Citation : 2011 Latest Caselaw 108 Del
Judgement Date : 10 January, 2011
THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment Reserved on: January 07, 2011
Judgment Pronounced on: January 10, 2011
+ CS(OS) No. 2340/2008 & I.A. No. 15811/2008
M/S. SAIPEM TRIUNE ENGINEERING PVT. LTD
....Plaintiff
- versus -
INDIAN OIL PETRONAS PVT. LTD. .....Defendant
Advocates who appeared in this case:
For the Plaintiff: Ms. Malvika Rajkotia, Adv.
For the Defendant: Mr. Diggaj Pathak
CORAM:-
HON'BLE MR JUSTICE V.K. JAIN
1. Whether Reporters of local papers may
be allowed to see the judgment? Yes
2. To be referred to the Reporter or not? Yes
3. Whether the judgment should be reported Yes
in Digest?
V.K. JAIN, J
1. This is an application under Section 5 & 8 of
Arbitration and Conciliation Act, 1996, in a suit for recovery
of Rs.1,79,92,366/-. On 26.09.2005, the
defendant/applicant had issued a notice inviting tender for
Project Management Consultancy Services, for design and
CS(OS)No.2340/2008 Page 1 of 16
engineering, carrying out investigation work, basic
engineering with cost estimate, statutory approvals,
procurement assistance etc. and preparation of project
completion documents for implementation of
LPG/Propane/Butane Import/Export Terminal at
Ennore(Tamil Nadu), on a lump sum turnkey basis. The bid
documents consisted of two volumes. The first volume
contained instructions to bidders; forms of bid, bank
guarantee and conditions of contract, etc. whereas the
second volume consisted of scope of work and other project
requirements. On 1.9.2006, the defendant/applicant issued
a Letter of Intent to the plaintiff with respect to the aforesaid
tender. Pursuant thereto, a work order dated 3.10.2006
was issued to M/s.Triune Projects Pvt. Ltd., which was
substituted by amended work order dated 25.1.2007 in the
name of the plaintiff which had acquired the business of
M/s.Triune Project Pvt. Ltd. Other terms and conditions of
the work order dated 3.10.2006, however, remained
unchanged.
2. The work order, inter alia, provided as under:-
"All the tender documents including
N.I.T., your quotation, payment terms,
special terms and conditions of the
CS(OS)No.2340/2008 Page 2 of 16
tender, general description of the works,
subsequent negotiations and all other
correspondences connected with the
tender, shall form a part of this contract
agreement."
3. The case of the applicant/defendant is that the
documents referred in the work order as forming part of the
contract included the Format for Agreement of Project
Management Service, Article 31 of which provided as
under:-
"ARTICLE 31 : ARBITRATION
The arbitration proceedings shall be in
accordance with OM No.3/5/93-PMA
dated 30/6/93, Govt. of India,
Department of Public Enterprises, which
reads as follows:-
"In the event of any dispute or difference
relating to the interpretation and
applications of the provisions of the
CONTRACTS, such dispute or difference
shall be referred by either pasty to the
arbitration of one of the Arbitrators in the
Department of Public Enterprises to be
nominated by the Secretary to
Government of India, incharge of Bureau
of Public Enterprises. The Arbitration Act,
1940 shall not be applicable to the
arbitration under this clause, provided,
however, any party aggrieved by such
award may make a further reference for
setting aside or revision of the award to
the Law Secretary, Department of Legal
Affairs, Ministry of Law and Justice,
Government of India. Upon such
reference, the dispute shall be decided
by the Law Secretary or the Special
CS(OS)No.2340/2008 Page 3 of 16
Secretary/Additional Secretary when so
authorized by the Law Secretary, whose
decision shall bind the parties finally
and conclusively. The parties in the
dispute will share equally the cost of
Arbitration as intimated by the
Arbitrator."
4. The contract was terminated by the
defendant/applicant vide its letter dated 12.8.2008 on the
allegations of various breaches on the part of the plaintiff
and claims are stated to have been raised by it against the
plaintiff in this regard.
5. The case of the plaintiff is that the work was
completed by it by December, 2006 except for soil testing
which took another five months as clear site was not made
available by the defendant. It is also claimed that the
investigation works could start only in April, 2007 and
report was submitted to the defendant on 25.2.2007. It is
further alleged that vide letter dated 8.9.2007, the
defendant issued instructions to the plaintiff to resume the
work on part-II of the project and extended the project
completion schedule to April, 2009. Pursuant to that letter,
the plaintiff commenced work on part-II. However, on
9.6.2008, the defendant asked the plaintiff to cancel the
tender giving high cost estimate and non-incorporation of
CS(OS)No.2340/2008 Page 4 of 16
some of its comments as the reason for cancellation. The
plaintiff, however, continued with the work till August, 2008
when the PMC contract was terminated by the defendant on
12.8.2008. According to the plaintiff, it had submitted
invoice amounting to Rs.2,15,17,485/- for the work
performed till May, 2008 but the defendant released only a
sum of Rs.37,60,119/- leaving a balance of Rs.77,57,366.
It is also alleged that a bank guarantee of Rs.52,35,000/-
which the plaintiff had submitted to the defendant was also
encashed. The plaintiff has now claimed a sum of
Rs.1,79,92,366/- which comprises the balance amount
payable to it, the amount of bank guarantee and an amount
of Rs.50 lakhs as nominal damages.
6. The case of the defendant/applicant in this
application is that since the suit pertains to subject matter
of an arbitration agreement between the parties, the matter
is required to be referred to arbitration.
7. It is stated in the reply that there are three
different clauses pertaining to arbitration, i.e. (a) 9.0.0.0 of
C 154 - C - G -102 (sheet no.76 of 89 at page 105). (b)
Article 31 of C 154-C-G 109 (sheet no.23 of 24 at page
no.188 to 189). (c) Article 34 of the draft contract agreement
CS(OS)No.2340/2008 Page 5 of 16
and all the clauses are at variance. It is alleged that since
all the clauses are at variance and had not attained finality,
in the absence of a valid arbitration clause, the dispute
cannot be referred to arbitration.
8. In Eastern Coalfields Limited vs. Sanjay
Transport Agency and Another, (2009) 7 SCC 345, the
agreement between the parties contained the following
clause:-
"ARBITRATION WITH REGARD TO THE
COMMERCIAL DISPUTES BETWEEN
THE PUBLIC SECTOR ENTERPRISES
INTER SE AND BETWEEN THE PUBLIC
SECTOR ENTERPRISES AND
GOVERNMENT DEPARTMENTS.
In the event of any dispute of difference
relating to the interpretation and
application of the provisions of the
commercial terms of the contract such
dispute or difference shall be referred by
either party to the arbitration, to one of
the arbitrators in the Department of
Public Enterprises, to be nominated by
the Secretary to the Government of India
incharge of the BUREAU OF PUBLIC
ENTERPRISES. The Arbitration Act, 1940
shall not be applicable to the arbitration
under this clause. The award of the
arbitrator shall be binding upon the
parties to the dispute, provided however,
any party aggrieved by such award,
may make further reference for setting
aside or revision of the award to the Law
Secretary, Department of Legal Affairs,
CS(OS)No.2340/2008 Page 6 of 16
Ministry of Law & Justice, Government of
India. Upon such reference, the dispute
shall be decided by the Law Secretary or
the Special Secretary/Additional
Secretary when so authorised by the
Law Secretary, whose decision shall
bind the parties finally and conclusively.
The parties to the dispute will share
equally the cost of arbitration, as
intimated by the arbitrator."
Relying upon the above-referred clause, the High
Court referred the dispute which had arisen between the
parties to the sole arbitration of a retired judge of the High
Court. Setting aside the order of the High Court, Supreme
Court, inter alia, held as under:-
"The aforesaid clause No. 14 relates to
disputes of commercial nature arising
between the Public Sector Enterprises
inter se and between the Public Sector
Enterprises and Government
Departments. The text that follows also
makes the said position clear which
provides that after the award is given by
the arbitrator in the department of public
sector enterprises, reference for setting
aside or revision of the award is to be
made to the Law Secretary, Department
of Legal Affairs, Ministry of Law &
Justice, Government of India. The said
clause, therefore, concerns the
commercial disputes arising between the
Public Sector Enterprises inter se and
between such enterprises and
Government Departments. The said
clause will have no application to an
agreement which is entered into between
the appellant and the respondents, one
of whom is a private party.
9. Since Article 31 of the Format for Agreement of
Project Management Service is absolutely identical to clause
14 of the agreement between the parties in the case of
Eastern Coalfields (supra), it must necessarily be held that
since one of the parties to the agreement is a private
company, it can have no application to the agreement
between them and, therefore, no reliance can be placed on
the aforesaid clause for referring the disputes between the
parties to arbitration.
It was pointed out by the learned counsel for the
defendant/applicant that in the case of Eastern Coal fields
(supra), the heading of the arbitration clause indicated that
it applied to disputes between the Public Sector Enterprises
inter se and the Public Sector Enterprises and the
Government Departments, but, no such heading has been
given to clause 31 of the Format for Agreement of Project
Management Service. In my view, the contention is
misconceived for two reasons. Firstly, the heading to Article
31 of the Format for Agreement of Project Management
Service indicates that the arbitration shall be in accordance
with OM No.3/5/93-PMA dated 30.6.1993, Government of
India, Department of Public Enterprises and that OM,
undisputedly, refers only to arbitration between Public
Sector Enterprises inter se and the Public Sector
Enterprises and Government of India. Secondly and more
importantly, the arbitration clause in that case being
absolutely identical to the arbitration clause contained in
Article 31, the heading of the arbitration clause would not
be a material factor.
10. However, clause 9.0.1.0 of the general
conditions of contract for Project Management Consultancy
Services, which form part of the tender document, also
provides for arbitration and reads as under:-
9.0.1.0 Subject to the provisions of Clauses 6.7.1.0, 6.7.2.0 and 9.0.2.0 hereof, any dispute arising out of a Notified Claim of the CONSULTANT included in the Final Bill of lie CONSULTANT in accordance with the provisions of Clause 6.6.3.0 hereof, if the CONSULTANT has not opted for the Alternative Dispute Resolution Machinery referred to in Clause 9.1.1.0 hereof, and any dispute arising out of any Claim(s) of the OWNER against the CONSULTANT shall be referred to the arbitration of a Sole Arbitrator selected in accordance with the provisions of Clause 9.0.1.1 hereof. It is specifically agreed that the OWNER may prefer its Claim(s) against the CONSULTANT as counterclaim(s) if a Notified Claim of the
CONSULTANT has been referred to arbitration. The CONSULTANT shall not, however, be entitled to raise as a set off defence or counterclaim any claim which is not a Notified Claim included in the CONSULTANT's Final Bill in accordance with the provisions of Clause 6.6.3.0 hereof.
9.0.1.1 The Sole Arbitrator referred to in Clause 9.0.1.0 hereof shall be selected by the CONSULTANT out of a panel of 3 (three) persons nominated by the OWNER for the purpose of such selection, and should the CONSULTANT fail to select an arbitrator within 30 (thirty) days of the panel of names of such nominees being furnished by the OWNER for the purpose, the Sole Arbitrator shall be selected by the OWNER out of the said panel.
11. Since the work order issued by the defendant
company specifically stipulated that all the tender
documents including general terms and conditions of the
tender shall form part of the contract agreement, it cannot
be disputed that the above-referred general terms and
conditions of contract, including the arbitration clause
referred-above, form part of the contract between the
parties. Thus, there is an agreement clause between the
parties and in terms of that clause, any dispute arising out
of a notified claim of the plaintiff included in the final bill of
the plaintiff as also any dispute arising out of any claim of
the defendants against the plaintiff as required to be
referred to the arbitration of a sole Arbitrator to be selected
in accordance with the provisions of clause 9.0.1.1 since
admittedly the plaintiff has not opted for the alternative
dispute resolution machinery referred to in clause 9.0.1.0
and the provisions of clause 6.7.1.0, 6.7.2.0 and 9.0.2.0
also do not apply to the claim of the plaintiff.
12. An analysis of Section 8 of Arbitration &
Conciliation Act would show that the following conditions
are required to be satisfied before the Court can exercise its
powers under this provision: (1) there should be an
arbitration agreement; (2) a party to the agreement should
bring an action in the court against the other party; (3)
subject-matter of the action should be the same as the
subject-matter of the arbitration agreement; (4) the other
party should move the court for referring the parties to
arbitration before it submits his first statement on the
substance of the dispute. In my view, clause 9.0.1.0
constitutes an arbitration agreement between the parties.
The plaintiff before this Court is a party to the arbitration
agreement; the defendant which is the other party to the
arbitration agreement has moved the Court for referring the
disputes between the parties to arbitration, before
submitting its first statement on the substance of the
dispute and prima facie subject matter of the suit is the
same as the subject matter of the arbitration agreement.
Therefore, all the conditions required for exercise of powers
by the Court under Section 8 of the Act stand fulfilled in
this case.
13. It was contended by the learned counsel for the
plaintiff that since the disputes subject matter of this suit,
do not arise out of a notified claim of the plaintiff included
in the final bill submitted by it, the arbitration clause
referred-above does not apply to the suit claim. As noted
earlier, the case of the plaintiff is that it had submitted
invoices amounting to Rs.2,15,17,485/- for the work
performed till May, 2008 and a sum of Rs.77,57,366/- out
of that amount is still due to it from the defendant. It is
difficult to accept that the claim with respect to this amount
is not covered under the above-referred arbitration clause.
Admittedly, the defendant has also raised claims against the
plaintiff and presumably the amount of the bank guarantee
of Rs.52,35,000/- has been encashed towards satisfaction
of those claims of the defendant. In any case, it will be very
much open to the arbitrator to take a view on this aspect of
the matter and decide whether any or all the claims forming
subject matter of this suit are covered under the arbitration
clause or not. Section 16 of the Arbitration & Conciliation
Act, 1996 specifically confers power upon the arbitral
tribunal to rule on its jurisdiction including ruling on any
objections with respect to the existence or validity of the
arbitration agreement. Therefore, it will only be appropriate
if this aspect of the matter is left to the arbitrator to
determine.
14. In Hindustan Petroleum Corporation Ltd. v. M/s
Pinkcity Midway Petroleums, AIR 2003 SC 2881 the
appellant before the Supreme Court filed an application
under Section 8 read with Section 5 of the Arbitration and
Conciliation Act, 1996 in a civil suit filed by the respondent
seeking a decree of declaration. The learned Civil Judge
dismissed the application holding that the disputes between
the parties were not covered by the arbitration agreement.
The revision filed by the appellant against that order was
dismissed by the High Court. Setting aside the decision of
the High Court, the supreme Court referred to the decision
of its Constitutional Bench in Konkan Railway
Corporation Ltd. v. Rani Construction Pvt. Ltd., AIR
2002 SC 778 and held that if there is any objection as to
the applicability of the arbitration clause to the facts of the
case, the same will have to be raised before the concerned
arbitral tribunal and, therefore, the Courts below ought not
to have proceeded to examine the applicability of the
arbitration clause to the facts of the case in hand but ought
to have left that issue to be determined by that arbitral
tribunal. Referring to its earlier decision in the case of P.
Anand Gajapathi Raju v. P.V.G. Raju, (2000) 4 SCC 539,
the Supreme Court was of the view that in cases where
there is an arbitration clause in the agreement, it is
obligatory for the Court to refer the parties to arbitration in
terms of their arbitration agreement and nothing remains to
be decided in the original action after such an application is
made except to refer the dispute to an arbitrator. The
Supreme Court was of the view that once the arbitration
clause was admitted, considering the mandatory language
of Section 8 of the Arbitration Act, the Court below ought to
have referred the dispute to arbitration.
15. Dealing with the question as to what would be the
role of Civil Court when an argument is raised that such
arbitration clause does not apply to the case in hand, the
Supreme Court noted that Section 16 of the Act had
empowered the arbitral tribunal to rule on its own
jurisdiction, including the rule on any objection with respect
to the existence or validity of the arbitration agreement. The
Supreme Court was of the view that the arbitral tribunal's
authority under Section 16 of the Act was not confined to
the width of its jurisdiction but goes to the very root of its
jurisdiction and, therefore, there would be no impediment in
contending before the arbitral tribunal that it had been
wrongly constituted and, therefore, it had no jurisdiction.
16. As observed by Supreme Court in P.Anand
Gajapathi Raju And Others vs. P.V.G. Raju (Dead) And
Others, (2000) 4 SCC 539, the language of Section 8 of
Arbitration & Conciliation Act is preemptory and, therefore,
it is obligatory for the Court to refer the parties to
arbitration in terms of their arbitration agreement and in
such a case, nothing remains to be decided in the original
action. Similar view was taken by the Supreme Court in
Branch Manager, Magma Leasing and Finance Ltd. and
another v. Potluri Madhavilata and another, (2009) 10
SCC 103.
For the reasons given in the preceding paragraphs,
the application is allowed and the disputes between the
parties which are subject matter of this suit are referred to
arbitration. The respondent is directed to nominate a panel
of three persons in terms of clause 9.0.1.1. The plaintiff will
be entitled to select any one out of those three persons to
act as Arbitrator, within thirty days of the name of the
panelist being forwarded to it by the defendant, failing
which the arbitrator will be selected by the defendant out of
the panel forwarded by it to the plaintiff. The defendant will
also be entitled to prefer counter-claims against the plaintiff
in terms of clause 9.0.1.0 to the arbitrator.
The suit as well as the IA stand disposed of in
terms of this order.
(V.K. JAIN) JUDGE JANUARY 10, 2011 'sn'/'vk'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!