Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Devraj vs Bses Yamuna Power Ltd.
2011 Latest Caselaw 1048 Del

Citation : 2011 Latest Caselaw 1048 Del
Judgement Date : 22 February, 2011

Delhi High Court
Devraj vs Bses Yamuna Power Ltd. on 22 February, 2011
Author: Rajiv Sahai Endlaw
            *IN THE HIGH COURT OF DELHI AT NEW DELHI

                                       Date of decision: 22nd February, 2011.

+                            W.P.(C) No.5360/2010

%        DEVRAJ                                            ....... Petitioners
                            Through:      Mr. Deepak Pathak, Adv.

                                   Versus

         BSES YAMUNA POWER LTD.                  ..... Respondent
                     Through: Mr. K. Datta, Adv.

CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1.       Whether reporters of Local papers may
         be allowed to see the judgment?                          No

2.       To be referred to the reporter or not?             No

3.       Whether the judgment should be reported            No
         in the Digest?

RAJIV SAHAI ENDLAW, J.

1. The writ petition impugns the order dated 16th November, 2009 of

the Office of Electricity Ombudsman constituted under the Electricity Act,

2003. The only question falling for adjudication being as to whether the

electricity dues claimed from the petitioner are time barred or not, need

was not felt to call for any counter affidavit and the counsel for the

respondent appearing on advance notice heard finally.

2. The undisputed facts are that the petitioner has an industrial

electricity connection; no bills with respect thereto were raised since the

date of installation; the petitioner in the year 2003 approached the

Permanent Lok Adalat with the grievance of the bills having not been

raised; the Permanent Lok Adalat vide order dated 14 th August, 2003,

finding a total sum of `94,446/- to be then due from the petitioner up till

20th May, 2003 made provisions for payment thereof in installments.

However even thereafter no bills were raised. On 27th July, 2004, the

meter was changed under the scheme of mass replacement of electro

mechanical meters; however no bills were raised thereafter also.

3. The petitioner in or about the year 2008 approached the Consumer

Grievance Redressal Forum (CGRF) constituted under Section 42(5) of the

Electricity Act, 2003 with the case that the electricity dues if any against

him had become time barred and for a direction to the respondent to raise a

correct bill on him.

4. It was the case of the respondent before the CGRF that inadvertently

the master date of the meter installed at the premises of the petitioner could

not be punched in the system and due to which no bills were raised; that as

per the reading taken on 7 th July, 2008, a sum of `1,19,101.16 paise against

the old meter for the period after 20 th May, 2003 and a sum of

`7,41,886.51 paise for the period after the change of the meter was due

from the petitioner. It was further pleaded that under Regulation 16(xi)

and 44(iv) of the Delhi Electricity Supply Code & Performance Standards

Regulations, 2007 it was the duty of the petitioner as consumer to complain

of non receipt of the bill and the petitioner had not made any complaint at

all and could not escape the liability for the electricity actually consumed

by him.

5. Per contra, the petitioner relied upon Section 56(2) of the Act to

contend that the dues not recovered within two years had become time

barred. It was further contended that for the deficiency in service and

mistake of the respondent in non-punching of the master date, the

petitioner could not be burdened with heavy payment.

6. The CGRF held that the petitioner had not submitted any document

in support of his claim of approaching the respondent with the complaint of

non-receipt of bills after 20th May, 2003 and thus was liable to pay the

amounts demanded. However, the petitioner was permitted to pay the

amount in eight monthly installments without Late Payment Surcharge

(LPSC). Compensation of `2,000/- was also awarded to the petitioner for

inconvenience caused due to non-raising of bills by the respondent.

7. The petitioner being not satisfied, preferred an appeal to the Office

of Electricity Ombudsman. The Ombudsman vide order dated 16th

November, 2009, impugned in this writ petition, after going through the

accounts and giving adjustment of the lump sum payment made by the

petitioner since the order of the CGRF, found a sum of `5,06,875.78 paise

to be due from the petitioner and permitted the same to be paid in ten

monthly installments.

8. This writ petition was preferred after more than eight months of the

order of the Ombudsman. There is no explanation whatsoever for the

unusual delay in preferring the writ petition. Be that as it may, the

question urged being purely legal, the counsels for the parties have been

heard.

9. The mainstay of the case of the petitioner is Section 56(2) of the Act

which is as under:-

"(2) Notwithstanding anything contained in any other law for the time being in force, no sum due from any consumer, under this section shall be recoverable after the period of two years from the date when such sum became first due unless such sum has been shown continuously as recoverable as arrear of charges for electricity supplied and the licensee shall not cut- off the supply of electricity."

10. The question as to when the electricity charges become first due is

no longer res integra. The Single Judge of this Court in H.D. Shourie Vs.

Municipal Copn. of Delhi 32 (1987) DLT 73 held that the electricity

charges become due and the limitation for recovery thereof commences

only when the bill therefor has been raised. The Division Bench in appeal

reported as MCD (DESU) Vs. H.D. Shourie 53 (1994) DLT 1 reiterated

that liability to pay accrues when liability is quantified and bill is raised.

The counsel for the respondent has also drawn attention to Swastic

Industries Vs. Maharashtra State Electricity Board (1997) 9 SCC 465

upholding the order of the National Consumers' Disputes Redressal

Commission holding that even where the electricity distribution company

had woken up after nine years to make the claim, the electricity dues had to

be paid. Attention is also invited to the judgments of this Court in:-

(i) D.R. & Co. Vs. D.V.B. 130 (2006) DLT 158 laying down that

even though consumer has to pay for the electricity consumed from

the moment of consumption but there is no limit for raising demand.

(ii) Order dated 14th November, 2006 of the Appellate Tribunal

for Electricity in Appeal Nos.202 & 203 of 2006 interpreting Section

56(2) aforesaid and the Terms & Conditions for Supply of

Electricity, 2004 then in force and holding that the same were

identical to the provisions earlier existing and reiterating that the bar

of two years in Section 56(2) would come into play only after two

years from the date of raising of the bill and not from the date of

consumption.

(iii) Brihanmumbai Municipal Corporation Vs. Yatish Sharma

AIR 2007 Bombay 73 also holding that the payment for electricity

consumed falls due only upon service of bill.

(iv) Judgment dated 16th July, 2009 of the Division Bench in LPA

No.211/2009 titled N.D.M.C. Vs. Karam Chand Thapar & Brothers

P. Ltd. with reference to Section 56(2) of the Act and reiterating that

an Electricity Undertaking is entitled to issue the bill for

consumption of electricity even after three years of the date of

consumption.

11. Though the counsel for the petitioner has referred to judgment of a

Single Judge of this Court in NDMC Vs. Ashok Kumar Ahuja 154 (2008)

DLT 50 but the same was discussed by the Division Bench in the judgment

aforesaid and held to be not applicable.

12. Applying the aforesaid law, in the present case admittedly no bill

was raised for the electricity consumed by the petitioner, till the petitioner

approached the CGRF. It could not thus be said that the demand had

become time barred as contended by the petitioner.

13. There is thus no merit in the writ petition; the same is dismissed. I

refrain from imposing any costs. The petitioner if has not paid the dues

aforesaid till now, to clear the same within four weeks from today. If the

dues are not so cleared, the petitioner shall become liable for Late Payment

Surcharge besides other remedies of the respondent.

RAJIV SAHAI ENDLAW (JUDGE) FEBRUARY 22, 2011 bs

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter