Citation : 2011 Latest Caselaw 1351 Del
Judgement Date : 8 March, 2011
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP NO.8/2011
Date of Decision : 08.03.2011
Marathon Electric Motors (India) Ltd. ......Plaintiff
Through: Mr. T. K. Ganju, Sr. Adv
with Ms. Kumkum Sen,
Adv.
Versus
North Eastern Electric Power Corporation Ltd. ...... Defendant
Through: Mr. V. K. Jindal, Sr. Adv.
with Mr. Saurabh Prakash,
Adv.
CORAM :
HON'BLE MR. JUSTICE V.K. SHALI
1. Whether Reporters of local papers may be
allowed to see the judgment? NO
2. To be referred to the Reporter or not ? NO
3. Whether the judgment should be reported
in the Digest ? NO
V.K. SHALI, J.
1. This order shall dispose of OMP No. 8/2011, a petition under
Section 9 of the Arbitration and Conciliation Act, 1996.
Though in the petition, the prayer is to pass an order to the
effect that the Bank Guarantee No. ILG0903 dated
27.03.2003 issued by Punjab National Bank, Chennai and
later on substituted by Bank Guarantee No. BG No.
2007012IBGP0052 issued by IDBI Bank, Kolkata stands
released but during the course of arguments, it was urged
that the necessity of filing this application has arisen on
account of the order dated 11.11.2010 passed by Shri S.N.
Phukan, learned Arbitrator, wherein he has refused to release
the balance 50% amount of the aforesaid Bank Guarantee as
the same was withheld in pursuance to the order dated
05.02.2003 passed by Hon'ble Mr. Justice J.D. Kapoor in
OMP No.241/2001.
2. In order to appreciate the controversy, a brief background of
the case which is not disputed by either of the parties, is
necessary.
(a) The present petitioner (which was previously known as
Alstom Limited) had entered into a contract with the
respondent for providing consultancy and commissioning of
certain electrical projects in the North East. In pursuance to
the terms and conditions of the NIT, the present petitioner
had furnished a performance guarantee for a sum of Rs. 61
lacs or so to the respondent. The agreement was entered into
sometime in 2003 and the bank guarantee was also furnished
in the same year, which was later on substituted by another
bank guarantee. The case of the petitioner is that it had
successfully executed the project but there were certain
disputes which had arisen between the parties with regard to
the payment, which were referred to the Arbitrator for
adjudication. The respondent also has purported to have
raised certain disputes regarding the over payment having
been drawn allegedly by floating of wrong bills. It is the case
of the respondent that as a matter of fact, a case was
registered by the CBI against the present petitioner for having
floated wrong and fictitious bills and taken illegal payments
by raising such bills.
(b) The respondent in the year 2003 itself tried to invoke the
performance bank guarantee on account of the fact that the
petitioner was not able to perform the work according to their
satisfaction. This necessitated the filing of a petition being
OMP No. 241/2001 by the Alstom Limited, predecessor-in-
interest of the present petitioner under Section 9 of the
Arbitration and Conciliation Act. The said petition was
disposed of by this Court vide order dated 05.02.2003
wherein it was observed that although there are allegations
made by the CBI against the present petitioner for having
drawn excess and wrongful payments but at the same time,
there is no dispute about the fact that the petitioner is
purported to have performed and executed successfully the
project, for which it was engaged, to the satisfaction of the
respondent. In the light of these two competing interests, one
with regard to the successful execution of the entire project
and the other with regard to an allegation made against the
petitioner of having overdrawn the payment wrongfully, the
learned single Judge directed that 50% of the performance
bank guarantee be released to the petitioner whereas the
balance 50% be withheld and may be made subject to the
outcome of the proceedings which the respondent may initiate
for recovery of the overdrawn payment towards the alleged
extra work.
3. It is this balance 50% of the withheld performance bank
guarantee which is sought to be released by the present
petitioner.
4. The respondent has filed the reply and contested the claim of
the petitioner for the release of this 50% of the balance value
of the performance bank guarantee on the ground that the
counter claim of the respondent to the tune of `90 lacs or so
is still pending adjudication and is on a fairly advanced stage
before Shri S.N.Phukan, the learned sole arbitrator.
Therefore, so long as the said counter claim of the respondent
is not finally adjudicated, the balance 50% of the amount may
not be released to the petitioner.
5. I have heard Mr. T.K. Ganju, learned senior counsel for the
petitioner as well as Mr. V.K. Jindal, learned senior counsel
for the respondent and have also perused the record.
6. There is no dispute about the fact that the law regarding
performance guarantee is well-settled in the sense that once
the performance guarantee is furnished by a contracting
party and the opposite side is fully satisfied regarding the
performance of the contract, having been successfully
executed, the guarantee deserves to be released. It was
contended by Mr. Ganju, learned senior counsel, that since
there is no dispute that the withheld 50% amount pertains to
performance guarantee and the work has been executed,
there is no justification for withholding the balance 50% of
the amount. It has been stated that both the period of
warranty and latent guarantee or otherwise also according to
the terms and conditions of the contract, were valid for a
maximum period of six years, which period came to an end in
2009. The learned senior counsel had drawn the attention of
the Court to the relevant clause of the agreement in this
regard. In addition to this, it was also contended that the
CBI has also filed a Closure Report which has been accepted
by the competent Court and, therefore, there is no
justification for withholding the said amount of performance
guarantee any more.
7. In the present case, there is no dispute about the fact, as has
been observed by the learned single Judge in its order dated
05.02.2003 that so far as the question of the performance of
the project by the petitioner is concerned, that has actually
been completed to the satisfaction of the respondent and
consequently in normal circumstances, the bank guarantee
which was in the nature of the performance guarantee
furnished by the petitioner ought to have been discharged or
released. But with the performance guarantee having been
invoked, the petitioner was constrained to approach the Court
(by filing OMP No.241/2001) for a restraint order whereupon
the Court also took into consideration the fact that there were
serious allegations against the present petitioner itself for
having raised false, frivolous and wrongful bills and
consequently over drawn the payment. On account of the
said allegations against the petitioner, the CBI registered an
FIR. It was on account of these serious allegations levelled
against the petitioner by the CBI that the learned single
Judge, while balancing the equities, directed release of only
50% of the performance guarantee amount whereas the
balance 50% was made subject to the decision in the counter
claim which may be filed by the respondent against the
present petitioner.
8. It is the case of the petitioner that so far as the CBI case
against the present petitioner is concerned, a Closure Report
had already been filed by the CBI, which has been accepted
by the competent court. The learned senior counsel has in
this regard placed on record a copy of the Closure Report and
drawn the attention of the Court to the relevant averments
made in the Closure Report. This fact has also not been
disputed by the learned senior counsel for the respondent. If
that be so, the main ground on the basis of which the balance
50% of the performance guarantee amount was withheld,
goes.
9. It has also been contended by the learned senior counsel for
the petitioner that according to the terms and conditions of
the contract, the equipment which was installed by the
present petitioner was to have warranty and the latent
guarantee ranging from a period of 15 months to maximum of
6 years, and even this period of six years has elapsed and
there has been no defect pointed out in the equipment
provided by the petitioner to the respondent, therefore, that
could also not be a ground for withholding the balance 50% of
the amount of performance guarantee.
10. This argument could not be successfully countered by the
learned senior counsel for the respondent.
11. I fully agree with the contention of the learned senior counsel
for the petitioner that according to the terms and conditions,
it is neither in dispute that the work has been successfully
executed in 2003 nor that the period of six years, which is the
maximum period provided for the warranty and latent
guarantee with regard to the equipment provided by the
petitioner, has also come to an end. Therefore, it could not be
a valid justification for depriving the petitioner of his
legitimate claim by withholding the balance 50% of the
amount of performance guarantee. The CBI case has also
been closed, so that could also not be a ground for
withholding the amount from the petitioner.
12. Now, the only ground on which the balance 50% of the
performance guarantee amount has been withheld is the
counter claim, which is under adjudication before the learned
sole arbitrator. The petitioner had admittedly filed an
application for release of that balance 50% amount with the
learned sole arbitrator who refused to pass any order on the
ground that this was a condition which was imposed by the
Court and, therefore, the petitioner must approach the Court
for modification of the said order. It is because of this reason
that the restraint was issued. The present petition is as a
sequel to the direction given by the learned arbitrator. Since
the learned single Judge vide order dated 05.02.2003 has
specifically directed that the balance 50% shall be released to
the petitioner subject to the decision in the proceedings
initiated by the respondent, therefore, in order to balance the
equities, I am of the view that no useful purpose would be
served by keeping the balance 50% amount of the
performance guarantee if the interest of the respondent to the
extent of this balance 50% is fully secured. This can be done
by directing the petitioner to either furnish an undertaking or
to give a bank guarantee with regard to this balance 50% till
the time the matter is not finally adjudicated by the learned
arbitrator.
13. I am of the considered opinion that the amount which has
been withheld by the Court is essentially forming a part of the
performance guarantee and not as a security to the counter
claim. The petitioner admittedly has successfully performed
the contract to the satisfaction of the respondent and,
therefore, there is absolutely and prima facie no valid
justification for depriving the petitioner of the said balance
50%. I feel that the application of the petitioner for the
release of the balance amount of 50% of the performance
bank guarantee deserves to be allowed on petitioner's
furnishing an undertaking to the satisfaction of the learned
Registrar (Original) of this Court stating that in the event of
the learned arbitrator deciding against the petitioner and
granting any claim of the respondent which is of any amount
up to the 50% of the bank guarantee, the said amount shall
either be deposited by the petitioner with the Registrar
General or alternatively he shall furnish necessary bank
guarantee in this regard. Needless to say that this will be
subject to such legitimate challenge which the petitioner may
like to lay to such an award, which if at all is ultimately
passed against them. Once these conditions are met, I am of
the view that the interest of the respondent will also be
sufficiently protected and accordingly, I direct the petitioner
to furnish the said undertaking to the satisfaction of the
learned Registrar within a period of two weeks from today.
On that undertaking having been furnished and accepted, the
aforesaid 50% of the balance amount of the performance
bank guarantee along with interest accrued thereupon, shall
be released to the petitioner.
14. With these observations, the application of the petitioner
stands disposed of.
V.K. SHALI, J.
MARCH 08, 2011 MA
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!