Wednesday, 29, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Associated Builders & ... vs M/S Sahyadri Cooperative Group ...
2011 Latest Caselaw 3523 Del

Citation : 2011 Latest Caselaw 3523 Del
Judgement Date : 25 July, 2011

Delhi High Court
M/S Associated Builders & ... vs M/S Sahyadri Cooperative Group ... on 25 July, 2011
Author: Vipin Sanghi
*      IN THE HIGH COURT OF DELHI AT NEW DELHI

                  Judgment reserved on: 15.07.2011

%                 Judgment delivered on: 25.07.2011

+      EX.P. 38/2010

       M/S ASSOCIATED BUILDERS & CONTRACTORS ..... Decree Holder
                      Through:  Mr. Sandeep Sharma, Mr. Vikash
                                Sharma and Mr. Anuj Malhotra,
                                Advocates
                 versus

       M/S SAHYADRI COOPERATIVE GROUP HOUSING
       SOCIETY LTD                          ..... Judgement Debtor
                      Through:  Mr. C.V. Francis, Mr. Amit George,
                                Mr. Arun Francis and Ms. Manpreet
                                Kaur, Advocates

                                  AND

+      EX.P. 165/2010

       SAHYADRI COOPERATIVE GROUP HOUSING
       SOCIETY LTD                         ..... Decree Holder
                     Through:  Mr. C.V. Francis, Mr. Amit George,
                               Mr. Arun Francis and Ms. Manpreet
                               Kaur, Advocates
                     versus

       M/S ASSOCIATED BUILDERS & CONTRACTORS .....
                                               Judgement Debtor
                      Through:  Mr. Sandeep Sharma, Mr. Vikash
                                Sharma and Mr. Anuj Malhotra,
                                Advocates

CORAM:
HON'BLE MR. JUSTICE VIPIN SANGHI

1.     Whether the Reporters of local papers may
       be allowed to see the judgment?             :   No

2.     To be referred to the Reporters or not?     :   Yes

3.     Whether the judgment should be reported
       in the Digest?                              :   Yes


EX.P. 38/2010 & 165/2010                                 Page 1 of 15
                             JUDGMENT

VIPIN SANGHI, J.

1. These are two execution petitions preferred in relation to and

arising out of the arbitral award dated 29.08.2009 made by Mr. Justice

R.P. Gupta (Retd.), the Arbitral Tribunal. While Execution Petition No.

38/2010 has been preferred by M/s Associated Builders & Contractors,

who acted as the contractor, Execution Petition No. 165/2010 has been

preferred by M/s Sahyadri Cooperative Group Housing Society Limited,

the Cooperative Society.

2. Before I deal with the respective submissions of the parties, I

may first set out a few relevant facts. The parties entered into a

contract on 11.10.1995, whereunder the contractor agreed to raise

construction of residential flats for the society. The work was to be

completed within 18 months. The work order was issued on

01.01.1996 and the date of completion of the work was 31.07.1997.

The Society terminated the contract on 01.01.1999. Disputes arose

between the parties. The society preferred O.M.P. No. 27/1999 before

this court to seek interim measures under Section 9 of the Arbitration

& Conciliation Act, 1996. The Contractor claimed that its dues were

outstanding. On 12.05.1999, the parties agreed that on the society

depositing Rs.39 Lakhs with the Registry of this court, it shall be open

to the society to engage another agency for completing the balance

work of the dwelling units. The court also appointed a Local

Commissioner to measure the work done by the contractor. It was

agreed that the possession of the site shall be handed over by the

contractor to the society immediately after measurement work is

completed by the Local Commissioner and after the deposit of the

amount of Rs.39 Lakhs with the Registry of this court.

3. On 29.03.2000, the said O.M.P. was taken up by the court as an

application had been preferred by the society to seek appointment of

another Local Commissioner. However, the society, with a view to

save time, withdrew its application to seek appointment of another

Local Commissioner. The court also recorded on 29.03.2000, that the

society had deposited the amount of Rs.39 Lakhs. The society was

held entitled to possession of the work site. The contractor was

directed to hand over the possession of the site within a week. In

relation to the deposit made by the society, the court directed that

"the question of entitlement to Rs.39 Lakhs lying in deposit will be

decided after the arbitration proceedings are over". The O.M.P. was

disposed of by the court.

4. Subsequently, the contractor filed I.A. No. 3027/2001 for release

of the amount of Rs.39 Lakhs deposited by the society in this court.

I.A. No. 3027/2001 was taken up for consideration by the court on

04.02.2002. The court allowed the said application and directed that

the amount of Rs.39 Lakhs deposited by the society in this court be

released to the contractor on the contractor furnishing a bank

guarantee to securitise the said amount and on furnishing an

undertaking that the contractor shall keep the bank guarantee alive

and that it will refund the amount to this court without demur as and

when required by the court.

5. I may note that the arbitration agreement was invoked by the

society a few days before the passing of the said order.

6. The order dated 04.02.2002 was challenged in appeal in FAO(OS)

No. 96/2002 without much success. It was further challenged before

the Supreme Court by filing SLP (Civil) No. 12180/2002, again, without

much success. The result was that the contractor after furnishing the

bank guarantee for Rs.39 Lakhs withdrew the said amount on

08.08.2002.

7. Before the Arbitrator, both the parties raised their claims and

counter-claims.

8. The learned Arbitrator made the aforesaid award which has been

accepted by both the parties. No objections to the award were filed by

either of them. The learned Arbitrator, after adjusting the claims and

counter-claims, which were partially allowed, awarded a net amount of

Rs.19,74,472/- as the principal liability in favour of the contractor and

against the society. He also awarded interest on the amount of

Rs.9,74,472/- from 01.01.1999 to 11.05.1999 amounting to Rs.31,671/-

The amount of Rs.10 lacs (the refundable security) was held payable

on 01.01.2000 and, therefore, was not to carry interest from

01.01.1999.

9. Thus the total amount payable under the award to the contractor

was quantified as Rs.20,06,143/-. The learned Arbitrator also held that

"the future rights between the parties after 11.05.1999 are

determinable by and within the jurisdiction of the High Court". He also

held that as to "what are the rights of the parties in respect of the

amount deposited and disbursed under the order of the High Court is

not to be decided in these proceedings but remains within the

jurisdiction of the High Court". The ultimate and effective relief

granted in the award reads as follows:

"In view of my findings on above issues, I pass an Award that the Contractor is entitled to recover from the Society a sum of Rs.20,06,143/- including interest upto 11.5.1999 when the order of deposit of Rs.39 Lacs by the Society was passed by the High Court and Society deposited as per those orders. Consequential effect of the deposit thereof and rights of the parties thereunder are within the jurisdiction of the Hon'ble High Court to decide."

10. The contractor in its execution petition has claimed that the

amount payable as on 12.05.1999 was Rs.20,06,143/-. The contractor

further claims interest @ 18% from 12.05.1999 till 01.02.2010 (the

date of filing of the execution petition) on the amount of Rs.20,06,143/-

which comes to Rs.38,91,886/-. Thus, the total amount claimed is

Rs.58,88,029/-. After granting adjustment of Rs.39 lakhs received by

the contractor, in its execution petition the contractor claims

Rs.19,88,029/-. The contractor also claims bank guarantee charges

from 08.08.2002 till 07.08.2010 quantified at Rs.3,28,233/-. Thus, final

amount claimed in the execution is Rs.23,16,262/- along with future

interest @ 10% per annum from 02.02.2010 on the amount of

Rs.23,16,262/-.

11. Mr. Sharma, learned counsel for the contractor, places reliance

on P.S.L. Ramanathan Chettiar and Ors. Vs. O. Rm. P. Rm.

Ramanathan Chettiar, AIR (1968) SC 1047, to contend that the

deposit by the society in this court and the withdrawal of the said

amount by the contractor from this court does not tantamount to

payment under the decree, and the withdrawal of such amount by the

decree holder upon furnishing of security would not prevent the

accruing of interest in favour of the decree holder. Reliance is placed

on the following extracts from this decision:

"12. On principle, it appears to us that the facts of a judgment-debtor's depositing a sum in court to purchase peace by way of stay of execution of the decree on terms that the decree-holder can draw it out on furnishing security, does not pass title to the money to the decree- holder. He can if he likes take the money out in terms of the order; but so long as he does not do it, there is nothing to prevent the judgment-debtor from taking it out by furnishing other security, say, of immovable property, if the court allows him to do so and on his losing the appeal putting the decretal amount in court in terms of Order 21 Rule 1 C.P.C. in satisfaction of the decree.

13. The real effect of deposit of money in court as was done in this case is to put the money beyond the reach of the parties pending the disposal of the appeal. The decree-

holder could only take it out on furnishing security which means that the payment was not in satisfaction of the decree and the security could be proceeded against by the judgment-debtor in case of his success in the appeal. Pending the determination of the same, it was beyond the reach of the judgment-debtor."

12. He also places reliance on an order passed by the Division Bench

of this court in Delhi Development Authority v. Saraswati

Construction & Co. in EFA(OS) No. 01/2007 dated 22.01.2009,

wherein the Division Bench referred to and relied upon the judgment of

the Supreme Court in P.S.L. Ramanathan Chettiar (supra) and other

decisions and observed as follows:

"The principal which emerges is that where a party chooses to challenge the decree before the appellate forum and the appeal court grants conditional stay, the amount deposited was only keep the portion of the decree in abeyance and the amount so deposited was not akin to a tender of the amount to the decree holder. In such a situation, the interest would not stop running. If the deposit amount in court has earned some interest, they would enure to the benefit of the judgment debtor."

13. He also places reliance on the judgment of this court in

Engineering Projects (India) Limited Vs. Arvind Construction

Company Limited, EFA(OS) Nos. 4 & 6/2008 reported as

MANU/DE/0744/2009, wherein the Division Bench of this court, inter

alia, observed as follows:

"17. .............................................Sub-rule 1 of Rule 1 of Order 21 of the said Code provides for payment to be made under the decree and the manner of the same. A deposit in Court has to be before the Court, which has to

execute the decree. The executing court is the court which passed the decree and not the appellate court. Clause (b) refers to payment out of court and the latter provision of the said clause cannot be read de hors the original provision "out of court". The object of sub-rule 1 of Rule 1 of Order 21 of the said Code is only where money is paid unconditionally in the manners provided, such payment should be treated towards the decree and that is when interest would stop as per Clauses 4 & 5 of Rule 1 of Order 21 of the said Code. The significant aspect is that these are unconditional payments towards the decree and not payments made partial or in whole for obtaining stay of the decree. We may notice that the amount has been released to the respondent on the condition of furnishing a bank guarantee and the respondent has incurred a large amount as costs towards furnishing bank guarantee in terms of averments made in the application. This is, thus, not payment towards the decree.

18. The respondent cannot charge the bank guarantee charges which bank guarantee was furnished to withdraw the amount but the payment cannot be construed as a payment towards the decree. Thus, the amounts as specified in the decree would continue to earn interest till the decision in the matter and only at the stage of the decision in appeal would the question arise of adjustments of the amount of Rs.1.5 crore towards the amount of principal and interest due thereon since at that stage on dismissal of the appeal, the bank guarantee would be discharged and the amount would be unconditionally available to the respondent."

14. On the other hand, the society in its execution petition claims Rs.

39 Lakhs along with interest @ 18% per annum on the said amount

from 08.08.2002 (the date on which the contractor withdrew the

amount of Rs. 39 Lakhs from this court) up to the date of filing of the

execution petition, i.e. 25.05.2010. After granting adjustment of the

amount claimed by the contractor of Rs.58,88,029/-, the society claims

recovery of Rs.34,85,167/- from the contractor.

15. Learned counsel for the society places reliance on Union of

India Vs. Raman Iron Foundry, (1974) 2 SCC 231, to submit that

until the making of the award there was no debt or liability on the

society to make any payment. He submits that in case this court holds

that the contractor is entitled to any interest, the same principle has to

apply to the society as well. He relies on Indian Hume Pipe

Company Limited Vs. State of Rajasthan, (2009) 10 SCC 187,

wherein the Supreme Court, inter alia, observed:

"If the appellant was not entitled to claim interest then how the respondent State would get powers or competence to receive it. Same doctrine should have been made applicable for the respondent's case also. Two persons, similarly situated, could not have been treated differently as the same may amount to discrimination."

16. He also relies on a decision of this court in Sudha Gupta Vs.

BSES Rajdhani Power Limited, MANU/DE/1426/2011, wherein the

court while quashing the demand of the respondent BSES Rajdhani

Power Limited and granting refund to the consumer had directed the

said refund with 7% interest.

17. The issue which arise for consideration is as to which of the two

parties is liable to pay to the other any amount under the award, and

the second issue is about the quantification of the amount.

18. The decisions relied upon by Mr. Sharma, learned counsel for the

petitioner, in my view, have absolutely no application in the present

fact situation. Those are all cases, where the liability had already been

adjudicated upon and, consequently, there was a debt which was due

and recoverable. However, that is not the position in the case in hand.

When the Contractors received the amount of Rs.39 lacs, there was no

ascertained liability of the Society. The principle stated by the

Supreme Court in P.S.L. Ramanathan Chettiar & Ors. (supra),

which has been followed in Engineering Projects (India) Ltd.

(supra), and Saraswati Construction & Co. (supra), has no

application in the present fact situation. The contention of Mr. Sharma

that the Contractor should continue to earn interest on the

subsequently awarded amount, even after the date of receipt of the

amount of Rs.39 lacs cannot be accepted. If the amount of Rs.39 lacs

had continued to remain in the deposit in this Court, the position would

have been different. The Contractor would have, in that situation,

continued to earn interest on the awarded amount till the date of

receipt by him of the awarded amount.

19. The Society deposited the amount of Rs.39 lacs in this Court with

a view to ensure that its construction project is not unduly held up, as

the contractor was retaining possession of the project. Under Section

9 of the Act, upon making out a deserving case, the Contractor could

have asked for security from the Society of the amount in dispute in

the arbitration. There was no admitted liability of the Society and,

consequently, no direction was passed by the Court to release any

amount, whatsoever, to the Contractor unconditionally. As aforesaid,

the amount was deposited by the Society in pursuance of the order

dated 12.05.1999 some time after 12.05.1999 and before 29.03.2000.

20. Without getting the extent of the Society's liability determined,

the Contractor on its own, and at its own peril, moved I.A.

No.3027/2001 for release of the entire amount of Rs.39 lacs lying

deposited in this Court. At the Contractors' behest, that application

was allowed and the amount of Rs.39 lacs was directed to be released

upon furnishing of a bank guarantee by the Contractor.

21. It has been found by the learned Arbitrator that the Contractor

was entitled to payment of Rs.9,74,472/- on 01.01.1999, i.e. the date

of termination of the contract. The Contractor was also entitled to

payment of Rs.10 lacs after one year, i.e. on 01.01.2000. The learned

arbitrator takes note of the fact that the amount of Rs.39 lacs was

deposited by the Society under the order of this Court dated

12.05.1999 and the amount was released under the subsequent order

dated 04.02.2002.

22. The learned arbitrator has awarded interest on the amount of

Rs.9,74,472/- upto 11.05.1999, i.e. the date of the passing of the order

by this Court requiring the Society to deposit the amount of Rs.39 lacs.

He has also held that interest for the subsequent period is a matter

within the jurisdiction of this Court. As aforesaid, while arriving at the

figure of Rs.20,06,143/-, the learned arbitrator has computed interest

on the amount of Rs.9,74,472/- from 01.01.1999 to 11.05.1999 @ 9%

p.a., i.e. Rs.31,671/-.

23. In my view, the Contractor would be entitled to interest at the

same rate, i.e. 9% p.a. on the amount of Rs.9,74,472/- from

12.05.1999 till the date of withdrawal of Rs.39 lacs by the Contractor

from this Court. On the amount of Rs.10 lacs (security deposit),

interest would accrue from 01.01.2000 till the date of withdrawal (i.e.

08.08.2002) of Rs.39 lacs by the Contractor. The said amounts add up

as follows:

i)     Interest on Rs.9,74,472/- @ 9% p.a. from

       12.05.1999 to 08.08.2002 -                        Rs.2,84,252/-

ii)    Interest on Rs.10 lacs @ 9% p.a. from
       01.01.2000 to 08.08.2002 -                        Rs.2,34,473/-
                                                         ------------------
              Total                                =     Rs.5,18,725/-
                                                         ========



24.    The    total   amount       recoverable     by   the   Contractor          as   on

08.08.2002      was        Rs.20,06,143/-   plus   Rs.5,18,725/-       is     equal     to

Rs.25,24,868/-. The amount, in fact, released to the Contractor as on

08.08.2002 was Rs.39 lacs. Therefore, the excess amount recovered

by the Contractor as on 08.08.2002 was Rs.39 lacs minus

Rs.25,24,868/- = Rs. 13,75,732/-.

25. Since the arbitrator has granted interest @ 9% on the claims of

the Contractor, in my view, it would be fair and equitable if the same

rate of interest is granted on the amount to be refunded to the Society

from 08.08.2002 onwards till the amount is so refunded.

26. The Contractor would, however, be entitled to partial payment

towards the cost of maintaining the bank guarantee. On the date on

which the Contractor received the payment, i.e. 08.08.2002, the

Contractor was entitled to receive Rs.25,24,868/-, as aforesaid.

Therefore, the bank guarantee charges incurred by the Contractor

after 08.08.2002 in respect of that amount i.e. Rs.25,24,868/- are

recoverable by the Contractor. He would, however, not be entitled to

recover the bank guarantee charges as pertain to the amount of

Rs.13,75,732/-, to which the Contractor was, in fact, not entitled.

27. The Contractor has claimed bank guarantee charges of

Rs.3,28,233/-. However, no documents have been filed on record to

substantiate the said claim. The Contractor is directed to place on

record the documents evidencing the incurring of expenditure of

renewal of bank guarantee and also to file alongwith an additional

affidavit, a computation of the said charges for the amount of

Rs.25,24,868/- within two weeks.

28. So far as the entitlement towards the interest accrued on the

amount of Rs.39 lacs, from the date of its deposit in this Court, till the

date of its withdrawal by the Contractor is concerned, the said amount,

in my view, certainly cannot be claimed by the Contractor. The said

amount has to be released in favour of the Society, as the Contractor

has been fully compensated by grant of interest for the period for

which the Contractor was found to be so entitled. I, therefore, direct as

follows:

i) The Society shall be entitled to withdraw the amount of interest

accrued on the deposit of Rs.39 lacs from the date of its deposit

till the date of its withdrawal by the Contractor, which is lying in

this Court, forthwith;

ii) The Contractor shall pay to the Society the amount of

Rs.13,75,732/- alongwith interest @ 9% p.a. from 08.08.2002 till

the date of its payment;

iii) The Contractor shall be entitled to adjustment from the aforesaid

amount stated in para (ii) above, the bank guarantee charges

incurred in relation to the bank guarantee amount of

Rs.25,24,868/- for keeping the bank guarantee alive after

08.08.2002 till date;

iv) In case the Contractor does not pay the amount, as aforesaid,

within three weeks, the bank guarantee furnished by the

Contractor shall be encahsed by the Registrar General of this

Court for the amount of Rs.13,75,732/- plus 9% interest thereon

from 08.08.2002 till the date of encashment, and the proceeds

shall be forthwith released in favour of the Society.

29. List the matter for compliance on 26.08.2011.

(VIPIN SANGHI) JUDGE JULY 25, 2011 sr/bsr

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter