Citation : 2011 Latest Caselaw 1313 Del
Judgement Date : 7 March, 2011
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ ARB.P. NO.256/2010
Date of Decision : 07.03.2011
Mr. Satish Kumar Bakshi ......Petitioner
Through: Mr. Hemant Malhotra,
Advocate.
Versus
M/s Kohli Realtors Pvt. Ltd. ...... Respondent
Through: Mr. Dinesh Garg, Adv.
CORAM :
HON'BLE MR. JUSTICE V.K. SHALI
1. Whether Reporters of local papers may be
allowed to see the judgment? NO
2. To be referred to the Reporter or not ? NO
3. Whether the judgment should be reported
in the Digest ? NO
V.K. SHALI, J.
1. This order shall dispose of the Arbitration Petition filed by the
petitioner Mr. Satish Kumar Bakshi against M/s. Kohli
Realtors Private Limited, under Section 11 of the Arbitration
and Conciliation Act, 1996.
2. Briefly stated, the facts of the case are that the petitioner is
the owner of property bearing Plot No. A-304, Defence Colony,
New Delhi, measuring 217 Sq. Yds. The petitioner entered
into a collaboration agreement in respect of re-building of his
entire property with the respondent M/s. Kohli Realtors
Private Limited vide collaboration agreement dated
07.01.2008. According to the collaboration agreement, the
respondent agreed to pay a total consideration of `35 lakhs to
the petitioner and also to bear the entire cost of construction
to be raised on the said building in accordance with the
sanctioned plan. The built-up portion of the area was to be
shared by the parties in certain proportions after ear-marking
common areas, the details of which are given in the
agreement itself. The specifications for the construction were
given in the collaboration agreement by way of Annexure „A‟
which were broadly of class „A‟ construction. The time for
construction was also enunciated in the collaboration
agreement. The relevant clause for our purpose, on the basis
of which the present petition has been filed is contained in
Clause 22, which reads as under :-
"That in the event of any question or dispute arising in connection with or incidental or in respect of interpretation or scope of this agreement or any part thereof then the same shall be referred to the arbitration who is mutually appointed arbitrator and the decision of the mutually appointed arbitrator will be binding on both the parties on this agreement."
3. It is alleged by the petitioner that after the rebuilding of the
entire property, he was put in the possession of his portion of
the property in question except the first floor, with one
servant quarter having common toilet both on the top terrace
floor and one car parking space inside the building with
undivided, indivisible, unpartable land rights underneath
exclusively as it was to fall to the share of the respondent.
4. The petitioner alleges that after using the premises in
question, he felt that the work which was carried out by
the respondent was not in accordance with the terms
agreed to, apart from the fact that certain deficiencies in
the execution of the work were pointed out. These
deficiencies which are enumerated by the petitioner are
broadly given as under :-
(i) That as per clause 15 of the agreed specifications it was, inter alia, agreed and provided that the basement of the property will be water proofed by the process of guniting to avoid dampness and seepage. However, shortly after taking over the possession, the basement of the property showed signs of dampness and today the basement is totally damped clearly indicating that no guniting work has been done. Besides there are other structural defects also in the basement. As per the estimate obtained by my client, the present cost of redoing the basement is approximately Rs.7,00,000/- (Rupees Seven Lakhs Only).
(ii) That as per clause 12 and 13 of the specifications you were required to make provisions of grills in the apartment and also make provisions of 300 sq. feet temporary cover on the terrace. The same has also not been done/provided. The estimated cost for providing the same is approximately Rs. 2,00,000/- (Rupees Two Lakhs Only).
(iii) That vide clause 14 of the specifications it was, inter alia, agreed between the parties that a lift as per approved design would be provided by you for all the floors i.e. from basement upto the terrace. However, as already pointed out to you that lift provided by you covered only upto the terrace but has not covered the basement of the property. The present estimated cost of carrying out necessary rectifications and alterations etc. in respect thereof is approximately Rs. 15,00,000/- (Rupees Fifteen Lakhs Only).
(iv) Payment of electricity bill pertaining to period August, 2009 to December, 2009 i.e. relating to the period of construction which amount/liability, as per the agreed terms, was to be borne by you. The said liability comes to Rs.14,600/- (Rupees Fourteen Thousand Six Hundred Only) which is to be borne by you.
(v) The parts of flushing cisterns have not been installed by you due to which water pipes are full of debris causing frequent malfunctioning of the said systems. The estimated cost of rectification/ replacement is Rs. 15,000/- (Rupees Fifteen Thousand Only).
5. The case which has been set up by the petitioner now is that
since the respondent has not carried out the construction in
accordance with the terms and conditions of the collaboration
agreement, he approached the respondent a number of times
for rectification of deficiencies who assured him to rectify the
same. Since the repeated attempts on the part of the
petitioner to get the deficiencies rectified did not yield any
fruitful result, he was constrained to issue a notice on
11.05.2010 to the respondent invoking the arbitration clause
contained in Clause 22 of the collaboration agreement for
reference of the dispute enumerated hereinabove for
adjudication by a Sole Arbitrator to be appointed mutually.
6. The respondent replied to the said notice on 27.05.2010 and
stated that the entire work of rebuilding was carried out to
the full and final satisfaction of the petitioner, whereupon he
had also taken the possession of his share and signed in
token of having done the same. It is only after satisfying
himself that the petitioner has now, with a view to coerce the
respondent to agree to his unreasonable demands, issued a
notice to him for rectifying the deficiencies and for raising the
construction which would be unauthorized and not approved
by the MCD. It was in this context that the respondent stated
that the lift could not go to the basement while as the
petitioner wanted the lift to go right up to the basement.
7. The petitioner gave a response to the reply of the respondent
vide letter dated 12.07.2010 denying the same and reiterated
his plea of appointment of an independent arbitrator. Since
this was not done, the petitioner was constrained to file the
present petition for appointment of an independent arbitrator
for adjudication of the disputes between the parties. It was
contended that the respondent has now forfeited his right to
appoint the arbitrator.
8. The respondent filed the reply to the petition and contested
the prayer of the petitioner. It was stated in the reply that the
present petition has been filed only for the purpose of black
mailing the respondent to agree to the unreasonable demands
of the petitioner. Apart from this, it was contended that the
petitioner had received the possession of his share vide a
written document on 24.12.2009 wherein he had specifically
stated that the suit property had been rebuilt according to the
terms and conditions of the collaboration agreement dated
07.01.2008 and the entire construction had been completed
to his satisfaction. The petitioner also accorded his consent
that all his bills were fully cleared and settled and, therefore,
it was contended that there exists no live dispute between the
petitioner and the respondent and the collaboration
agreement which contained the arbitration clause stood
discharged. The petitioner filed his rejoinder to the reply and
contested the claim and reiterated the points made in the
petition.
9. I have heard the learned counsel for the parties and perused
the record.
10. It has been contended by the learned counsel for the
petitioner that merely because the petitioner has received and
signed the possession letter wherein it has been observed that
the entire work has been carried out in accordance with the
terms and conditions of the collaboration agreement and the
petitioner is satisfied, it does not mean that the petitioner
cannot get the dispute adjudicated through the mechanism
envisaged in clause 22. It was contended that the signatures
of the petitioner on the possession letter were obtained under
coercion and undue influence. Even otherwise, if the
petitioner has signed the said letter, still the respondent could
not be permitted to evade his duty of carrying out the
requisite work with regard to seepage in the basement and
removing other deficiencies as these deficiencies would come
into notice after the actual user of the premises and not at
the time of signing of the possession letter. The learned
counsel stated that there was neither any intention nor any
reason for the petitioner to sign the discharge document of
the collaboration agreement and, therefore, the dispute has to
be necessarily adjudicated by the learned arbitrator. In order
to support his contention that merely the signature of the
petitioner on the letter of possession or a receipt would not be
sufficient to absolve the respondent from the responsibility of
getting the dispute adjudicated by an arbitrator, reliance was
placed on the case titled National Insurance Co. Ltd. Vs.
M/s Boghar Polyjab Pvt. Ltd. AIR 2009 SC 170.
11. The learned counsel for the respondent had taken the plea
that the petitioner not only concealed the information with
regard to having taken the possession but also did not reveal
the exact contents of the said possession letter. It is stated
that the possession letter dated 24.12.2009 specifically
records the satisfaction of the petitioner, that the respondent
had built the entire property on the plot of land in question in
accordance with the collaboration agreement and the terms
and conditions annexed thereto. The petitioner had satisfied
himself regarding the quality of construction and only
thereafter appended his signature. Once the petitioner signs
the document of possession and records his satisfaction, the
collaboration agreement under which the construction was
raised, stands concluded and the petitioner after a lapse of 7-
8 months could not be permitted to raise a dispute with
regard to the interpretation of the collaboration agreement or
the so-called deficiencies in the construction of the building.
It is alleged by the learned counsel for the respondent that if
the petitioner was aggrieved on account of discharge of the
agreement, he should have revealed in the notice that his
signatures were appended on the possession letter by
coercion or inducement or without prejudice to his rights.
Since this has not been done, therefore, it is contended that
there is no occasion for reference of the matter to arbitration
as there is no dispute much less the same being a live
dispute. Reliance in this regard has been placed by the
respondent on Prime Engineers and Consultants Vs.
Punjab National Bank, 103 (2003) DLT 133 and
Pollytron & Fragrance Industries (P) Limited Vs. National
Insurance Co. Ltd. 159 (2009) DLT 534.
12. I have thoughtfully considered the submissions made by the
learned counsel for the parties. There is no dispute about the
fact that the consistent view has been taken by the courts
that in order to get the dispute between the two parties
adjudicated by an Arbitral Tribunal in terms of the arbitration
clause, there must not only be an arbitration agreement but
also a live dispute. Conversely meaning that the agreement
which contained the arbitration clause should not have been
discharged or come to an end on account of either
cancellation or by its performance. In the instant case, the
letter of possession purported to have been issued by the
petitioner to the respondent clearly shows that the
collaboration agreement dated 07.12.2008 executed between
the petitioner and the respondent has come to an end on
account of its performance. Not only it has come to an end by
the petitioner having taken the possession he has fully
recorded his satisfaction to the effect that the construction
has been raised in accordance with the terms and conditions
of the collaboration agreement and the construction has been
raised according to the specifications attached to the
document. Once this has been done, the arbitration
agreement between the parties ceases to exist and, therefore,
the respondent is well within his right to contest the plea of
the petitioner that there is no live dispute between the
petitioner and the respondent for reference of the same to an
Arbitral Tribunal. It does not mean that the petitioner may
not have his remedy. He may have his remedy by either
approaching a different forum or by using a different
modality. But certainly the arbitration is ruled out on
account of his signing the satisfaction agreement.
13. It has been contended by the petitioner during the course of
the argument that his signatures on the possession letter
were obtained by coercion and fraud and, therefore, in terms
of the judgment of the Apex Court in case of National
Insurance Company's Case it could not be said that the
satisfaction of the petitioner could be the basis for ousting the
jurisdiction of the Court for appointing an arbitrator.
14. I do not agree with the contention made by the learned
counsel in this regard. The facts of the case which have been
relied upon by the petitioner in National Insurance
Company's Case are totally different from the facts of the
present case. In the said case, there was a claim which was
preceded by a certificate of satisfaction having been signed by
him before he had actually received the claim. Further, this
was his plea in the petition itself and, therefore, he had
pleaded that his signatures on the satisfaction certificate or
no claim certificate were obtained by fraud or undue influence
which the Apex Court observed, has to be decided either by
the Court which appoints an arbitrator or alternatively has to
be left to be decided by the Arbitrator himself.
15. So far as the facts of the present case are concerned, the
petitioner in his petition, has nowhere stated that he had
received the possession of his share in terms of the
collaboration agreement nor has he made any reference to the
said letter having recorded his satisfaction. In other words, it
could be said that the petitioner has tried to conceal this vital
information from the Court that he was signatory to a
certificate/letter purported to be issued by him where he has
reiterated his satisfaction and this ground in itself will make
the Court to exercise its discretion in his favour by
appointing an Arbitrator.
16. Even otherwise, on the merits also, this has not been his case
that his signatures on the possession letter were obtained by
coercion or fraud. This is a point which should have been
urged by the petitioner during the course of the oral
submission whereas there is no plea in this regard.
Therefore, I feel that the judgment which has been relied
upon by the petitioner is not at all applicable to the facts of
the present case. The submission made by the respondent
that the notice issued by the petitioner for appointment of an
arbitrator is on account of ulterior motives, cannot be said to
be totally without merit. In any case, the point whether it
was guided by ulterior motive or motive becomes irrelevant
because the collaboration agreement having been acted upon
and thereby having been discharged, on account of the
project having been completed and the possession having
been handed over to the petitioner, who has recorded his
satisfaction, there is no live dispute between the parties
which can be referred to an arbitrator.
17. Accordingly, I feel that the petition is totally without any merit
and the same is dismissed. Parties to bear their own costs.
V.K. SHALI, J.
MARCH 07, 2011 MA
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!