Citation : 2011 Latest Caselaw 1514 Del
Judgement Date : 16 March, 2011
*IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of decision: 16th March, 2011
+ W.P.(C) 1712/2011
SMT. KANTA SHARMA ..... Petitioner
Through: Mr. Ujjwal K. Jha & Mr. B.P.
Agarwal, Advocates
Versus
BSES RAJDHANI POWER LTD ..... Respondent
Through: Ms. Anjali Sharma, Advocate.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? Yes
2. To be referred to the reporter or not? Yes
3. Whether the judgment should be reported Yes
in the Digest?
RAJIV SAHAI ENDLAW, J.
1. The petition impugns the speaking order dated 27th January, 2011 of
the respondent holding the petitioner guilty of Dishonest Abstraction of
Energy (DAE) and the consequent demand for `2,29,085/-.
2. Since the Division Bench of this Court in B.L. Kantroo Vs. BSES
Rajdhani Power Ltd. 154 (2008) DLT 56 has held that even a consumer is
entitled to approach the Special Court set up under Section 153 of the
Electricity Act, 2003, it is felt that the writ petitions be entertained only in
cases where no factual controversy arises and where the speaking order can
be quashed merely on an illegibility / breach of procedure as borne out
from the speaking order and the other documents of the respondent.
3. Finding that the petition in the present case raises a number of
factual controversies also, it has been put to the counsel for the petitioner
that the matter cannot be permitted to be agitated simultaneously before
two foras i.e. the factual controversy before the Special Court and the legal
questions raised in this Court and the petition would be entertained only if
the petitioner is willing to give up the challenge on factual grounds.
4. The counsel for the petitioner has contended that though factual
ground may also be necessary but it may be examined by this Court
whether the procedure followed in the instant case by the respondent is in
accordance with the Regulations or not. The counsels have been heard on
the said limited aspect, without intending to prejudice the parties in any
manner before the Special Court.
5. The petitioner herein had reported to the respondent of the meter
installed at her premises having got burnt. Upon such complaint, the meter
was replaced and a Meter Replacement Report / Meter Burnt Report dated
3rd September, 2010 prepared. In the said report, no observation has been
made with respect to any of the meter seals having been found broken or
tampered with.
6. The petitioner was served with a notice dated 6th September, 2010
informing that the burnt meter which had been sealed and taken away by
the respondent will be de-sealed in the presence of the petitioner on 21 st
September, 2010. There is no plea as to whether the petitioner reported on
21st September, 2010 or not. No letter also was sent by the petitioner in
this regard. As per the documents furnished to the petitioner, the meter
was tested in the laboratory on 28th October, 2010 and in which report it is
stated that visual observation showed that the top cover of the meter was
found re-fixed and IP terminal was found burnt. It was further reported
that one illegal re- soldering was found on PCB at 12 V AC point and
another at CT6 point. The report accordingly concluded that the burnt
meter had been tampered.
7. The respondent thereafter inspected the premises of the petitioner on
29th November, 2010 and found excess connected load over sanctioned
load and a show cause notice given to the petitioner including with respect
to the report aforesaid of meter testing of the laboratory and which
ultimately resulted in the speaking order impugned in this petition.
8. The counsel for the petitioner at the outset argued that no case for
DAE can be said to have been made out in the present case since under
Regulation 52 of the Delhi Electricity Supply Code and Performance
Standards Regulations, 2007 an inspection has to necessarily precede
booking of a case for theft of electricity.
9. The aforesaid contention is not found acceptable. Accepting the
said contention would tantamount to holding that there can be no case of
theft in the case of a burnt meter. An unscrupulous consumer cannot be
permitted to escape the charge and liability of theft by burning the meter.
If the meter is reported to be burnt, Regulation 40 requires the respondent
to immediately install the new meter and to send the burnt meter for
testing. If on such testing, the respondent finds that the meter has been
burnt to escape charge of theft, certainly a case thereof can be booked.
10. The counsel for the petitioner has next contended that even if the
case for theft were to be booked in pursuance to a burnt meter, the
respondent was required to carry out the test of the meter in the laboratory
in the presence of the petitioner. Reliance in this regard is placed on
Regulations 52(viii) & (ix). It has been put to the counsel for the petitioner
whether the expression "and the same must be handed over to the
consumer or his / her representative at site immediately under proper
receipt" in Regulation 52 (ix) does not mean / refer to the premises of the
petitioner from where the meter is removed. The counsel for the petitioner
however contends that in the case of a burnt meter, the expression "site"
would denote the site where the meter is tested.
11. I am unable to accept the said proposition also. Neither Regulation
52 nor Regulation 40 dealing with burnt meter requires the testing in the
lab to be in the presence of the consumer.
12. The counsel for the petitioner then contends that the testing had to
be necessarily in the presence of the petitioner in as much as a notice
therefor was given. He contends that pursuant to the said notice, even if
the petitioner had not reported for testing on 21st September, 2010, and if
the respondent was not able to carry out the test on that date, another notice
of the fresh date for testing ought to have been given.
13. The counsel for the respondent on the contrary contends that the
notice of testing is given as a part of good practices and without any
obligation in this regard.
14. Once the Regulations are not found to impose any obligation on the
respondent to test the meter in the presence of the consumer and the
consumer fails to avail the opportunity on the date given for testing, the
process cannot be made cumbersome and the condition that no testing can
be carried out without the presence of the petitioner and which may lead to
delays cannot be imposed.
15. The counsel for the petitioner has next contended that in the present
case, the burnt meter was not even sealed in the presence of the petitioner.
He contends that there is nothing to the said effect in the burnt meter /
meter replacement report also. However, this is found to be a question of
fact and which is left to be best adjudicated by the Special Court.
16. The other question which arises is whether it should be the petitioner
who should approach the Special Court, as contended by the counsel for
the respondent, or the respondent should be directed to approach the
Special Court with its case for DAE against the petitioner and the
petitioner should be protected till then.
17. The respondent is required to approach the Special Court only for
enforcement of the civil liability. As far as disconnection for non payment
of the assessment in pursuance of the speaking order is concerned, the
respondent is authorized to carry out the same under the Act and the
Regulations.
18. In my opinion, ordinarily it should be the consumer who if
aggrieved by the speaking order and the demand in pursuance thereto and
if raising factual controversies should approach the Special Court and
claim interim relief against disconnection before the Special Court.
However, in exceptional cases where writ petitions are filed and the
consumers are relegated to the Special Court for adjudication of the factual
controversies, this Court, if finding a strong prima facie case in favour of
the petitioner, can order that the respondent will not exercise the right of
disconnection without approaching the Special Court.
19. The counsel for the petitioner seeks to withdraw the writ petition
with liberty to approach the Special Court and seeks interim protection till
then.
20. The petition is dismissed as withdrawn with liberty to the petitioner
to raise all questions before the Special Court. Subject to the petitioner so
approaching the Special Court on or before 31st March, 2011, the electric
supply to the petitioner shall not be disconnected in pursuance of the
speaking order and demand impugned in this petition till the consideration
of the application of the petitioner for interim relief by the Special Court.
21. It is reiterated that nothing contained herein shall prejudice the
respective contentions of either parties before the Special Court.
No order as to costs.
Dasti.
RAJIV SAHAI ENDLAW (JUDGE) MARCH 16, 2011 „gsr‟
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!