Citation : 2011 Latest Caselaw 1310 Del
Judgement Date : 7 March, 2011
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ Date of Decision: 07.03.2011
% O.M.P. No. 539/2009
DELHI DEVELOPMENT AUTHORITY ..... Petitioner
Through: Mr. Bhupesh Narula, Advocate
versus
M/S S S JETELY ..... Respondent
Through: Ms. Ginny J. Rautray, Advocate
CORAM:
HON'BLE MR. JUSTICE VIPIN SANGHI
1. Whether the Reporters of local papers may
be allowed to see the judgment? : No
2. To be referred to Reporter or not? : Yes
3. Whether the judgment should be reported
in the Digest? : Yes
VIPIN SANGHI, J. (Oral)
1. These are objections preferred under Section 34 of the
Arbitration and Conciliation Act, 1996 to the award dated 23.01.2009
and the corrigendum dated 03.02.2009 made by Shri S.S.Jain, Sole
Arbitrator. The parties had entered into a contract whereunder the
respondent-contractor had undertaken to construct Surbathing Ghat at
downstream site of Wazirabad barrage on bank of river Yamuna, vide
award letter dated 01.05.1995. The stipulated date of start of work was
11.05.1995 and the stipulated date of completion was 10.08.1996.
The period of execution of the work under the contract was 15 months.
A formal agreement was executed between the parties on 04.05.1995.
Admittedly, the respondent-contractor executed about 44.7% of the
work. The contract was rescinded by the petitioner on 29.05.1998.
Disputes arose between the parties as the petitioner claimed that the
respondent was responsible for the delays and non-execution of the
work. The petitioner sought to effect recoveries by levying
compensation under clause 2 of the contract of Rs.37,38,790. On the
other hand, the respondent alleged breach of contract by the petitioner
and the termination of the contract as illegal. The respondent raised
various claims under different heads.
2. The petitioner filed Civil Suit No. CS(OS) No.161/2000 to claim
the amount of Rs.37,38,790. The said suit was contested by the
respondent herein, and the respondent also preferred a counter claim
for about Rs. 89 lakhs. The petitioner filed another suit being CS(OS)
No.941/2001 claiming an amount of Rs.1,04,78,947/-, being the
amount allegedly recoverable from the respondent for getting the work
done at the risk and cost of the respondent. On an application moved
by the respondent under Section 89 C.P.C, this Court vide order dated
23.05.2007 referred the matter to arbitration, and appointed Shri S.S.
Jain, Retd. Superintending Engineer (Arbitration), DDA, as the
Arbitrator. The petitioner, Delhi Development Authority was the
claimant and the contractor M/s. S. S. Jetley was the counter claimant.
The learned Arbitrator has rendered his award whereby he has partially
allowed the counter claims made by the respondent-contractor, and
disallowed the claims of the petitioner towards compensation under
Clause 2 and the claim for recovery of risk-cum-cost amount.
3. The learned Arbitrator firstly considered the issue whether the
petitioner-claimant was entitled to levy compensation under clause 2
of the agreement to the tune of Rs. 37,38,790/- along with interest at
the rate of 18% per annum. The right of the petitioner to levy
compensation could arise only if it were established that there was
delay in execution of the work, for which the respondent-contractor
was responsible. Consequently, the learned Arbitrator considered the
said issue and returned a finding that the petitioner was responsible
for a fundamental breach of the contract inasmuch, as, the petitioner
failed to provide the drawings without which the respondent could not
have carried out the works.
4. The submission of Mr. Narula, learned counsel for the petitioner
DDA is that the learned Arbitrator while dealing with the said aspect
has failed to take into account the various letters issued by the
petitioner to the respondent from time to time during the execution of
the work, wherein the petitioner repeatedly called upon the
respondent-contractor to execute the works expeditiously. He submits
that even if some drawings were not available, various other works
within the reach, where the contractual work was to be done, were
possible to be executed by the respondent. However, the respondent
did not carry out even those works which could possibly have been
done without the drawings for the retaining wall abutting the MCD's
settling tanks.
5. The aforesaid submission of Mr. Narula does not appear to be
correct. A perusal of the award shows that on internal page 10, the
learned Arbitrator has generally discussed the correspondence issued
by the petitioner wherein it was recorded that there was no hindrance
in the execution of the work and whatever hindrances were pointed out
had been sorted out. I may extract the relevant portion of the award
from internal page 10 thereof, which reads as follows:-
"By reading the letters it was pointed out that there was no hindrance in the execution of the work and whatever hindrances were pointed out by the respondent those were sorted out. On the contrary on inspection of the site on the various dates it was observed by various authorities that the work was slow. So by the various letters as shown in the chart filed by the claimant, the respondent was informed of the slow progress and taking effective steps for executing the work. Respondent was also informed that sufficient labour to cope up with the situation were not deployed at the site."
6. The discussion and the reasoning of the learned Arbitrator, while
dealing with the aforesaid issue, is found on internal page 21 onwards
of the award. The learned arbitrator takes note of the petitioner's own
stand that, of the total delay of 657 days from 11.08.1996 to
21.05.1998, when the work was rescinded, the delay of 169 days was
attributable to the petitioner herein and the remaining delay of 488
days was attributed to the respondent herein. The learned Arbitrator
has digested the correspondence exchanged between the parties and
the material brought before him in the following manner:-
"The admitted case of the claimant in Suit No. 161/2000 filed by them in Hon'ble Delhi High Court that till 11.8.1996 (the stipulated date of completion) there was no delay on the part of the respondent. The respondent referred para 14 of the plaint at page 66 of the paper book as extracted below:
"The extension of time case was submitted by
concerned Executive Engineer vide letter No.1335 dated 26.8.1998. As per the Extension of Time performa submitted by the Executive Engineer concerned, it was pointed out that against the delay of 657 days (from 11.8.1996 to 29.5.1998) when the work was rescinded, a delay of 169 days was on account of hindrances attributable to the plaintiff and the remaining delay of about 488 days was attributable to the defendant."
From the documents filed by both the parties and submissions made, it is clear that the respondent was interested to complete the work but could not do so because there were one after the other hindrances. It is also an admitted position that the drawings and designs of many items e.g. flooring and step pattern and more particularly drawings for retaining wall of Municipal Corporation of Delhi settling tank were issued on 21.5.1998. In fact the drawing given to the respondent was not final and was again revised by the claimant and issued to the subsequent agency only on 7.1.1999. This hindrance is recorded by the claimant. From the record it is also clear that Extension of Time was granted by the claimant suo moto up to 30.6.1998 by the letter dated 16.5.1998 after giving the show cause notice dated 1.5.1998 which was replied by the respondent by the letter dated 12.5.1998. On the one hand claimant by the letter dated 16.5.1998 unilaterally extended the time for completion of the work up to 30.6.1998 and on the other hand by the letter dated 29.5.1998 terminated the contract. The ground given for termination of the contract is that the respondent failed to complete the work by the extended date of completion. As per the claimant this date was 30.6.1998. Thus, there was no reason to terminate the contract prior to this date. Another important fact to be noticed is that the Executive Engineer in the letter dated 26.8.1998 addressed to the Superintending Engineer admitted the failure on the part of the claimant to make available the drawings for retaining wall near Municipal Corporation of Delhi boundary wall along with water channel. This hindrance was from 16.7.1995 to 20.5.1998. From the record it is also noticed that the wall was required to be provided on 16.7.1995 immediately after 1995 flood. The claimant also admitted in this letter that the value of work of retailing wall to be executed after the drawing was to be made available was of Rs.35.00 lacs. As per Executive Engineer for execution of this work minimum 45 days were required. It was submitted by the respondent that the consideration of
period of 45 days by the claimant was wrong because other related works dependent upon the construction of retaining wall could be executed only thereafter. Admittedly the drawing for Municipal Corporation of Delhi boundary retaining wall was to be issued on 16.07.1995. It has been established by the respondent through the drawings and also in my expert opinion the said drawing also led to hindrance of the work up to the mid-landing level. This is the work which was possible even during the flood season and would have also given the much needed space for stacking etc., continuity of work and access to the site which were the reasons also responsible for crippling the pace of the work from the very beginning. The claimant has not been able to give any reason for non-issuance of this drawing was non payment of the dues of the Consultant. The drawing was made available on 21.5.1998. From this date even as per the claimant minimum period of 45 days was required for execution of this work. This being so the termination of the contract by the claimant on the excuse that respondent failed to complete the work within the extended date is unjustified and illegal." (emphasis supplied).
7. The learned arbitrator was himself a retired engineer and an
expert in the field of Civil engineering. He has returned a finding that
the failure to provide the drawings for the MCD boundary retaining wall
led to hindrance of the work up to the mid landing level. He has
observed that work was not possible during the flood season, given the
much needed space for stacking etc., continuity of work and access to
the site. He observed that failure to provide the said drawings was the
reason responsible for crippling the pace of the work from the very
beginning.
8. The submission of Mr. Narula also cannot be accepted for the
reason that the authority of the arbitral tribunal to conduct the
proceedings in the manner it considers appropriate includes the
authority to determine the admissibility, relevance, materiality and
weight of any evidence (Section 19(4) of the Act). Therefore, it was for
the learned Arbitrator to have considered the evidence led by the
parties. It is clear from the aforesaid extracts that he has considered
the evidence brought before him and has also considered the aspect of
admissibility, relevance, materiality and weight of the evidence.
From the aforesaid extracts it certainly cannot be said, that the finding
of the learned Arbitrator, that there was a fundamental breach of the
contract on the part of the petitioner in not supplying the relevant
drawings has been arrived at without any evidence.
9. The learned Arbitrator while discussing the aforesaid issue has
also examined the aspect of the hindrance faced by the Contractor in
carrying out the works as the water level was more than 203.25 G.T.S.
The learned Arbitrator has noted that as per drawing No.1015, the
execution of the work was possible only if the water level was at
203.25 G.T.S., and not above that. He refers to the letters dated
05.10.1996 and 21.11.1998 of the respondent and the letter dated
02.07.1996 of the claimant. I may only refer to para 6 of the
petitioner's own letter dated 02.07.1996, wherein the petitioner had
observed as follows:-
"6. Though the coffer dam was constructed up to 204 in good condition and pocklain machine was continuously passing over it, it is practically not possible always to keep the coffer dam workable. This can work only in the dry season when the river water remain always below RD 203.00. The river water level fluctuate with the time and raise the moisture contents in the coffer dam. No trucks with heavy loads never agreed to use the coffer dam to dump the building material. This difficulty was also to be considered. The proper case is however being taken to
protect the landings."
10. The learned Arbitrator takes note of the water level registered
from July 1996 onwards when the level was found to be more than
203.25 G.T.S. Consequently, the learned arbitrator holds that as the
delay was attributable to the petitioner and not to the respondent, the
levy of liquidated damages under clause 2 was not justified. This
submission of Mr. Narula is, therefore, rejected. The finding of fact of
the learned Arbitrator is based on the evidence brought before him and
certainly cannot be said to be perverse.
11. The next submission of Mr. Narula pertains to the award made by
the learned Arbitrator in respect of extra items No.2/(1)(a), 2/(1)(b)
while considering issue No.2. The submission of Mr. Narula is that the
learned arbitrator has allowed the payment for 7448 cu mtr and 6034
cu mtr for excavation in underwater for ordinary rock and hard rock.
He submits that the entries in relation to the aforesaid quantities were
made in pencil in the measurement book. He further submits that
neither in its final bill prepared by the respondent, nor in the statement
of claim, any claim was made in respect of the aforesaid quantities. At
the time when these measurement books were produced, these entries
were found in pencil and merely because these entries were present,
the learned arbitrator has awarded the amounts, as if the aforesaid
works had also been done. He submits that it is not explained as to
where these entries came from. There is no record of the respondent
having done the works to which these pencil entries relate. Had the
respondent done the works, the respondent would have made a claim
therefor in the final bill, as also in the statement of claim.
12. On the other hand, learned counsel for the respondent submits
that the measurement books are written and maintained by the
petitioner, and it is for them to explain these pencil entries. The
submission of learned counsel for the respondent in support of the
award is that once these entries had been made in the measurement
book, it could not be said that the works had not been done. As these
entries are present, the learned Arbitrator was justified in allowing
payment in relation to the said quantities as well.
13. Learned counsel for the respondent further submits that when
the final bill was raised, the respondent was not aware of the
quantities of work done between 18.03.1998, when the 18 th RA bill was
prepared, and 21.05.1998, when the contract was rescinded. The work
had been done upto 21.05.1998. She submits that the quantities of
7488 cu mtr and 6034 cu mtr are the additional work done between
the 18th RA bill and the date of recession for excavation in ordinary
rock and hard rock.
14. I do not find any merit in the submission of the respondent, and
in my view, there is patent illegality in the award insofar as the award
made in items 2/1(a) and 2/1(b) for the quantity of 7488 cu mtr and
6034 cu mtr respectively is concerned. The respondent/contractor did
not even raise a claim in respect of these quantities, neither in the final
bill nor in the statement of claim. Had the respondent carried out the
said works, the respondent certainly would have been aware of it and
would have included these quantities in the final bill and the statement
of claim.
15. The submission that the entries relate to works done after the
raising of the 18th RA bill and before the date of termination cannot be
accepted for the reason that the final bill was raised by the respondent
after the recession of the contract. The respondent did not even claim
that the figures mentioned in the final bill were those taken from the
18th RA bill and that further work had been done between the date of
18th RA bill and the date of recession. The arbitrator could not have
awarded the claim which was not even raised by the respondent. For
the arbitrator to assume jurisdiction and make an award, there has to
be a live dispute or claim.
16. A perusal of the award shows that while allowing the payment for
the quantities mentioned in pencil as aforesaid, the learned arbitrator
has placed heavy reliance on the instructions printed on the
measurement book, that measurements should be recorded in ink and
if made in pencil, the same may not be overwritten in ink.
17. An entry made in a measurement book in the ordinary course,
may raise a presumption of its being a correct recording of the work
done by the Contractor. But such a presumption cannot be made
when an entry is disputed; not corroborated by any other material
evidence; and, the Contractor does not even contemporaneously claim
to have done the work to which such an entry relates. The entry
should clearly reflect that they are intelligible, and should contain the
details and particulars that routinely accompany such an entry. They
should be complete. I have seen the two pencil entries and they
appear not to have been made in the ordinary course of book writing.
They just stand out from the rest of the notings. It is not clear when,
by whom, and for that purpose they were made. They are not
intelligible. The instruction that entries made in pencil should not be
overwritten in ink does not lead to the conclusion that the pencil entry
made in the measurement book was necessarily made in the ordinary
course. All that it means is that there could also be genuine entries
made in the ordinary course in pencil in the measurement book.
Therefore, the reasoning of the learned Arbitrator for relying on the
two pencil entries is completely and fundamentally flawed.
18. So far as the quantity of 7488 cu mtr and 6043 cu mtr for
ordinary rock and hard rock are concerned, these claims were never
asserted at any point of time. The said claim would have been barred
by limitation by the time the respondent asserted these claims during
the course of the arbitral proceedings. In my view, the learned
arbitrator has exceeded his jurisdiction in awarding these claims, which
were never raised by the respondent. Accordingly, the award made on
items 2/1(a) and 2/1(b) mentioned at Sl. Nos.13 and 14 of statement
No.II at internal page 76 of award stands modified and reduced by
Rs.6,36,480/- and Rs.7,18,046/- respectively.
19. The next submission of Mr. Narula is in relation to the award
made on Item 2(a), which pertain to earth work done for banking. The
learned arbitrator has awarded an amount of Rs.4,97,199.51 in
Statement No.I of the award under this claim. The learned arbitrator
has awarded the aforesaid amount for the quantity 2167.37 cu mtr @
Rs.23 per cu mtr. The discussion on the award on this particular
aspect reads as follows:
"The Claimant in the final bill in respect of agreement item No.2(a) has shown only a quantify of 15,169.91 Cu. M. and out of this quantity 4788.00 Cu. M. is shown payable at the agreement rate of Rs. 23.00 per Cu. M. and another quantity of 10381.91 Cu. M. @ Rs. 16.44 per Cu.M.
It was explained by the respondent that the total quantity excavated by the Respondent is 31,098.98 Cu. M. under agreement item No. 1(a)(i), (ii), 1(b) and 1(c). Out of this total quantity 9481.61 Cu. M. is shown payable under extra item No. 3/I(b), having been transported up to a lead of 6 Km. thus, leaving the balance quantity of 21617.37. This quantity was disposed of by the Respondent as per item No.2 of the agreement. It was thus submitted that under agreement item No.2 the quantity payable is 21617.37 Cu. M. and not 15,169.91 Cu. M. The Claimant has not only shown the less quantity but also the rate of Rs.16.44 per Cu. M. payable for a quantity of 10381.91 Cu. M. in the final bill."
20. The submission of Mr. Narula is that in the 18th RA bill, quantity
of 151611 cu mtr was paid vide MD 4484. This was accepted by the
respondent by acknowledging that the bill and measurement are
accepted. He submits that this work of banking had to be done with
soft/loose soil excavated under item 1(a) and 1(b). However, it is not
that the entire soft soil excavated under item 1(a) and 1(b) was utilized
to carry out the work under item No.2(a). The respondent had taken
out a part of the excavated soft earth from the work site, and under
extra item 3(a) and 3(b), the contractor had been allowed the
transportation charges for earth for leads upto 1 km and 6 km
respectively. Mr. Narula submits that the earth which was transported
upto 1 km and 6 km leads respectively should have been excluded
from the quantity assumed to have been utilized for purpose of
banking under item 2(a). He submits that only those quantities which
were removed under item 3(b) (i.e. upto a lead of 6 km), amounting to
9481.61 cu mtr had been excluded, and the earth removed under item
3(a) (i.e upto a lead of 1 km) amounting to 6148.11 cu mtr has not
been excluded from the total quantity of earth work for banking,
claimed to have been excavated by the respondent under item 2(a).
He submits that the learned arbitrator has merely proceeded on
approximations and has disregarded the actual quantity of banking
work done under item 2(a) which amounted to 15169.91 cu mtr as per
measurement. In this regard, he places reliance on the measurements
recorded in the various running bills such as 14th, 15th, 16th, 17th and
18th RA bills, where, consistently, the said figure 15169.91 cu mtr has
been mentioned and accepted by the respondent.
21. On the other hand, learned counsel for the respondent submits
that under the contract in question, the respondent was required to
carry out the work within the period of 15 months. Consequently, the
respondent was expected to face only one flood. In reality, the
respondent faced three floods as the work prolonged for over three
years and the work in embankment had to be redone thrice over after
each flood. She submits that the respondent had repeatedly raised a
grievance with regard to the less recording and non recording of the
quantities in the measurement book.
22. A perusal of the award made in respect of item 2(a) shows that
the learned arbitrator has not examined various aspects, such as the
recording made in the various RA bills with regard to the quantity of
work done under item 2(a); the issue whether the quantities allowed
under item 3(a) should also have been excluded from the total
quantity of earth work done or not for the purpose of item 2(a);
whether the quantity claimed by the petitioner as 15169.91 cu mtr was
the actual work done under item 2(a) or not, and; whether the quantity
of ordinary rock covered by item 1(c) has been included and if so,
whether it could have been included in the work under item 2(a).
23. Though learned counsel for the petitioner also raised a question
about the rate of Rs.23 per cu mtr awarded by the learned arbitrator
for the work done under item No.2(a), I am not inclined to agree with
his submission on that aspect and the rate of Rs.23 per cu mtr
appears to be correctly adopted as that was the contractual rate. Even
for the extra quantity, the said rate would have been applicable under
the contract.
24. As the submissions of the rival parties have not been properly
examined by the learned arbitrator, the award made in respect of item
2(a), in my consideration, needs to be re-determined. The award made
on item No.2(a) is remitted back to the learned Arbitrator for fresh
adjudication.
25. The next submission of Mr. Narula is in respect of award made in
relation to agreement Item No. 35. Item No. 35 of the agreement
reads as follows:
"35. Providing and fixing in position 25mm dia and 1500mm long rock bolts conforming to I.S. 1786 including drilling up 1.5 m in rock, water jet cleaning and grouting, cutting etc. complete as per direction of Engineer in Charge."
26. The contractual quantity of this item as shown in the B.O.Q., was
1734 Kgs. The contractual rate earlier fixed was Rs.70/- per Kg.
However, the same was mutually reduced to Rs.60/- per Kg. Upto the
18 RA Bill, the total quantity of work done under Item No. 35 was
shown as 7601.54 Kgs. Out of this 6542.38 Kgs. of the work was paid
@ Rs.60/- and 1059.16 Kgs. was paid @ Rs.35/-. It is informed that the
quantity paid @ 35/- per Kg. was on account of part-rate payment.
27. The submission of Mr. Narula is that in respect of rock bolts of
length beyond 1500mm + 20% the said work had to be treated as
falling under BOQ Item No. 13, which reads as follows:
"13. Reinforcement for R.C.C. work including straightening, cutting, bending binding and placing in position complete.
a) Cold twisted bars." 28. The submission of Mr. Narula cannot be accepted. As the
learned Arbitrator has noted in his award, the petitioner itself had
recorded the quantity of the work done under agreement Item No. 35
in the 18th RA Bill as 7601.54 Kgs. The reduction of the quantities in
the 20th RA Bill to 3750.90 Kgs could possibly not have taken place.
The two items, namely BOQ Item No. 35 & BOQ Item No. 13 are
different and distinct works. Whereas Item No. 35 pertains to providing
and fixing of 25mm dia and 1500 mm long rock bolts conforming to
IS:1786 which includes drilling up to 1.5 metres waterjet cleaning and
grouting, etc., the work to be done under BOQ Item No. 13 pertains to
reinforcement for RCC work including straightening, cutting, bending
binding and placing in position the cold twisted bars etc. Therefore,
the substantive work under Item No. 35 pertains to providing and fixing
of rock bolts and the work in relation to the fixation of those bolts,
whereas Item No. 13 pertains only to the work of reinforcement of RCC
work and other related works.
29. When the size of the rock bolts exceeds 1500 mm length, there
is no justification to reduce the rate at which the contractor should be
paid for the work done in relation to the excess length of the rock bolt.
Therefore, the rate applicable for the work done pertaining to the
excess length of the rock bolt, i.e. beyond 1500 mm + 20% could not
be reduced from Rs.60/-. The learned Arbitrator rightly awarded the
contractual rate applicable to contract item No.35 for the quantity of
1059.16 kg. The view of the learned Arbitrator cannot be said to be
either patently erroneous or implausible. I find no reason to interfere
with the award made by the learned Arbitrator in relation to the BOQ
Item No. 35.
30. Mr. Narula then submits that the quantity of work falling under
BOQ Item NO. 35 which was treated by the petitioner as falling under
Item No. 13 namely 3750.90+3850.64=7601.54 Kgs. needs to be
reduced. The total quantity for which payment under Item No. 13 of
the BOQ had been made by the petitioner was 372692 Kgs.
Ms.Rautray fairly does not object to the reduction in the quantity from
372692 Kgs by 7601.54 Kgs. Consequently, the quantity of agreement
Item No. 13 in Statement No. 1 of the award stands reduced to
365090.46. The amount payable @ Rs.16.65/- would, therefore, come
to Rs.60,78,756.16/-. The award stands modified to the aforesaid
extent as made on agreement Item No. 13 in Statement No. 1.
31. The next submission of Mr. Narula pertains to extra Item No. 1
and substituted Item No. 1, i.e. SIS No. 1. The submission of Mr. Narula
is that the cost of sand to be supplied by the respondent-contractor
was included in the rate fixed under agreement Item No. 4 which was
substituted as extra item. A perusal of the award shows that the
learned Arbitrator has, in depth, considered the facts of this case. The
discussion in the award shows that the petitioner, as per the directions
of the consultant, substituted the item of filling of excavated earth with
sand filling. The respondent demanded a rate of Rs. 165 per cubic
metre vide a letter dated 26.03.1996. Subsequently, on account of the
fact that ban on excavating sand from the river Yamuna had been
removed, the respondent reduced its demand from Rs.165 per cubic
metre to Rs. 145 per cubic metre vide letter dated 30.04.1996. The
respondent points out, and the learned Arbitrator takes note of the
fact, that the subsequent agency appointed by the petitioner was paid
@ Rs.161 per cubic metre for supply of sand and Rs.32 per cubic metre
for filling. Thus, the claim of Rs. 145 per cubic metre demanded by the
respondent was held to be justified.
32. The learned Arbitrator has taken into account the materials
produced before him and concluded that the rate of Rs.145 per cubic
metre demanded by the respondent was justified. He also observes
that there is no dispute as to the quantity of sand consumed and
utilized.
33. In the light of the aforesaid discussion found in the award, it
cannot be said that the award made by the learned Arbitrator on the
item in question is without any reason. The view taken by him is a
plausible view based on the materials and facts produced before him. I
do not find any justification for interfering with the award made on this
item either in respect of the quantity, or in respect of the rate.
34. The next objection raised by the petitioner is in respect of the
award made on agreement Item No. 26. Item Nos. 25 & 26 in the BOQ
read as follows:
"25. Supply of River Bed Boulders minimum size 22.5 cm in at least three directions including royality carriage to the site of work, loading, unloading and stacking etc. complete.
26. Dumping of stone for making protection apron to the required saction including packing and dressing of top surface with all leads and lifts (from stack to the site of work) (excluding the cost of stone)."
35. The quantity mentioned against both these items in the BOQ is
3840 cubic metres. Whereas Item No. 25 pertains to river bed
boulders of minimum size 22.5 cm, Item No. 26 pertains to the carrying
out of the specific work mentioned therein with the river bed boulders
referred to in Item No. 25. It is not disputed that no claim was made
under Item No. 25 of the BOQ for supply of river bed boulders. The
hard rock excavated at the site was used for carrying out works at item
No. 26 of the BOQ.
36. The submission of Mr.Narula is that the quantity of work done
under Item No. 26 was measured at 218.26 cubic meters as per the
20th RA Bill. Even in the 18th RA Bill, the same quantity was measured
and paid to the respondent and accepted by the respondent. The
reasoning adopted by the learned Arbitrator while allowing the claim
under Item No. 26 of the BOQ for the 1449.31 cubic meters is that
1449.31 cubic meters of hard rock was excavated and whole quantity
was dumped by the contractor for making the protection apron as
required under Item No. 26. The learned Arbitrator has proceeded on
the basis that the petitioner had not shown any document that the
quantity over and above 218.26 cubic metres (which quantity was
used, even according to the petitioner, for carrying out works under
Item No. 26) was taken away by the contractor from the site for use
somewhere else. The submission of the petitioner is that it could not
be assumed that the entire quantity of hard rock excavated under Item
No. 1(d) of the BOQ was utilized for carrying out work under Item No.
26.
37. Ms. Rautray, learned counsel for the respondent, on the other
hand has submitted that even the respondent had issued
communications stating that the excavated hard rock has been
dumped by the contractor for making the Coffer Dam. Pertinently, the
petitioner has not explained as to what happened to the balance
quantity of the hard rock excavated by the respondent. It is also not
disputed that 1449.31 cubic meters was the total quantity of the hard
rock excavated. Pertinently, the quantity of river bed boulders as per
the BOQ required for execution of the contract was 3840 cubic meters.
How then the contractor could have constructed the Coffer Dam with
only 218.26 cubic meter of the rock, which is only a small fraction of
the 3840 cubic metres, is difficult to understand. I, therefore, find that
the award made by the learned Arbitrator is plausible and reasonable
and does not call for interference. This objection is rejected.
38. In relation to the award made on the item Sl. No. 17 in Statement
No. 2 of the award, learned counsel for the respondent concedes that
the said award may be set aside. Accordingly, the award made under
Sl. No. 17 Statement No. 2 for Rs. 35797.50 is hereby set aside.
39. The submission of Mr. Narula, learned counsel for the petitioner
in relation to the Award made on Item Serial No.15 is that the
Agreement item provided for rich mix of concrete cement in the ratio
of 1:2:4. According to him, the Agreement did not provide for laying of
staircase with richer mix of concrete in the ratio 1:1.5:3 RCC.
However, a perusal of the Award shows that the learned Arbitrator has
relied upon the drawings provided by the petitioner to the respondent
for execution of the works. The said drawing has also been shown by
learned counsel for the respondent to Mr. Narula, and the same indeed
shows that the staircase had to be constructed using the concrete
mixture in the ratio 1:1.5:3 RCC. In view of this position, I find no merit
in the objection raised by the petitioner. The same is accordingly
rejected.
40. In relation to the Award made on Item Serial No.18, i.e. de-silting
for excavation and de-watering after monsoon season for the year
1995, 1996 and 1997, the submission of Mr. Narula is that the
stipulated date of start of work was 11.5.1995 and stipulated date of
completion was 10.8.1996. Therefore, two monsoon seasons, that is,
of the years 1995 and 1996 were covered under the contract and it
was the responsibility of the respondent/contractor to build and
maintain the height of the Coffer Dam so that the working area was not
flooded. Mr. Narula has placed reliance on condition Nos. 21 and 34 of
the Specifications and Special Conditions, which read as follows:-
"Condition No.21: Nothing extra shall be paid on account of de-watering sometimes at greater depth, the sub-soil water rushes out with great speed in form of springs tidals or river seepage broken water mains/drains etc. Nothing extra shall be paid for bailing out that water other than the provision made in the schedule under different items." Condition No.34: Coffer dam shown in the drawing is indicative only. The contractor is advised to design his own section or suggest alternatives such that all key activities of raising the structures to appropriate heights before the onset of monsoon are completed."
41. He submits that the learned Arbitrator, while making the Award,
did not note the fact that two monsoon seasons were covered and,
secondly, it was the responsibility of the respondent to make and
maintain the coffer dam at the proper height. He submits that the
petitioner never prevented the respondent from raising the height of
the Coffer Dam to prevent flooding in the working area.
42. On the other hand, the submission of learned counsel for the
respondent is that the respondent was not permitted to raise the
height of the Coffer Dam. The petitioner was not willing to measure
the height of the Coffer Dam beyond 204 GTS. Ms. Rautray has
referred to the communications dated 24.1.1998 and 4.4.1998 of the
petitioner in this regard. She also refers to the communication dated
2.3.1998 of the respondent issued to the Engineer Member, DDA. In
the communication dated 24.1.1998, the DDA, inter alia, recorded that
"The Cofferdam RL were fixed at 204 GTS and therefore in the
circumstances when the water level was 203 GTS or near to it the work
is possible to take up after protection of the cofferdam." In the letter
dated 4.4.1998, the petitioner had recorded "the water level was noted
down approx. 203.30 GTS. The height of the cofferdam shall be
maintained at 204 GTS strengthen for which it was paid and
dewatering shall be restarted." The communication dated 2.3.1998 of
the respondent reads as follows:-
"Dear Sir I personally wanted to meet you in respect of above said project earlier specifically wanted to send fax messages on Saturday & Sunday but your fax was off connection, although the Cofferdam constructed in 1996 was raised up to 206 GTS level, inspite of repeated request & so verbally agreed by C.E, E.Z & S.E, C.C-10. The level was never again allowed to be raised beyond 204 GTS, because the instruction was not confirmed in writing. Only 10 days earlier the matter was reported to S.E,C.C-10 regarding flash flood increasing 204 level, but no remedial instruction were issued. On Saturday 28th of Feb when our excavation in last reach R.D.128 to 150 was complete, there came a flash flood, night of 28th Feb & 1st March with level 204.50 GTS which could only be saved if the Cofferdam is at least 205.50 GTS to avoid breach. I suffered a loss of `1.75 lacs over due to this negligence although the same has been suffered number of times earlier.
No action has been taken so far regarding instructions & decisions to be taken by all concerned inspite of yours and Worthy V.C. instruction specifically meeting at site since 7.2.98, which is highly regretted. Request & an immediate interview in your office at the earliest." (emphasis supplied)
43. A perusal of the impugned Award shows that the learned
Arbitrator has observed that "as per record placed before me that the
respondent was not allowed to increase the height of the Coffer Dam
beyond 204 GTS and flood level in all these years was 207 GTS to
208.4 GTS."
44. The interpretation of documents falls within the realm of the
Arbitrator. From the correspondence between the parties, it does
indeed appear that the petitioner was insistent that the Coffer Dam
level should be maintained at 204 GTS for which the respondent was
being paid. It appears that the petitioner insisted on maintaining the
level of the Coffer Dam at 204 GTS even though the flood in the years
1995, 1996 and 1997 was beyond 204 GTS, that is, 207 GTS to 208.4
GTS. The submission that the learned Arbitrator has ignored the
factum that the contractor was obliged to maintain the Coffer Dam
during the flood seasons of 1995 and 1996 appears to be meritless.
After each flood (when the working area was flooded), the contractor
had to resort to de-watering and de-silting which included the years
1995, 1996 and 1997. This objection is, therefore, rejected.
45. The next submission of Mr. Narula in relation to the Award made
on Item Serial No.18 is that the learned Arbitrator has not given any
basis for arriving at the awarded amount of Rs.2,50,000/- for the first
year, that is, 1995 and Rs.1,50,000/- for the two subsequent years,
that is, 1996 and 1997.
46. I may note that the learned Arbitrator is a technically qualified
person having a Civil Engineering Diploma. He was a Superintending
Engineer with the petitioner-DDA having sufficient experience.
Moreover, the learned Arbitrator has taken note of the fact that M/s.
Swastic Construction Company, who was subsequently awarded the
balance work was paid Rs.22,91,330.78 for de-watering and de-silting,
the same work site. Considering the aforesaid aspects, I am not
inclined to interfere with the Award made on Item Serial No.18 as it
cannot be said that the Award made by the learned Arbitrator is
without reasons or not plausible. This objection is, therefore, rejected.
47. The next submission of Mr. Narula is in relation to the Award
made towards escalation under Clause 10cc. He submits that on
account of a part of the Award being set aside, the calculation of the
claim awarded under Clause 10cc needs to be re-determined. On the
other hand, the submission of Ms. Rautray is that the claim made by
the respondent towards escalation under Clause 10cc was only
Rs.8,92,611.42, even though as per calculations the Award to which
the respondent was entitled under Clause 10cc was Rs.13,15,011.45.
She has referred to the brief submissions dated 19th August, 2008 of
the respondent filed before the learned Arbitrator. She submits that
even if the items on which the Award of the Arbitrator has been set
aside were to be excluded, the Award made towards escalation under
Clause 10cc would not call for re-calculation.
48. Having heard learned counsel for the parties, I am of the view
that it would be appropriate that in view of the fact that the Award on
some of the claims has been set aside and remanded back to the
learned Arbitrator, the Arbitrator should re-calculate the amount due to
the respondent towards escalation under Clause 10cc. Accordingly,
the award made on claim under clause 10cc is set aside and remanded
back for recalculation in the light of this judgment.
49. The next objection raised by Mr. Narula is to the award of
`14,09,353/- under Issue No.7 which was to the effect:
"Whether the respondent is liable towards loss of profitability to the tune of `14,09,534.90?"
50. The value of the work awarded to the respondent was
`3,53,32,387/-. The value of the work executed by the respondent was
`2,12,36,837/-. The balance value of the work which could not be
executed, because of the illegal recession of the contract by the
petitioner was `1,40,95,550/-. The respondent claimed loss of profit to
the extent of 10% of the balance value of the work which could not be
executed on account of illegal recession, and the same has been
awarded by the learned Arbitrator. The learned Arbitrator while
awarding the said amount relied upon the decisions of M/s. A.T. Brij
Paul Singh & Bros. v. State of Gujarat; AIR 1984 SC 1703 and also
the decision of a Division Bench of this Court in DDA Vs. Polo Singh,
101 (2002) DLT 401.
51. The submission of learned counsel for the petitioner is that
Clause 13 of the General Conditions prohibits the raising of any claim
by the contractor on account of recession of the contract or part
thereof, on the ground that the contractor could not execute the
rescinded work. Clause 13 of the General Conditions of Contract reads
as under:-
"Clause 13. If at any time after the commencement of the work the Authority shall for any reason whatsoever not require the whole thereof as specified in the tender to be carried out, the Engineer-in-Charge shall given notice in writing of the fact to the contractor who shall have no claim to any payment of compensation whatsoever on account of any profit or advantage which he might have derived from the execution of the work in full, but which he did not derive in consequence of the full amount of the work not having been carried out, neither shall he have any claim for compensation by reason of any alterations
having been made in the original specifications, drawings, designs and instructions which shall involve any curtailment of the work as originally contemplated. Provided that the contractor shall be paid the charges on the cartage only of materials actually and bona fide brought to the site of the work by the contractors and rendered surplus as a result of the abandonment or curtailment of the work or any portion thereof and then taken back by the contractor provided however that the Engineer-in-Charge shall have in all such cases the option of taking over all or any such material at their purchase price or at local current rates whichever may be less. In the case of such stores having been issued from D.D.A. Stores and returned by the contractor to D.D.A. Stores, credit shall be given to him by the Engineer-in-Charge at rates not exceeding those at which they were originally issued to him, after taking into consideration and deduction for claims on account of any deterioration or damage while in the custody of the contractor and in this respect the decision of the Engineer-in-Charge shall be final." (emphasis supplied)
52. Mr. Narula places reliance on a decision of this Court
rendered in M/s. Kalyan Chandra Goyal & Co. V. Executive
Engineer, Southern Western Division-8, Delhi Development
Authority, CS (OS) No.765/2009 decided on 13.12.2010 which was
also argued by Mr. Narula on behalf of the DDA. He submits that in
that case, this Court had set aside the Award made by the Arbitrator
whereby he awarded damages towards loss of profit on the
quantum of work which remained to be executed on account of
recession of contract by the DDA, which too was found to be illegal.
53. I had considered, in the course of that judgment, various
decisions relied upon by the parties and held as follows:-
"25. Having considered the submissions and perused the judgments of the Supreme Court in Ramnath International Construction (supra) and G. Ramchandra Reddy (supra), I find merit in the submission of Mr. Narula. In my view, it cannot be said that the ratio in the judgment of G. Ramchandra Reddy (supra) is that the entitlement
to claim damages cannot be denied on the ground of contractual clauses. Moreover G. Ramchandra Reddy (supra) was rendered without considering the decision in Ramnath International Construction (supra) or the earlier decisions cited in that decision in the cases of Associated Engineering Co. (supra) or Ch. Ramlinga Reddy (supra). The decision in Ramnath International (supra), on the other hand, contains a detailed discussion on the very issue in question. I, therefore, reject the submission of Mr. Aggarwal founded upon decision in G. Ramachandra Reddy (supra).
26. A perusal of the judgment in A.S. Sachdeva (supra) shows that the court rejected the reliance placed on the decisions in M.L. Mahajan (supra); J.C. Budhiraja (supra); and Republic Construction Co. v. DDA in CS (OS) No.454/2009 decided on 13.07.2009, on the basis of, what the learned single Judge held, to be the ratio of the decision in G. Ramachandra Reddy's (supra) case. However, as I have already discussed, the decision in G. Ramachandra Reddy (supra), cannot be held be lay down that entitlement of damages cannot be denied on the ground of contractual clause. The decisions in Ramnath International Construction (supra), Associated Engineering Co. (supra) and Ch. Ramlinga Reddy (supra) were not brought to the notice of this court which decided A.S. Sachdeva (supra).
27. The decisions cited by Mr. Narula in the case of J.C.Budhiraja (supra) and M.L. Mahajan (supra), in my view, squarely apply in the facts of the present case.
28. Pertinently, Mr. Aggarwal has not, on a reading of clause 13, disputed that the said clause would bar the claim as made under claim no.5. In the face of clause 13 of the agreement, the award made on claim no.5 cannot be sustained, inasmuch, as, clause 13 specifically provides that "the contractor ... ... ... shall have no claim to any payment of compensation whatsoever on account of any profit or advantage which he might derive from the execution of the work in full, but which he did not derive in consequence of the full amount of the work not having been carried out ... ... ...". The same is, accordingly, set aside.
29. In response of submission of Mr. Narula objecting to the award made on claim no.8, Mr. Aggarwal submits that this court in A.S. Sachdeva (supra) has also considered the same clauses of the contract and rejected the reliance placed thereon by the objector DDA.
30. I have already discussed hereinabove the decision in A.S. Sachdeva (supra). In the light of the decision of the Supreme Court in Ramnath International Construction
(supra), no reliance can be placed on A.S. Sachdeva (supra) for the proposition that the contract cannot provide for non-payment of damages if the same are allowable in law. The Plaintiff did not challenge the validity of any of the contractual clauses before the learned Arbitrator. This dispute cannot be raised at this stage. Consequently the clause 1 of the additional specifications and clause 10 of the conditions of contract are liable to be enforced and given effect to. As already noticed, clause 1 squarely provide that if a part of the site is not available for any reason, or there is some unavoidable delay in supply of materials stipulated by the department, the programme of construction shall be modified accordingly, and the contractor shall have no claim for any extras or compensation on this account. Clause 10 of the conditions of contract provides that the contractor shall in no case be entitled to compensation or damages on account of any delay in supply or non supply of any materials and stores. As the learned arbitrator has rendered his award in contradiction of the aforesaid clauses, he has acted beyond his jurisdiction and has misconducted himself. Consequently the award made on claim no.8 cannot be sustained. "
54. In support of his submission, Mr. Narula has also placed reliance
on M/s R.B.Chy.Ruchi Ram Khattar & Sons V. Delhi
Development Authority, 1997(1) Arb.LR 372 and decision of the
Supreme Court in Bharat Cooking Coal V.L.K.Ahuja, (2004) 5 SCC
109. He submits that the award on issue no.7 is not founded on any
material or evidence of actual loss, and is only premised on the finding
of breach of contract by the petitioner and assumed loss of profit. He
submits that the respondent should have pleaded and established that,
had the contract not been rescinded, the Contractor would have
utilized his time in carrying out another contract.
55. On the other hand, learned counsel for the respondent has
submitted that the Division Bench decision in Polo Singh (supra) was
not placed before this Court while deciding M/s. Kalyan Chandra
Goyal (supra). She submits that the said Division Bench judgment, in
turn, inter alia, takes note of earlier judgments including the one
rendered by the Supreme Court in Karsandas H. Thacker V. The
Saran Engineering Co. Ltd, AIR 1965 SC 1981, wherein it was held
that a party is liable to be compensated for breach of contract by the
other party, on account of direct loss of profit. She further submits
that clause 13 of the General Conditions of Contract contemplates a
situation where the scope of the work itself is reduced, i.e. the
employer DDA decided not to get a part of the work done-not just
through one or the other contractor, but not at all. Clause 13 does not
cover a case like the present, where the scope of the work remains
unchanged but the Contractor is prevented from carrying out the
entire work on account of illegal recession of the contract, and the
work is then got executed through another contractor. She submits
that in the present case there was no reduction in the scope of the
work inasmuch, as, the petitioner did not take a conscious decision
after the award of the contract to the respondent, to not to get certain
part of the work done at all. In fact, after the illegal recession of the
respondent's contract, the petitioner proceeded to get the balance
work executed from another contractor.
56. Having considered the submission of learned counsels, I am of
the view that the decision rendered by me in Kalyan Chandra
(supra), in so far as it dealt with the award made by the learned
Arbitrator towards loss of profit on the quantum of work which
remained to be executed on account for illegal recession of the
contract, appears to be erroneous, for more than one reasons, and
cannot come to the aid of the petitioner.
57. Firstly, the decision of the Division bench of this Court in Polo
Singh (supra) was not brought to the notice of this Court, which
specifically deals with the law on the aspect of award of damages on
account of breach of contract by one of the parties under Section 73 of
the Contract Act. In Polo Singh (supra), the Division Bench held as
follows:
"15. The arbitrator, taking note of the fact that the rescission of the contract by the appellant-Authority having already been held in his earlier award dated 26.12.1992 as legally unjustified, allowed the claim of the respondent/claimant on account of loss of profit to the extent of Rs. 12,35,742/- in view of his finding as stated hereunder. ... .... ...."
16. To justify award of damages on account of loss of profit, a finding adjudging rescission of the contract as illegal is essential. The quantum of damages to be awarded in a particular case is another point for consideration... ... ... " ... .... ...... .... ...... .... ...... .... ...... .... ...... .... ...... .... ...... .... "18. The award dated 4.3.1998 clearly spells out the reasons for awarding the aforesaid amount on account of damages for loss of profit. The arbitrator took note of the entire relevant facts and the materials placed before him by the parties, and made his award in the light of observations occurring in the earlier judgment dated 30.5.1997 is evident on a bare perusal of the same. The plea to the effect that the award is base don no evidence is, therefore, totally unfounded.
19. Adverting to the point relating to award of compensation reference may be made to a decision in "A.T. Brij Paul Singh & Brothers v. State of Gujarat" AIR1984SC1703 , wherein while interpreting the provisions of Section 73 of the Indian Contract Act, 1872, the Supreme Court held that where the party entrusting the work commits breach of contract by improperly rescinding the contract, the contractor is entitled to claim damages for loss of profit which he expected to earn by undertaking the works/contract. Speaking on measure to evaluate the amount of damages, it was observed:
"What would be the measure of profit would depend upon facts and circumstances of each case. But that there shall be a reasonable
expectation of profit is implicit in a works contract and its loss has to be compensated by way of damages if the other party to the contract is guilty of breach of contract cannot be gainsaid..."
20. In "Mohd. Salamatullah and Anr. v. Government of Andhra Pradesh" AIR1977SC1481, where the trial court awarded damages for breach of contract @ 15% and the High Court, in appeal, reduced the same from 15% to 10% of the contract price, the Supreme Court held that the appellate court was not justified to interfere with the finding of fact given by the trial court regarding quantification of the damages even if it was based on guesswork.
21. In yet another decision in "Dwarka Das v. State of Madhya Pradesh and Anr." [1999]1SCR524 , where the appellant was in response to the tenders invited by the respondent/State, allotted the work for construction of a hostel within a specified period, in different phase, failed to complete the work within the time schedule and the contract executed between the parties was rescinded by the respondent/State on the ground of non-completion of work within the stipulated time, and the appellant made a claim of Rs. 20,000/- as damages contending that the termination of the contract was in breach thereof and the suit in this respect was decreed by the trial court in favor of the appellant, which was, however, disallowed by the High Court, in appeal, as the appellant was found to have not placed the material on record to show that he had actually suffered any loss on account of the breach of contract, setting aside the judgment of the High Court, the Supreme Court held:
"The appellant had never claimed Rs. 20,000/- on account of alleged actual loss suffered by him. He had preferred his claim on the ground that had he carried out the contract, he would have earned profit of 10% on Rs. 2 lakhs which was the value of the contract....."
".....it follows, therefore, as and when the breach of contract is held to have been proved being contrary to law and terms of the agreement, the erring party is legally bound to compensate the other party to the agreement. The appellate Court was, therefore, not justified in disallowing the claim of the appellant for Rs. 20,000/- on account of damages as expected profit out of the contract which was found to have been illegally rescinded."
58. Section 73 of the Contract Act itself was not even alluded to, by
learned counsel for the respondent in that case, while making his
submissions on the aforesaid issue.
59. Section 73 of the Contract Act reads as follows:-
"73. Compensation for loss or damage caused by breach of contract.-
When a contract has been broken, the party who suffers by such breach is entitled to receive, from the party who has broken the contract, compensation for any loss or damage caused to him thereby, which naturally arose in the usual course of things from such breach, or which the parties knew, when they made the contract, to be likely to result from the breach of it.
Compensation for failure to discharge obligation resembling those created by contract.- When an obligation resembling those created by contract has been incurred and has not been discharged, any person injured by the failure to discharge it is entitled to receive the same compensation from the party in default, as if such person had contracted to discharge it and had broken his contract."
60. The parties cannot contract out of Section 73 of the Contract Act.
Section 73 is in imperative terms. Therefore Clause 13 of the General
Conditions of Contract, for it to be saved from the vice of voidity under
Section 23 of the Contract Act would have to be read down and would
have to be read in the context.
61. The submission of Ms. Rautray that Clause 13 can be invoked in
a case where the scope of the work that the DDA intends to get
executed itself is reduced i.e. the DDA consciously takes a decision not
to get the entire contracted work executed- not only through the
appointed Contractor but through any other Contractor as well,
appears to be a correct reading of the said clause. The purport of
Clause 13 indeed appears to be to restrict the right of the Contractor to
claim damages in a situation where the DDA decides not to get the
entire work executed at all. It does not pertain to cases where the
contract is rescinded midway illegally, and on that account the
Contractor is prevented from executing the balance work, and the said
balance work got executed through another contractor.
62. Another important aspect which appears to have escaped the
attention of the Court while deciding M/s. Kalyan Chandra Goyal
(supra), is the fact that the line of decisions in Steel Authority of
India v. J.C. Budhiraja, AIR 1999 SC 3275; M.L. Mahajan v. Delhi
Development Authority, 76 (1998) DLT 701; Continental
Construction Co. Ltd. v. State of Madhya Pradesh, AIR 1988 SC
1166; Ramnath International Construction Pvt. Ltd. v. Union of
India, 1 (2008) SLT 82; Associated Engineers Co. v. Govt. of
Andhra Pradesh, 1991 (4) SCC 93; Ch. Ramalinga Reddy v.
Superintending Engineer, 1999 (9) SCC 610, relied upon by the
Court, were cases where the right of the Contractor to claim damages
for delay in performance of its obligations by the employer, which, in
turn, resulted in delay in execution of the work, leading to extension of
the contractual period had been limited contractually.
63. In my view, those are different situations, than the situation
where the contract is illegally rescinded and the balance work is got
executed through another contractor. A Contractor is not obliged to
carry out the work beyond the stipulated date of contract. If the
execution of the contractual work is delayed for reasons attributable to
the employer or for reasons not attributable to the contractor, he has
two options. He may either choose to put the contract to an end and
claim damages for breach of contract by the employer, or he may
agree to continue to carry on the work by accepting the extension of
time and giving up his right to claim damages for such delay, because
he may find it more profitable to execute the balance work, even after
delay, than to claim damages by putting the contract to an end.
Therefore, a contractor who has opted to continue to execute the work,
even though its execution is delayed for reasons attributable to the
employer or for reasons not attributable to him may, contractually, be
prohibited from claiming any damages due to the delays, as aforesaid.
He cannot claim damages because he has been put to prior notice that
he would not be entitled to claim damages for such delays and would
be entitled only to claim extension of time for completion of the
contractual work. He, therefore, exercises his option consciously, if he
still chooses to carry out the work, despite the delays, as aforesaid. He
is, therefore, bound down by the option he makes. However, when the
contract is illegally determined, there is no option given to the
contractor. He has no option but to claim damages.
64. The observations of the Supreme Court in G. Ramachandra
Reddy & Co. v. Union of India, (2009) 6 SCC 414 to the effect: "The
question as to whether damages were payable for illegal termination of
contract cannot be a subject matter of contract" - have their genesis in
Section 73 of the Contract Act. G. Ramachandra Reddy (supra)
was, in fact, a case dealing with a similar situation, i.e. where claim of
damages for illegal termination of contract was opposed by relying
upon a contractual clause. The Supreme Court brushed aside the said
reliance by observing that as to whether damages are payable for
illegal termination, cannot be contractually provided. Therefore, G.
Ramachandra Reddy (supra) is squarely applicable to the present
case. In Kalyan Chandra Goyal (supra), the distinction between G.
Ramachandra Reddy on the one hand, and the other line of decisions
(dealt with in para 62 above) on the other hand was not brought out
and properly appreciated.
65. For the aforesaid reasons, reliance placed by Mr. Narula on M/s.
Kalyan Chandra Goyal (supra) appears to be of no avail, as that
decision appears to have proceeded on an erroneous premise.
66. The decisions in Ruchi Ram (supra) and Bharat Coking Coal
(supra) are also of no avail. A perusal of Ruchi Ram (supra) shows
that the claimant had raised a claim towards loss of damages due to
delays, defaults and breaches of contract by the DDA. The said claim
was divided into two parts, namely (a) loss of profit due to reduction in
scope of the work; (b) loss of profit due to long stay at site.
Pertinently, the Arbitrator had himself rejected the first part of the said
claim i.e on account of loss of profit due to reduction in scope of work.
It was only the second part of the claim i.e loss of profit due to longer
stay at site which was the matter for consideration before the Court.
Therefore, the issue with regard to the maintainability of claim (a)
above did not even arise for consideration of the Court.
67. In Bharat Coking Coal (supra), the Supreme Court was
considering the claim of a different nature than the one in question.
The claim under consideration was for loss of profit arising out of
dimunition in turnover on account of delay in the matter of completion
of the work. It was not a claim for loss of profit on account of illegal
recession of the contract midway, towards profit that the Contractor
would have earned, had the Contractor been allowed to execute the
entire contracted work. While dealing with the aforesaid claim, the
Supreme Court held that what the Contractor should establish in such
a situation is that, had he received the amount due under the contract,
he could have utilized the same for some other business in which he
could have earned profit. Unless such a plea is raised and established,
claim for loss of profit could not have been granted. As aforesaid, that
is a different head of claim from the one under consideration in this
case. This aspect has been considered by the Division Bench in detail
in Polo Singh (supra).
68. For the aforesaid reasons, the objection to the award of
`14,09,535/- does not call for interference as it cannot be said that
there is anything illegal, much less a patently illegality in the said
award.
69. The next submission of Mr. Narula is in relation to the award
made under issue no.5 i.e towards infructuous expenditure and
overhead expenditure. The respondent-claimant had raised a claim of
`6 lakhs under this head and has been awarded an amount of
`4,50,000/- by the Arbitrator. The submission of Mr. Narula is that the
said award could not have been made and was prohibited under clause
10 of the General Conditions as well as clause 1 of the specifications
and conditions. He further submits that the learned Arbitrator has not
given the basis on which he has arrived at a figure of ` 4,50,000/- and
there is no reason in the award in so far as this aspect is concerned.
70. I find no merit in the submissions of Mr. Narula. Clause 10 of the
General Conditions deals with the aspect of stores to be supplied by
the DDA. The second paragraph of Clause 10 inter alia states:
"Provided that the contractor shall in no case be entitled to any
compensation or damages on account of any delay in supply or non-
supply thereof all or any such materials and stores."
71. The delay in the execution of the work was not only on account
of non-supply of materials but also on account of non-supply of
drawings by the petitioner to the respondent. The learned Arbitrator
has found the non-supply of drawings to be a fundamental breach of
the contract.
72. So far as clause 1 of the specifications and conditions are
concerned, the same also has no relevance. The relevant part of that
clause, on which reliance has been placed by Mr. Narula reads as "if
part of site is not available for any reason or there is some un-
avoidable delay in supply of materials stipulated by the Department,
the programme of construction shall be modified accordingly and the
contractor shall have no claim for any extras or compensation on this
account."
73. As aforesaid, the primary breach on the part of the petitioner
was the non-supply of the drawings. The said aspect is not covered by
Clause 1 of the specifications and conditions. The learned Arbitrator
has noted that the stipulated date of completion was 10.08.1996.
However, the work continued thereafter till it was illegally rescinded
on 29.05.1998. During this period, the respondent executed work of a
substantial value of `1,04,67,349.91. As per the contractual terms it
was mandatory for the respondent to keep a graduate engineer at site
of work, apart from watch and ward at the site. The learned arbitrator
has relied upon audited balance-sheets filed by the respondent after
taking into account the financial statements filed by the respondent to
substantiate the said claim. He has awarded an amount of ` 4.50
lakhs. In my view it cannot be said that the amount made by the
learned Arbitrator is not founded on any evidence. He has taken into
account relevant and germane material. I see no illegality, much less
a patent illegality in the award made on issue no.5. This objection of
Mr. Narula is therefore rejected.
74. The award made on other claims which are under challenge,
have been challenged only on the aspect of rate awarded by the
learned arbitrator. I may generally note that the learned Arbitrator has
merely awarded as the final rate, the part rates granted to the
Contractor. There is no meaningful or serious challenge raised by the
petitioner. Accordingly all other objections are also rejected. The
respondents shall be entitled to costs quantified at ` 10,000/-.
VIPIN SANGHI, J
MARCH 07, 2011 "AS/SR/BSR''
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!