Citation : 2011 Latest Caselaw 322 Del
Judgement Date : 20 January, 2011
THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment Pronounced on: 20.01.2011
+ CS(OS) No. 474/1997
M/s Bharat Electronics Limited. .....Plaintiff
- versus -
M/s Shyam Telecom Limited .....Defendant
Advocates who appeared in this case:
For the Plaintiff: Mr.H.L. Raina
For the Defendant: None.
CORAM:-
HON'BLE MR JUSTICE V.K. JAIN
1. Whether Reporters of local papers may
be allowed to see the judgment? YES
2. To be referred to the Reporter or not? YES
3. Whether the judgment should be reported YES
in Digest?
V.K. JAIN, J. (ORAL)
1. This is a suit for recovery of Rs.1,78,22,826/-.
The plaintiff is a Government company
incorporated under the Companies Act, 1956. The suit has
been instituted and plaint signed and verified by its Deputy
Manager (Personnel and Administration) Mr. M.S. Khan.
The plaintiff company is engaged in catering to the needs of
defence forces and para-military forces, by manufacturing
and supplying various professional grade electronic
equipments and is also engaged in manufacturing and sale
of various equipments such as PCM MUX (VLSI) etc. to the
private parties. It is alleged in the plaint that the defendant
approached and informed the plaintiff that it had obtained
order from the Department of Telecommunications (DOT) for
supply of 2 GHZ 30 channel digital micro wave radio
equipment and wanted to purchase 200 units of PCM MUX
(VLSI) equipment from the plaintiff for supply to the DOT.
The quotations for supply of the aforesaid equipment was
submitted by the plaintiff at the rate of Rs.74,500/- per
unit, FOR kotdwara basis, exclusive of taxes and duties,
which were to be charged at the rate prevailing at the time
of dispatch of goods. The rate of excise duty, according to
the plaintiff, at the relevant time was 20% and CST payable
against C/D Forms was 4% whereas the freight was to be
charged on actual basis. One of the terms of the quotations
submitted by the plaintiff to the defendant provided that
interest charged beyond 30 days up to 90 days shall be
equally shared by the parties. The equipments were to be
inspected by the Inspectors of the plaintiff, which already
had an inspection status issued by CGM (QA) of Department
of Telecommunications for PCM I, II, III Order MAX RAX 256
P., SBM RAX & MAX L. products. The equipments could
also be inspected by the defendant at the works of the
plaintiff before their dispatch. On receipt of quotations, the
defendant placed purchase order dated 1st February, 1995
for supply of 200 units of PCM MUX (VLSI). However, while
placing the purchase order, the defendant changed the
condition stipulated by the plaintiff in the quotation for
furnishing of bank guarantee to opening of a Letter of Credit
(LOC) for 90 days and it was also stipulated that last 60
days interest was to be shared by the parties. Regarding
inspection of the equipment, the defendant while placing the
order stipulated that DOT ( QA) inspection will be done at
the premises of the plaintiff and it will be the responsibility
of the plaintiff to get the equipment passed by DOT (QA) and
get a certificate for the same. It was further stipulated that
if it was not possible to conduct DOT (QA) testing at the
premises of the plaintiff then the same will be done at his
place and the plaintiff will help in getting it cleared by DOT
(QA).
2. It is further alleged that in response to the
purchase order, the plaintiff vide fax dated 10 th February,
1995 gave delivery schedule, which envisaged completion of
delivery of the entire equipments by 31st March, 1995 and
also set out the procedure for inspection of the equipments
before its dispatch. It was stated by the plaintiff that the
equipments would be inspected by the BEL (QA) Inspectors,
who had "Approved Inspection Status" conferred by CGM
(QA) (DOT) and based on the inspection certificate issued by
BEL(QA) Inspector, the defendant could get those
equipments cleared by DOT(QA) resident Inspector at
defendant's factory. The plaintiff also confirmed that the
Multiplexers to be supplied by it will conform to the Telecom
Engineering Centre (TEC) DOT specifications. The
defendant was requested to issue LOC for full value of the
order, including taxes, up to 90 days, with interest free
credit for 30 days and interest for balance 60 days at the
rate of 16% per annum to be shared equally between the
parties. The defendant was requested to make necessary
amendments accordingly in the purchase order issued by it.
3. In pursuance of the fax dated 10th February, 1995
sent by the plaintiff, the defendant vide its fax dated 15 th
February, 1995 raised no objection to the amendments
suggested by the plaintiff but requested the plaintiff to
complete delivery by 25th March, 1995. The defendant also
informed the plaintiff that it was in the process of opening
LOC.
4. Acting on the assurance of the defendant, the
plaintiff started production of the equipments ordered by
the defendant. In the meantime, it also arranged DOT (QA)
inspection to be carried out by the DOT (QA) resident
inspector at the premises of the plaintiff. In order to take
up inspection, the DOT (QA) inspector asked for DOT
purchase order placed on the defendant. Since the order
placed by the order placed by the DOT to the defendant was
not in possession of the plaintiff, the defendant was
requested to send a copy of the purchase order so that
inspection of the equipments by DOT (QA) Resident
Inspector Kotdwara could be carried out. Thereafter,
defendant vide fax message dated 13th March, 1995 sent a
copy of the purchase order dated 20th December, 1993. A
perusal of the order dated 20th December, 1993 revealed
that the delivery date mentioned therein was 31 st December,
1994 which had already expired. As a result, Resident
Inspector of the DOT (QA) refused to inspect the equipments
till the delivery date in the purchase order was extended.
The plaintiff, therefore, vide fax dated 16 th March, 1995
informed the defendant that delivery date mentioned in the
purchase order dated 20th December, 1993 needed to be
extended and requested the defendant to forward extension
of the delivery date to it. The defendant, however, failed to
respond to the request made by the plaintiff, which then
sent a reminder dated 22nd March, 1995 to the defendant in
this regard and again requested it to forward the LC and
letter of extension, treating the matter as most urgent. The
defendant ultimately vide fax dated 24th March, 1995, sent
copy of letter extending the delivery date up to 30 th June,
1995. The defendant also informed the plaintiff that due to
insufficiency of funds in their L/C limit, they were unable to
open the LOC and, therefore, their management had
decided to issue post dated cheques for 90 days including
interest of the last 30 days in lieu of LOC. The plaintiff was
also requested to send proforma invoices in order to enable
the defendant to prepare the cheques. The plaintiff sent
proforma invoices to the defendant for delivery of 50 units of
the equipments on 27th March, 1995, for a sum of
Rs.47,10,784/- inclusive of interest. The defendant vide its
fax dated 27th March, 1995 informed the plaintiff that the
cheque was ready and sought confirmation of dispatch of
the equipments. It was further stated by the defendant that
the cheques would be given after receiving the material. A
photocopy of the postdated cheque No.753333 dated 27th
June, 1995 drawn on State Bank of India, Industrial
Finance Branch, New Delhi for Rs.47,10,784/- was also
sent to the plaintiff. Acting on the fax dated 27th March,
1995, the plaintiff dispatched 50 units of equipments to the
defendant on 27th March, 1995. Those units had been
inspected by the DOT(QA) on 11th March, 1995, 15th March,
1995 and 18th March, 1995 and certificates to this effect
were issued by DOT (QA) on 27th March, 1995.
5. The defendant vide fax dated 28 th March, 1995
informed the plaintiff that there were certain defects in the
equipments sent to it and requested that the engineers of
the plaintiff be sent to set the equipments in order. A
meeting was accordingly held on 29th March, 1995 wherein
it was decided that the plaintiff will make the further
supplies. The plaintiff further supplied 116 equipments
between 28th March, 1995 and 31st March, 1995. All these
equipments had been finally inspected and cleared by the
DOT (QA) Resident Inspector on 28th March, 1995, 30th
March, 1995 and 31st March, 1995. Thus, in all the plaintiff
supplied 166 units of PCM (MUX) (VSLI) equipments to the
defendants by 31st March, 1995. The amount payable by
the defendant in respect of these 166 units comes to
Rs.1,55,28, 252/-, out of which the defendant has paid only
Rs.20,00,000/- vide cheque dated 15th July, 1995 leaving a
balance of Rs.1,35,28,252/-. Since the defendant has failed
to pay the aforesaid amount, the plaintiff has filed this suit
claiming a sum of Rs.1,35,28,252/- being the principal
amount and a sum of Rs.42,94,574/- towards interest upto
31st December, 1996 thereby making a total of
Rs.1,78,22,826/-.
6. The defendant filed the written statement
contesting the suit. The defendant denied authority of Mr.
M.S. Khan to institute the suit and sign and verify the
plaint. On merits, it was alleged that the equipments
supplied by the plaintiff were defective and, therefore, the
plaintiff was required to stop further shipment. The
plaintiff, however, ignored the instructions sent to it in this
regard on 28th March, 1995 and shipped the defective goods
to the defendant. It is also alleged that the plaintiff did not
adhere to the delivery schedule, which it had offered. It is
further alleged that the Government of India had placed an
order on the defendant for supply of 420 Terminals of 2 GHz
Microwaves system-30 Chl. (1+0) configuration for wireless
transmission of telephone signals between two telephone
exchanges. The tendered equipment i.e. 2 GHz MW System
- 30 Chl. (1+0) configuration comprises two important units,
one of them being Digital Microwave Radio System and the
other being 30-Channel PCM Multiplexer. Since 30-
Channel PCM multiplexer was not being manufactured by
the defendant company at that time, it proposed to buy that
equipment from the plaintiff. The payment was to be made
in full in respect of accepted quantity, including taxes and
duties and was to be made against proforma invoices within
30 days. The interest beyond 30 days and up to 90 days
was to be equally shared. A bank guarantee for full
payment was to be made before dispatch of the goods. The
defendant while placing the purchase order stipulated that
the entire delivery was to be made by 23rd March, 1995 and
50 pieces per week were to be supplied starting 1st
February, 1995. The purchase order also contained various
conditions such as training of engineers of the defendant
and free of cost repairs/replacement of the equipments. It
is also alleged that the plaintiff being a government
company, blank test certificate had been made available to
it by the Department of Telecommunications (QA). Since
the equipment in question was required to be inspected and
tested by DOT(QA), the plaintiff company made the format
of a letter offering equipment for inspection, available to the
defendant and asked it to provide sufficient number of
blank letters duly signed on behalf of the defendant and
addressed to the DOT, Camp, Bharat Electronics Limited,
Kotdwara, U.P. offering equipment for testing and clearance.
The defendant company signed 13 blank offer letters and
delivered the same to the plaintiff on 13th March, 1995. The
defendant denied that the 50 equipments dispatched on
27th March, 1995 were duly inspected by the concerned
department and alleged that the blank DOT (QA) certificates
were obtained by the plaintiff company and appeared to
have been filled up to suit the convenience of the plaintiff
without getting the equipment inspected and tested as per
DOT (QA) procedure. It is alleged that during the joint
inspection carried out on 29th March, 1995 by Mr.
Diwakaran, DGM (Mktd.) and Mr. Yudhbir Singh of
defendant, it was found that there were large number of
defects in the 50 equipments which the plaintiff had
supplied to the defendant. Those equipments were,
thereafter, attempted to be rectified and inspection was
carried out jointly on 7th April, 1995 by Mr. Manas Aich,
Deputy Manager (Design and Engg.) with Mr. Pankaj
Sharma, Engineer of the defendant. A large number of
operational defects were still found in the equipments.
Thereafter, the engineers from the plaintiff and defendant
company jointly sought to improve the equipment and 46
equipments were supplied to DOT as part of the purchase
order dated 20th December, 1993. 4 equipments could not
be rectified and the plaintiff was asked to take them back.
According to the defendant, the time of supply was the
essence of the purchase order. Hence, the belated supply of
116 equipments was never accepted by it. It is also alleged
that when the equipment when installed in the field did not
work and DOT instructed the defendant not to supply any
PCMs produced by the plaintiff to them. The equipments
supplied after 28th March, 1995, according to the defendant,
were left at site at the risk and costs of the plaintiff.
7. The following issues were framed on the pleadings
of the parties:-
(i) Whether the plaint has been signed, verified and instituted by a duly authorized person? OPP.
(ii) Whether the equipments supplied by the plaintiff to the Defendant under the Contract dated 1st February, 1995 were defective? OPD.
(iii) Whether the Plaintiff is entitled to recover any amount from the Defendant under the Contract dated 1st February, 1995 and if so what amount? OPP.
(iv) Whether the Plaintiff is entitled to pendente lite interest, and if so at what rate and for what period?
(v) Relief. Issue No.(i)
8. Exh. PW-6/10 is the copy of the resolution passed
by the Board of Directors of the plaintiff company in its
meeting held on 26 th November, 1983 whereby it was
resolved that the Heads of Units and Officers of the rank of
General Managers, Additional General Managers, Senior
Deputy General Managers, Deputy General Managers at the
Units and Head Office and Administrative Managers and
Chief Administrative Managers were designated as the
Principal Officers of the Company and were authorized to
sign and execute applications/petitions/documents on
behalf of the plaintiff and/or to depose before Government
and Judicial Authorities in relation to activities of their
respective Unit/Division/Department. In his affidavit by
way of evidence, Mr. M.S. Khan has stated that he was
working as Chief Administrative Officer and was designated
as Deputy Manager (Personnel and Administration) on 4 th
March, 1997. I see no reason to disbelieve the deposition of
Mr. M.S. Khan with regard to his designation. In view of the
Board resolution dated 26th November, 1983, Mr. Khan
being the Administrative Officer of the plaintiff company was
authorized to sign and very the plaint on behalf of the
plaintiff and was also designated as the Principal Officer of
the company. Order 29 Rule 1 of the Code of Civil
Procedure provides that in suits by or against a corporation,
any pleading may be signed and verified on behalf of the
corporation by the secretary or by any director or other
Principal Oficer of the corporation who is able to depose to
the facts of the case. Mr. M.S. Khan being the Principal
Officer of the company in terms of the Board resolution
dated 26th November, 1983 and also in view of the specific
delegation of power in this regard was competent to institute
this suit and sign and verify the pleadings on behalf of the
plaintiff. The issue is decided against the defendant and in
favour of the plaintiff.
Issue No.(ii) & (iii)
9. This is not in dispute that the plaintiff company
supplied 166 equipments to the defendant company and
those equipments were dispatched between 27 th March,
1995 and 31st March, 1995. The onus of proving that all
the equipments supplied by the plaintiff were defective was
on the defendant company. No witness has been examined
by the defendant, which was proceeded ex parte on 7 th
September, 2009. The case set out in the written statement
is that during the joint inspection carried on 29 th March,
1995 by Diwakaran, DGM (Mktd.) of the plaintiff and Mr.
Yudhbir Singh of defendant company, a large number of
defects were found in the 50 equipments supplied by the
plaintiff to the defendant. A perusal of the minutes of the
inspection held on 29th March, 1995, which is Exhibit PW-
6/6, does show that there were large number of defects in
the 50 equipments supplied by the plaintiff to the defendant
company. The minutes also show that the representative of
the plaintiff company assured the representative of the
defendant company that the defects found during inspection
will not be repeated and that they would take remedial
action, which will be informed to the plaintiff before
dispatching the next supply.
10. In his affidavit filed on 10th January, 2011, Mr.
B.K. Pant, Manager of the plaintiff company has stated that
on 28th March, 1995 after dispatch of 57 units of
equipments, a fax was received from the defendant company
intimating that 50 units, which they received on 27 th March,
1995, were defective and they requested that an Engineer be
sent for fixation and testing of those units. They also
requested them not to dispatch any further units. The fax
sent by the defendant is Exhibit PW-6/5. The affidavit of
Mr. Pant shows that the defects found during the joint
inspection carried on 29th March, 1995 were removed on
21st April, 1995, 22nd April, 1995 and 29th April, 1995 by the
engineers of the plaintiff company, in the presence of the
engineers of the defendant, at the place of the defendant. It
further shows that the equipments, which were supplied by
the plaintiff company on 28th March, 1995, 30th March,
1995 and 31st March, 1995, were also inspected and found
according to the requirement of DOT. Since no evidence has
been produced by the defendant, I see no reason to
disbelieve his deposition of Mr. Pant to the effect that the
defects noticed in the 50 units dispatched on 27th March,
1995 were rectified on various dates between 21 st April,
1995 to 29th April, 1995 at the premises of defendant
company. In the absence of any rebuttal from the
defendant, I see no reason to disbelieve his deposition to the
effect that equipments that were supplied by the plaintiff
company on 28th March, 1995, 30th March, and 31st March,
1995 were found as per the requirement of Department of
Telecommunications.
11. Exhibit PW-6/7 is the fax sent by the defendant
company to the plaintiff on 18 th May, 1995. A perusal of
this document would show that the defendant accepted only
44 pieces and declined to accept the remaining pieces on
the ground that they were supplied beyond the stipulated
date of delivery of the equipments. This was not the case of
the defendant in this communication that the remaining
equipments supplied by the plaintiff company also were
defective or were not in accordance with the specifications
prescribed by the Department of Telecommunications and
failure of the plaintiff to adhere to the agreed delivery
schedule was the sole ground for declining to accept the
remaining equipments.
12. Though the defendant accepted only 44
equipments out of 50 equipments shipped to it on 27th
March, 1995, there is no evidence of its having returned the
remaining six equipments to the plaintiff company. Though
it has come in the written statement that four units
supplied by the plaintiff could not be rectified and only 46
units were delivered by the defendant to the Department of
Telecommunications, the fax sent by the defendant to the
plaintiff on 18th May, 1995 conveyed acceptance of 44
equipments, whereas it should have been for 46 equipments
assuming that remaining four equipments out of 50
supplied to it continued to be defected. In fact, acceptance
of 44 equipments by the defendants indicates that the
plaintiff is right in saying that the equipments, which had
dispatched on 27th March, 1995 had been rectified by its
Engineers. Had those equipments not been rectified, the
defendant would not have accepted even 44 such
equipments.
13. This is plaintiff's own case that the equipments
were to be supplied by it by 31st March, 1995. The first
batch of the equipments was dispatched on 27 th March,
1995 and comprised 50 units. These 50 units were found to
be defective during the joint inspection held on 29th March,
1995. The plaintiff company removed the defects found in
these 50 units somewhere in the month of April, 1995. The
plaintiff company was under obligation to supply
equipments free from any defect on or before 31 st March,
1995. If the plaintiff company supplied 50 defective units
on 27th March, 1995, the defendant was not bound to
accept them, could have rejected those equipments and was
not bound to pay their price. However, since the defendant
accepted 46 equipments out of 50 units supplied on 27 th
March, 1995 by supplying them to DOT, it is obliged in law
to pay to the plaintiff company for those 46 units. However,
the defendant is not liable to pay for the remaining four
units out of 50 units dispatched on 27th March, 1995 since
they were defective when received by the defendant the
defects in those units were rectified by the plaintiff company
after the last date stipulated for supply of the equipment,
and the defendant did not accept them at a later date.
14. Section 43 of the Sale of Goods Act, 1930 provides
that unless otherwise agreed, where goods are delivered to
the buyer and he refuses to accept them, having the right so
to do, he is not bound to return them to the seller, but it is
sufficient if he intimates to the seller that he refuses to
accept the equipments. Since the defendant was not bound
to accept the equipments on removal of defects in the month
of April, 1995 and the plaintiff was informed of the defects
found in the goods and was also informed that only 44 units
were being accepted by it, the defendant complied with the
statutory requirement laid down in Section 43 of the Sale of
Goods Act, 1930 as far as four units of equipments are
concerned.
15. As regards remaining 116 units, the affidavit of
Mr. Pant shows that they were also inspected and were
found according to the requirement of Department of
Telecommunications. There is no evidence on record to
prove that any of the units out of 116 units dispatched to
the defendant company between 28th March, 1995 and 31st
March, 1995 were defective. The defendant could not have
refused to accept delivery of those equipments and could
not have asked the plaintiff to take them back.
16. The only ground on which supply of the remaining
units was rejected by the defendant, as conveyed vide fax
dated 18th May, 1995 was that there was delay in supply
and the balance quantity sent by the plaintiff was beyond
the delivery dates and, therefore, could not be accepted.
Exhibit PW-5/5 is the copy of the order placed by the
Government of India on the defendant company for supply
of equipment. This document shows that the delivery of 30
terminals of 2GHz., 30 channel (1+0) M/W equipment and
associated items was to be completed by 31 st March, 1994
whereas the delivery of the balance equipments was to be
supplied by 31st December, 1994. The case of the plaintiff is
that since the copy of the purchase order placed by the
Government of India on the defendant company, supplied to
it by the defendant, envisaged delivery by 31 st March, 1994
and that date already expired much before the purchase
order was placed by the defendant on the plaintiff company,
the officials of DOT, who were required to inspect the
equipments declined to carry out/certify the inspection and,
therefore, it had to write to the defendant company
requesting it to get the time for delivery of the equipments
by it, to Government of India, extended suitably so that
inspection could be carried out by the officials of DOT
posted at its premises.
17. Exhibit PW1/1 is the fax dated 16th March, 1995
sent by the plaintiff company to the defendant informing it
that as per the purchase order, delivery date was 31 st
December, 1994 and DOT(QA) needs the extension of
delivery date to take up the inspection. The defendant was
requested to forward the delivery date extension letter
immediately. Exhibit PW-6/3 is the fax sent by the
defendant to the plaintiff on 24th March, 2005 thereby
forwarding the delivery date extension letter of DOT against
purchase order dated 20 th December, 1993. Exhibit PW-
5/6 is the letter of the Department of Telecommunications
to the defendant whereby the delivery schedule for the
second lot of the equipments was extended upto 30th June,
1995 without levy of liquidated damages. This letter issued
by the Government of India is dated 2nd February, 1995. It
is, thus, quite obvious that the inspection of the equipments
which the defendant had manufactured could not be carried
out by DOT (QA) officials due to the lapse on the part of the
defendant company in not sending the letter whereby the
last date for delivery of the equipment by it to the
Government of India had been extended till 30 th June, 1995
though, being dated 2nd February, 1995, this letter issued
by the Government of India must be in possession of the
defendant company much prior to the date the inspection
was to be taken up the officials of DOT (QA). Since the
letter extending date of delivery of equipment by the
defendant to DOT was forwarded to the plaintiff company
only on 24th March 1995, it was not possible for the plaintiff
to dispatch the equipments to the defendant by 25 th March
1995, in terms of defendant's letter dated 15th February
1995. Inspection by officials of DOT posted at the premises
of the plaintiff was a condition required to be fulfilled before
dispatch of goods to the defendant company in terms of
agreement between the parties. Since inspection by DOT
officials was delayed solely on account of lapse of the
defendant in not sending the letter extending date of
delivery of equipment by it to the Government, the
consequent delay in dispatch of goods to the defendant is
also attributably solely to the defendant. The letter
extending date of delivery of equipment by the defendant to
the Government was sent to the plaintiff Company on 24 th
March 1995. The inspection at the premises of the plaintiff
was completed between 27th March 1995 and 31st March
1995 and the equipments, as soon as they were inspected in
parts, were dispatched to the defendant company. Had the
defendant company sent the letter extending date of delivery
to the plaintiff company in time along with the order on 15 th
February 1995, or even soon thereafter, there would have
been no delay in inspection by DOT officials posted at the
premises of the plaintiff and consequently no delay would
have occurred in dispatch of goods to the defendant
company.
18. As per the terms and conditions of purchase order,
the plaintiff could not have dispatched the equipments to
the defendant company without its inspection by DOT(QA).
Since the inspection was delayed on account of lapse of the
defendant company, it was not entitled in law to take
advantage of its own fault and reject the supply on the
ground that it had been made after the last day fixed for
supply of the equipments. Though vide its fax dated
15.2.1995 which is exhibit PW-6/2, the defendant had fixed
the delivery schedule as 30 equipments by 5.3.1995, 30
equipments by 10.3.1995, 40 equipments by 15.3.1995, 50
equipments by 20.3.1995 and 50 equipments by 25.3.1995,
vide subsequent fax dated 27.3.1995 Ex.PW-6/4, it had
informed the plaintiff that they would not accept any
material after 30.3.1995, meaning thereby that the plaintiff
could have supplied 200 equipments on or before
30.3.1995. Irrespective of whether the last date for supply
of equipments remained as 25.3.1995 in terms of the fax
dated 15.3.1995 or it was changed to 30.3.1995 in terms of
fax dated 27.3.1995, the fact remains that the dispatch of
the equipments was delayed on account of the lapse of the
defendant company in not supplying the letter whereby the
last date for supply of equipments by it to Government of
India had been extended upto 30.6.1995. The official of
DOT(QA) were not expected to inspect the equipment after
the last date stipulated for its supply to Government of India
had already expired by that time. In any case, the plaintiff-
company could not have compelled the officials of DOT(QA)
to carry out inspection despite the fact that the delivery
order supplied to it envisaged 31.12.1994 as the last date
for supply of the equipments to Government of India.
Therefore, in my view, the defendant company was not
entitled to reject the equipments supplied by the plaintiff
company on the ground that the supply was beyond the
delivery schedule agreed between the parties. I, therefore,
hold that the defendant company is required to pay the
price of 162 equipments to the plaintiff company. The price
of 162 equipments comes to Rs.1,52,02,270/- per unit.
After deducting Rs.20 lacs which the defendant had
admittedly paid to the plaintiff, the principal amount
payable by the defendant to the plaintiff for 162 units comes
to Rs.1,32,02,270/-. The plaintiff is entitled to recover this
amount from the defendant. The onuses are decided
accordingly.
Issue No.(iv)
19. The plaintiff has claimed a sum of Rs.4294574/-
towards interest on cash credit rate without specifying what
the cash credit rate was. There is no agreement between
the parties for payment of interest. No custom or usage for
term for payment of interest has either been pleaded or
proved by the plaintiff. Interest cannot be awarded as
damages. However, since this is a suit for price for goods
sold and delivered, the Court in view of provisions contained
in Section 61 of Sale of Goods Act can award interest to the
plaintiff at such rate as it finds fit on the price of the goods,
from the date of tender of the goods or from the date on
which the price was payable. The quotation given by the
plaintiff to the defendant envisaged opening of LOC with the
provision for payment upto 90 days with interest free credit
for 30 days and sharing of interest for balance 60 days,
calculated at the rate of 16% per annum. Since no LOC was
opened by the defendant in favour of the plaintiff company,
the provisions regarding interest free period or sharing of
interest in equal proportion for 60 days beyond the initial
period of 30 days does not come into play. In my view,
taking into consideration the nature of transaction between
the parties, the plaintiff should be awarded interest at the
rate of 12% per annum w.e.f. 1.4.1995. The amount of
interest on principal amount of Rs1,32,02,270/- calculated
at the rate of 12% per annum for the period upto 4.3.1997
comes to Rs.30,53,557/-.
The issue is decided accordingly.
Issue No.(v)
20. In view of my finding on above issues, the plaintiff
is entitled to recovery of Rs.1,62,55,827/- from the
defendant.
ORDER
A decree for Rs.1,62,55,827/- with proportionate
cost and pendente lite and future interest at the rate of 12%
per annum is passed in favour of the plaintiff and against
the defendant. Decree sheet be drawn accordingly.
(V.K. JAIN) JUDGE January 20, 2011 vk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!