibit PW-1/10 for Rs. 48,83,927/- has been arrived at. The
impugned demand, therefore, cannot be sustained and the bill
raised by the defendant is accordingly liable to be quashed.
24. The impugned bill demanding Rs. 48,83,927/- from
the plaintiff is hereby quashed and the defendant is restrained
from disconnecting the electricity of the plaintiff on account of
non-payment of the aforesaid bill. It is made clear that this
order will not come in the way of the defendant disconnecting
the electricity supply to the plaintiff for non-payment of some
other dues or on account of some other valid reason.
25. The amount of Rs. 6 lakhs which the plaintiff had
deposited in compliance of the interim order dated 3 rd August,
1999 shall be refunded back to him within 8 weeks.
26. The decree sheet be drawn up accordingly.
(V.K. JAIN) JUDGE MARCH 16, 2011 Sd
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!