Citation : 2011 Latest Caselaw 3349 Del
Judgement Date : 15 July, 2011
*IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of decision: 15th July, 2011
+ W.P.(C) 4946/2011
R.K. MACHINE TOOLS LTD. & ANR. ..... Petitioners
Through: Mr. V.N. Koura with Mr. Rakesh &
Mr. Sumit S. Benipal, Adv.
Versus
UNION OF INDIA ..... Respondent
Through: Mr. Sachin Datta & Mr. Abhimanyu
Kumar, Adv.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? Not necessary.
2. To be referred to the reporter or not? Not necessary.
3. Whether the judgment should be reported
in the Digest? Not necessary.
RAJIV SAHAI ENDLAW, J.
1. The petitioner no.1 Company of which petitioner no.2 is the
Chairman-cum-Managing Director claims to be engaged since the year
1962 in the business predominantly of manufacture of defence equipment;
it also claims to have researched and developed capability to manufacture
critical parts for the Indian Defence Industry, so that dependence on
foreign supplies could be reduced; it claims to be supplying Mortar Bomb
Bodies used in Ordnance Factories for manufacture of ammunition for the
Armed Forces, critical parts for the tanks and other heavy vehicles of the
respondent. It is claimed that as on 3 rd June, 2009 the petitioner Company
had outstanding contracts of value of `64,36,40,099/- from various
units/factories of the respondent, out of which supplies of `61,34,33,838/-
were outstanding. It is further pleaded that all the said contracts were on
the same Terms & Conditions and incorporated by reference the General
Conditions of the Contract of the DGS&D in Form 68; that neither the
General Terms & Conditions of DGS&D incorporated in Form 68 nor the
Terms & Conditions of any relevant contract contain any provision for
putting on "suspension" or "hold" any contract or the performance of any
obligation of the parties.
2. It is the case of the petitioner Company that notwithstanding the
aforesaid, the Ordnance Factory, Chanda of the respondent, vide letter
dated 3rd June, 2009 with reference to two Purchase Orders placed on the
petitioner, intimated the petitioner of the said Purchase Orders having been
"put on hold till further orders". Similar letters are stated to have been
received from the Heavy Vehicles Factory and other Ordnance Factories. It
is pleaded that in pursuance thereto neither any supplies are being received
from the petitioner Company nor any payments are being released, neither
of pending nor of completed contracts. It is yet further pleaded that even
the Bank Guarantees of the closed contracts are not being released.
3. It is yet further the plea of the petitioner Company that it is not being
considered for the award of any further contracts inspite of being the
lowest bidder.
4. The petitioner earlier filed W.P.(C) 13457/2009 in this Court
challenging the aforesaid action of the respondent. The petitioner claims
that during the pendency of the said petition it was furnished copy of FIR
and proceedings initiated by the CBI before the Court at Kolkata and in
which two of the employees of the petitioner are accused.
5. The writ petition aforesaid preferred by the petitioner was disposed
of vide judgment dated 11th February, 2010. The contention of the
petitioner Company that the orders putting on hold the contracts had been
passed in violation of the principles of natural justice was accepted and the
order putting on hold the contracts with the petitioner set aside, however
leaving it open to the respondent to proceed in a time bound manner and in
accordance with law i.e. not to take any decision without complying with
the principles of natural justice.
6. The petitioner no.1 Company admits that post the aforesaid
judgment, a notice dated 22 nd December, 2010 to show cause was received
by it. It is however the case of the petitioner no.1 Company that since the
said notice did not disclose the basis thereof, the petitioner no.1 Company
gave only an interim reply dated 12th January, 2011 thereto inter alia
demanding various particulars/documents from the respondent. It is further
stated that the said show cause notice dated 22 nd December, 2010 was
replaced by another show cause notice dated 25 th February, 2011 and to
which again an interim reply as aforesaid was given by the petitioner no.1
Company again seeking basis/particulars of the show cause notice. Other
show cause notices with respect to other contracts were also served on the
petitioner no.1 Company. It is the case of the petitioner no.1 Company that
all of them were without any basis and vague and interim replies thereto
seeking further particulars have been given.
7. The petitioner claims that without furnishing the
particulars/clarifications sought, the petitioner Company was called for a
personal hearing, first on 16 th May, 2011 thereafter on 16th July, 2011 but
on each of which occasion the petitioner Company sought adjournment
owing to the non-availability of its Advocate.
8. The petitioner Company claims to have on 30th May, 2011/2nd July,
2011/8th July, 2011 also invoked the arbitration clause in each of the
contracts and now contends that arbitration having been invoked, the
occasion for the respondent issuing show cause notice or passing any order
in pursuance thereto does not arise since the grounds on which show cause
notices have been issued are disputed and as per the agreement are to be
adjudicated by arbitration. This writ petition has been filed to restrain the
respondent from proceeding with the show cause notices issued aforesaid
without (i) furnishing the clarification/documents sought by the petitioner
Company; (ii) giving fair and reasonable opportunity of representation to
the petitioner Company; (iii) the decision of the arbitration proceedings
initiated by the petitioner Company; (iv) decision of the criminal
proceedings pending before the Court at Kolkata. The petitioner Company
has also claimed the relief of mandamus to the respondents to not withhold
or suspend deliveries or payments under the pending contract (s) and to
consider the petitioner Company in accordance with law and without
discrimination for the award of future contracts.
9. The counsel for the petitioner Company has vehemently argued that
the respondent in the manner aforesaid has put the petitioner Company out
of business resulting in immense loss to the petitioner Company, its
employees, its plant & machinery and equipment etc. It is urged that all
this has been done at the behest of the foreign suppliers of defence
equipment. It is contended that the petitioner Company has been supplying
defence equipment at a fraction of the cost demanded by the foreign
suppliers.
10. The counsel for the respondent appearing on advance notice states
that the decision pursuant to the show cause notices issued would have
already been taken had the petitioner Company availed of the hearing
granted by the respondent and the petitioner Company itself has been
seeking time and cannot blame the respondent therefor.
11. The counsel for the petitioner Company has argued under three
heads. Firstly, it is contended that non-supply of documents amounts to
violation of fair and reasonable opportunity to show cause against the
proposed action. Reliance in this regard is placed on State of Punjab v.
Bhagat Ram AIR 1974 SC 2335, Kashinath Dikshita v. Union of India
AIR 1986 SC 2118, Kumaon Mandal Vikas Nigam Ltd. v. Girja Shankar
Pant (2001) 1 SCC 182 and State of U.P. v. Saroj Kumar Sinha
MANU/SC/0082/2010.
12. Secondly, it is contended that the departmental proceedings as in
pursuance to the show cause notices issued cannot proceed simultaneously
with criminal proceedings. Reliance in this regard is placed on Delhi Cloth
& General Mills Ltd. v. Kushal Bhan AIR 1960 SC 806, Tata Oil Mills
Co. Ltd. v. The Workmen AIR 1965 SC 155, Kusheshwar Dubey v. M/s
Bharat Coking Coal Ltd. AIR 1988 SC 2118, G.M. Tank v. State of
Gujarat (2006) 5 SCC 446 and on Hoshiar Singh v. The State of Haryana
MANU/PH/0052/1970.
13. It is lastly contended that no order of black listing can be made while
arbitration regarding the same subject matter is pending. Reliance in this
regard is placed on Indian Oil Corporation Ltd. v. SPS Engineering Ltd.
128 (2006) DLT 417 (DB), National Building Construction Corporation
Ltd. v. NDMC 138(2007) DLT 414 and on Prakash Atlanta JV v.
National Highways Authority of India 169 (2010) DLT 664.
14. I may notice that the counsel for the petitioners has confined the
arguments to the show cause notice in so far as for blacklisting only and
the thrust of the argument is that till the decision of the criminal
prosecution and till the conclusion of the arbitration proceedings, no order
of blacklisting can be made. It is urged that as per the arbitration
agreement, the arbitrator is to be of the respondent only and the respondent
can appoint the arbitrator and conclude the arbitration proceedings
expeditiously and before that cannot blacklist the petitioner Company. It is
contended that the respondent should not jump the gun to blacklist the
petitioner Company even before the dispute resolution mechanism agreed
to between the parties has found the petitioner Company guilty of any
breach or violation of the agreement.
15. The petitioner Company was blacklisted as aforesaid in the year
2009, of course without any show cause notice, as found in the order in the
earlier writ petition. The said order of blacklisting was set aside vide order
in the earlier writ petition with liberty to the respondent to black list the
petitioner Company after following the procedure in law. The said
procedure is admittedly underway and is held up for reasons attributable to
the petitioners. No order of blacklisting has been made as yet. The question
which arises is, whether this Court should interfere at this stage or allow
the procedure directed by this Court in the judgment in the earlier writ
petition to be followed and completed.
16. Of the three grounds urged, the grounds of deficiency in the show
cause notice and of arbitration were not available to the petitioner
Company at the time of earlier writ petition. However the prosecution, till
the decision of which it is now argued that no black listing can be done,
had admittedly commenced during the pendency of the earlier writ
petition. The petitioner Company does not appear to have contended in the
first writ petition as is being contended now, that there can be no black
listing till the decision in the prosecution. The order in the first writ
petition has attained finality. In my opinion, it is now not permissible to the
petitioner Company to urge at least the said ground. Moreover, the Courts
have always shown reluctance to interfere at the intermediary stage of a
proceeding. If such interference is entertained, the same would result not
only into proceedings impugned being indefinitely delayed but would also
result in multiplicity of litigation with challenge being first made to the
procedure and thereafter to the final order passed. If at all there are any
deficiencies and vagueness in the show cause notices and if the respondent
inspite of demand by the petitioner Company fails to make up the said
deficiencies and proceeds to pass the order, it will be always open to the
petitioner Company to challenge the final order if made against the
petitioner Company on such grounds. In fact today it is not even known
whether the petitioner Company will be black listed or not. The respondent
is still to take a decision in this regard. It is well nigh possible (though the
counsel for the petitioner Company contends that the order of black listing
the petitioner is a foregone conclusion) that the respondent may be
satisfied with the response/defence of the petitioner Company as to the
vagueness/deficiencies in the show cause notice and/or as to no case for
black listing having been made out. In fact it is the petitioner Company
who is found to be jumping the gun and not otherwise as contended.
17. The Supreme Court in State of Punjab v. V.K. Khanna (2001) 2
SCC 330 has held that challenge at the intermediary stage can be
entertained only on the ground of bias. No bias of the decision making
authority of the respondent against the petitioner Company is pleaded in
accordance with law.
18. As far as the contention of the petitioner Company of black listing
being not permissible till the decision on the prosecution and till the
decision in the arbitration invoked by the petitioner Company is concerned,
I have enquired from the counsel for the petitioner Company as to whether,
if the said arguments were to be accepted, black listing would not become
illusory. This Court cannot gloss over the hard reality of the long time
taken in prosecution and arbitration; if it were to be held that till then no
black listing could be done, it would tantamount to a person/contractor
against whom there may be serious charges/allegations being required to
be considered for all future contracts also simply because he had invoked
arbitration proceedings or was being prosecuted or for that matter had filed
a Civil Suit. The Government as a purchaser of goods/equipments/services
cannot be put in such a situation. It is possible that if the Court is of the
view that the grounds for black listing are such which require adjudication,
the Court may in a given case observe that the order of black listing should
be deferred till the adjudication of disputes or finding of guilt. However the
general proposition as made cannot be accepted.
19. If that be the position, then without the order of black listing which
in terms of the directions in the earlier writ petition is to contain the
reasons/grounds, being before this Court, the Court is unable to apply its
mind whether the grounds of black listing are such which allow black
listing even during the pendency of adjudication before other Fora or
otherwise. Thus this petition is found to be pre-mature.
20. It cannot also be lost sight of that the petitioner Company in the
present case has invoked the arbitration at the last minute. As aforesaid, the
disputes are pending since 2009. No arbitration was then invoked. No such
plea which was available was taken in the first round of litigation. No such
plea was taken in response to the show cause notice also or while seeking
adjournments for hearing in pursuance thereto. The impression created is
that arbitration was invoked merely to avoid participating in the hearing
before the respondent pursuant to show cause notice. Such conduct of the
petitioner Company cannot be appreciated and lends me to believe that the
present petition has been filed to avoid consideration of its case by the
respondent as directed in the earlier writ petition and which is even
otherwise a right of the respondent. I may add that though it is pleaded as
aforesaid that the terms & conditions of contract do not provide for putting
on hold contracts with the petitioner but the counsel for the petitioner
Company in response to a specific query admitted the right of the
respondent to black list.
21. At this stage the contents of the show cause notices issued to the
petitioner Company may be noticed. The petitioner Company is alleged to
have paid illegal gratification to Sh. Sudipta Ghosh, former Director
General (Ordnance Factory). Clause 22 of the Terms & Conditions of
DGS&D - 68 Manual reserves a right in the respondent to cancel the
contract and all other contracts upon finding the seller/supplier to have
paid any consideration or commission to any person in the service of the
respondent. The clause provides for the decision of the respondent or his
nominee to the effect that conditions of such clause had been satisfied to be
final and binding on the petitioner Company.
22. I am of the opinion that the breach of contract on account of which
the show cause notices have been issued, besides being a breach of
contract, even otherwise is a malady which has afflicted the fabric of the
society. The country at this stage is involved in fighting the disease of
corruption and in exploring ways to combat the same. If at all the
respondents in the order to be made by them establish the guilt of the
petitioner, the petitioner cannot be allowed to continue with its business. It
is therefore deemed appropriate to await the order in pursuance to the show
cause notice aforesaid of the decision making authority of the respondents
and to only thereafter judicially review the same.
23. As far as the judgments on the aforesaid aspect cited by the counsel
for the petitioner Company are concerned, the Division Bench of this
Court in SPS Engineering Ltd. (supra) was concerned with black listing
for the reason of delay in execution of the contract; the arbitration
proceedings had been pending for considerable time when black listing
was effected for the same reason of delay in execution of the contract. It
was in this context that the order of black listing was set aside awaiting the
decision of the arbitrator.
24. The facts before the Division Bench cannot be compared with the
facts of the present case. The delay in execution of the contract affects only
the parties to the contract and not the general public and society, as
corruption does. Moreover in that case the arbitration was already
underway. In the present case arbitration appears to have been invoked
only to ward off the hearing in terms of order in the earlier writ petition.
Had the petitioner Company desired any arbitration, it would have invoked
the arbitration clause then only.
25. The position in National Building Construction Corporation
(supra) was same; in fact in that case an interim award had also been
announced and it was in this context that the order of black listing at that
stage was held to be malafide.
26. The same was the position in Prakash Atlanta JV (supra). Thus,
neither of the three judgments vehemently relied upon by the counsel for
the petitioner Company persuade me to hold otherwise.
27. Similarly, none of the judgments cited to urge that black listing
cannot be effected till the decision of the prosecution, deal with a case of
black listing and relate to disciplinary proceedings against employee and
prosecution simultaneously. The same thus have no application. I may
however add that the Apex Court in Southern Railways Officers
Association Vs. UOI (2009) 9 SCC 24 has held that acquittal in
prosecution can be no ground for setting aside the disciplinary proceedings
on the same ground.
28. The counsel for the petitioner Company agrees that none of the other
judgments cited, deal with a case of interference at the stage of show cause
notice and were concerned with challenge to the order on the ground of
proper opportunity to show cause having not been given. The same are in
consonance with whatever is observed hereinabove about reluctance of the
Courts to interfere at intermediary stage.
29. There is thus no merit in the petition; the same is dismissed. Since
the petition has been dismissed on the very first day though after full
hearing, I refrain from imposing any costs.
RAJIV SAHAI ENDLAW (JUDGE) JULY 15, 2011 Pp (Corrected & released on 29th July, 2011).
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!