Citation : 2011 Latest Caselaw 6251 Del
Judgement Date : 20 December, 2011
IN THE HIGH COURT OF DELHI AT NEW DELHI
O.M.P. 235/2004
Reserved on: November 24, 2011
Decision on: December 20, 2011
UNION OF INDIA ..... Petitioner
Through Ms. Geeta Sharma with
Ms. Priya Singh, Advocates.
versus
MICROWAVE COMMUNICATIONS LTD. ..... Respondent
Through Mr. Jasbir Singh, Advocate
CORAM: JUSTICE S. MURALIDHAR
JUDGMENT
20.12.2011
1. Union of India (`UoI') in this petition under Section 34 of the
Arbitration and Conciliation Act, 1996 (`Act') challenges an Award
dated 13th February 2004 to the extent it rejects the Petitioner's claim
against the Respondent to recover a sum of Rs. 1,21,42,490/- together
with interest from 1st January 2003 till the date of payment.
2. The Respondent Microwave Communications Ltd. (`MCL') applied
to the Department of Telecommunications (`DoT') for grant of licence
for operation of Voice Mail Service (`VMS') on their Radio Paging
Network in Mumbai, Delhi, Calcutta, Ahmedabad and Surat. The
Petitioner DoT issued to the Respondent a letter of interest (`LOI') on
30th January 1996 granting licences for the said five Service Areas.
3. As per the terms of the LOI, the Respondent MCL furnished to the
Petitioner 10% licence fee for all the five Service Areas, Financial
Bank Guarantee (`FBG') for a sum of Rs. 22.5 lakhs towards 90% of
the balance minimum licence fee payable for the five Service Areas
and two Performance Bank Guarantees (`PBGs') of Rs. 5 lakhs each.
Five separate licences for each of the five cities were signed between
the Petitioner and Respondent on 17th May 1996.
4. In terms of the LOI, the minimum licence fee payable in respect of
the Service Areas was as under:-
Sl. No. Service Area Minimum Licence
Fees Payable per
annum
1. Delhi Rs. 7.5 Lacs
2. Mumbai Rs. 7.5 Lacs
3. Calcutta Rs. 5 Lacs
4. Surat Rs. 2.5 Lacs
5. Ahmedabad Rs. 2.5 Lacs
Total Rs. 25 Lacs
5. According to the Petitioner, the above licence fee would be doubled
if the Respondent provided service to the other customers besides their
own registered radio paging subscribers. The schedule of payment of
licence fee, interest/penalty on the late payment of the licence fee was
also specifically indicated in the licence agreement.
6. According to condition 1.1 of Part II Schedule C of the Licence
agreements, MCL was to instal and commission the service within 12
months from the date of signing of the licence agreement in all the five
Service Areas. As per condition 6 of Part II, Schedule C of the licence
agreement, in the event MCL failed to bring the service of any part
thereof into commission within the prescribed period, the DoT would
be entitled to recover liquidated damages (`LD') from the licensee for
each Service Area at Rs. 5,000/- for each week of the delay or part
thereof, subject to a maximum of Rs. 1 lakh for each Service Area. By
a letter dated 24th September 1996 the Respondent informed the DoT
that VMS had been commenced in the Calcutta and Ahmedabad
Service Areas from 26th August 1996 and 22nd August 1996,
respectively. By a further letter dated 17th January 1997, MCL
informed the DoT that the VMS at Calcutta and Ahmedabad had been
offered to the subscribers. By a letter dated 17th February 1997 MCL
submitted to the DoT a TEC Certificate for testing of the installation at
Surat and Delhi and requested the DoT to give it permission to
commission the service in Delhi in view of the conditionalities in TEC
Certificate. TEC Certificates dated 16th January 1997 and 30th January
1997 were issued pursuant to the said letter stating that prior to the
commissioning of service, approval had to be obtained from the
licensing authority. In its letter dated 15th April 1997 written to MCL,
the DoT pointed out that 90% licence fee was still to be paid by it in
four Service Areas, i.e., Ahmedabad, Calcutta, Surat and Delhi and as
a result of the delay in payment of the said licence fee, a total amount
of Rs. 1,34,339/- was due towards interest. As regards Mumbai City,
90% of the licence fee for Rs. 6,75,000/- plus 25% licence fee of the
first quarter in the second year (Rs. 1,87,500) was due and payable on
7th May 1997. MCL was asked to inform the DoT whether the service
had started in the Mumbai area, and if so to also pay the licence fee.
By its letter dated 4th June 1997 MCL requested the DoT to grant it
approval to launch the services in the five cities.
7. In its letter dated 13th May 1997 the DoT reminded MCL about the
outstanding licence fee. Thereafter, on 30th October 1998 a notice was
issued informing MCL that its reply to the show cause notice dated
14th August 1997 was not found satisfactory and, therefore, the
competent authority had decided to terminate the Licence agreement at
the risk and cost of MCL. It was also mentioned that the termination of
the licences was without prejudice to the rights of the licensor. The
notice required MCL to pay DoT the outstanding dues as on that date
amounting to Rs. 52,13,475/-, i.e. licence fee of Rs. 36,45,833/- and
interest of Rs. 15,67,642/- including LD of Rs. 1 lakh as per condition
6 Schedule C, Part II of the licence agreement. A further reminder was
sent to the MCL by the DoT on 30th November 1998.
8. It is stated that meanwhile the DoT encashed the FBG in the sum of
Rs. 22.5 lakh. A request made to MCL to furnish fresh FBG in the sum
of Rs. 25 lakh was not complied with. It is stated that even after the
encashment of the FBG, a sum of Rs. 31.25 lakhs plus interest etc. still
remained outstanding. The PBG was invoked by the Petitioner to the
tune of Rs. 10 lakh.
9. MCL filed Suit No. 1684 of 1998 in this Court, inter alia, seeking
stay of encashment of the PBG. A statement was made on behalf of the
DoT during the hearing of the said suit that the said PBG would not be
encashed subject to the MCL agreeing to keep it renewed from time to
time. However, according to the DoT, MCL failed to keep the PBG
valid beyond 30th June 2001. After the notices of termination of
licence agreement was sent by the DoT, MCL filed Suit No. 1603 of
1998 seeking to recover from DoT a sum of Rs. 22.5 lakhs together
with interest @ 18% per annum. While filing a reply in the said suit,
the Petitioner reserved its right to invoke Section 8 of the Act and seek
reference of the disputes to arbitration. Thereafter DoT invoked the
arbitration clause and one Shri O.P. Nahar was appointed as the Sole
Arbitrator.
10. The learned Arbitrator, who was a Legal Adviser and Ex Officio
Additional Secretary (Conveyancing) Department of Legal Affairs,
Ministry of Law and Justice delivered his Award dated 13th February
2004. The learned Arbitrator rejected the three preliminary objections
raised by MCL. One concerned the validity of the appointment of the
Arbitrator; the second challenging the appointment on account of there
being no prior notice issued to MCL by the Petitioner and third that the
Petitioner's claim was barred by limitation. The learned Arbitrator also
rejected the Respondent's request for framing issues and leading oral
evidence. The arbitral reference was confined to the three components,
viz., (i) licence fee (ii) liquidated damages and (iii) interest thereon.
11. As regards the case of the Mumbai licence, learned Arbitrator held
that although the licencee (MCL) never started service in Mumbai, the
licensor, i.e. the DoT, did not cancel the licence nor issued MCL any
notice for non-performance. It was held that DoT had not shown any
positive action to mitigate the loss. On the other hand, it allowed the
losses to multiply. It was held that DoT could at best claim the licence
fee for the period from the effective date till the expiry of one year and
LD as agreed between the parties for non-performance. Even as
regards the other licence agreements in relation to the other Service
Areas, the learned Arbitrator found that the DoT continued to await the
start of the provision of service by the Respondent and never really
issued any notice for non-performance either on the expiry of twelve
months or even prior thereto. Judicial notice of the fact was also taken
that the service was not remunerative and DoT, after a certain time,
allowed the said service without payment of any licence fee. It was
held that MCL was entitled to the same treatment although the licence
agreements had been signed at an earlier point in time. Since DoT had
already recovered one year's licence fee in respect of each of the
licence agreements and accepted 10% in cash apart from invoking
FBG in respect of the remaining 90% amount, it was held that DoT
would be entitled at best to Rs. 5 lakhs as LD along with one year's
licence fee. In the circumstances, it was held that the Petitioner was
entitled to Rs. 5 lakhs and nothing more. As regards the payment of
interest, since there was no clause in the contract permitting such
payment, it was disallowed.
12. Ms. Geeta Sharma, learned counsel appearing for the Petitioner
referred to the letter dated 15th April 1997 from the DoT to MCL
which clearly mentioned the amounts of licence fee which were yet to
be paid by MCL as well as the penalty for late payments. According to
her, there was no failure by the Petitioner to take positive steps to
recover the amounts due. It was submitted that the learned Arbitrator
erred in holding that the Petitioner had not taken steps to mitigate the
losses and was therefore not entitled to recover the arrears of licence
fee. It was further submitted that the learned Arbitrator had gone
beyond the licence agreement in holding that if the service itself was
made free of charge the same facility should be extended to MCL as
well. Mr. Jasbir Singh, learned counsel for the Respondent on the other
hand defended the impugned Award. He submitted that it was based
on evidence led by the parties and that given the limited scope of the
powers of interference by the court under Section 34 of the Act, it was
not open to the court to re-appreciate the evidence as a court of appeal.
13. It appears to this Court that the view taken by the learned
Arbitrator on the basis of the documents placed before him was a
plausible one to take. There is no valid explanation offered by the DoT
to the contention of the Respondent that unless the performance tests
required for the successful commissioning of the service was carried
out by the Petitioner, the offering of services could not commence.
There were indeed several obligations cast on the DoT in terms of the
licence agreement, which were not met by it. Added to this was the
fact that the services themselves had begun to be offered free of
charge. In the circumstances, no exception can be taken to the
conclusion arrived at by the learned Arbitrator that at highest the
Petitioner was entitled to only one year's licence fee in regard to the
five licence agreements and LD in the sum of Rs. 1 lakh for every
Service Area. The finding of the learned Arbitrator was a factual one
based on the evidence led before the Arbitrator. It cannot be said that
the rejection of the DoT's claim by the Arbitrator was vitiated by any
'patent illegality'. As rightly observed by the learned Arbitrator, DoT
had already invoked the FBG as regards the 90% amount. In the
circumstances, this Court is not persuaded to interfere with the
impugned Award of the learned Arbitrator.
14. The petition is accordingly dismissed.
S. MURALIDHAR, J.
DECEMBER 20, 2011 akg
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!