Citation : 2011 Latest Caselaw 3796 Del
Judgement Date : 8 August, 2011
THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment delivered on: 08.08.2011
+ W.P. (C) 6063/2010
LARSEN & TOUBRO LIMITED & ANR ... Petitioners
Versus
UNION OF INDIA & OTHERS ... Respondents
Advocates who appeared in this case:
For the Petitioners : Mr Mukul Rohatgi, Sr Advocate with Mr S. Ganesh, Sr Advocate, Mr Pratap Venugopal, Ms Surekha Raman, Mr Dileep P. and Mr P.K. Jha For the Respondent No.1 : Mr B.V. Niren with Mr Aarumugam M. For the Respondent No.2: Mr Parag P. Tripathi, ASG with Ms Bindu Saxena, Ms Aparajit Swarup, Ms Neha Khattar and Mr Kunal Bahri For the Respondent No.3: Mr Gourav Banerjee, ASG with Mr Saurav Ajrawal and Mr Dinesh Kumar For the Respondent No.4: Dr Abhishek Manu Singhvi, Sr Advocate with Mr Prashant Mehta, Ms Radhika Arora and Mr Jaiveer.
For the Respondent No.5: Mr Rajiv Nayyar, Sr Advocate with Mr Sagar Pathak and Mr Shiv Shankar.
CORAM:-
HON'BLE MR JUSTICE BADAR DURREZ AHMED HON'BLE MR JUSTICE MANMOHAN SINGH
1. Whether Reporters of local papers may be allowed to see the judgment? Yes
2. To be referred to the Reporter or not? Yes
3. Whether the judgment should be reported in Digest? Yes
BADAR DURREZ AHMED, J
1. In this writ petition, there is a challenge to the rejection letter
dated 18.08.2010, whereby the petitioner No.1's bid has been rejected by
the respondent No.2 (NTPC) on the ground of it being non-responsive in
terms of clause 21 of the Instructions to Bidders (ITB) read alongwith
Item No.4 of the Bid Data Sheet (BDS), Section-III. Consequently, the
respondent No.2 also returned the bank guarantee submitted by the
petitioner No.1 towards bid security.
2. It may be pointed out straightaway that the rejection was on
the ground that the Deed of Joint Undertaking (DJU), which was to be
submitted by the bidders, including the petitioner No.1, was found to be
not in accordance with the prescribed format and was, therefore, regarded
as being non-compliant. It is for this reason that the respondent No.2
(NTPC) rejected the bid submitted by the petitioner No.1. However,
according to the learned counsel for the petitioners, the rejection is bad
inasmuch as the requirement of furnishing a Deed of Joint Undertaking
in the prescribed format was not a critical requirement. It was sufficient
that a Deed of Joint Undertaking was furnished. If there was any
deficiency in the Deed of Joint Undertaking furnished by a bidder, the
same could be rectified as it had been done by the petitioner No.1 at a
subsequent stage on 28.06.2010 when it submitted a revised Deed of
Joint Undertaking dated 17.06.2010. Thus, according to the learned
counsel for the petitioners, there was substantial compliance of the
condition of furnishing a Deed of Joint Undertaking, in the first instance,
and whatever deficiencies there were in the said Deed of Joint
Undertaking were, in any case, rectified by furnishing a revised Deed of
Joint Undertaking dated 17.06.2010 by the petitioner on 28.06.2010.
3. Thus, the entire controversy in this writ petition centres
around the Deed of Joint Undertaking. According to the petitioners, the
Deed of Joint Undertaking, which was initially submitted, was
substantially compliant with the requirements of the tender. It was also
contended that after the submission of the initial bid, there was
correspondence between the petitioner No.1 on the one hand and, the
respondent No.2 on the other, with regard to various aspects of the bid
documents, but no query was ever raised by the respondent No.2 with
regard to the Deed of Joint Undertaking alleging that the same was not
compliant. In fact, it was also contended on behalf of the petitioners that
the respondent No.2 (NTPC) sent a letter on 21.07.2010 indicating that
as the bids are still under processing and are likely to take some more
time and that the present validity of the petitioner No.1's proposal is upto
11.08.2010, the petitioner No.1 was requested to extend the validity of its
offer for a further period of at least 60 days upto and, including
11.10.2010 and that the bank guarantee against the bid security may also
be extended accordingly. Pursuant to this, the petitioner No.1 extended
the validity of the offer for a further period of 60 days and also extended
the validity. According to the learned counsel for the petitioners, there
was no mention in the respondent No.2's letter dated 21.07.2010 with
regard to the petitioner No.1's bid being non-compliant on account of the
Deed of Joint Undertaking not being in terms of the tender conditions. It
was contended that till the impugned rejection letter dated 18.08.2010,
the petitioners were never informed by the respondent No.2 that their bid
was non-compliant with respect to the Deed of Joint Undertaking. Thus,
according to the learned counsel for the petitioners, the respondent No.2
took a complete volt-face in issuing the rejection letter dated 18.08.2010.
Consequently, it was submitted that the said rejection was liable to be set
aside.
4. On behalf of the respondent No.2, Mr Parag Tripathi, the
learned Additional Solicitor General, submitted that no plea of
promissory estoppel or legitimate expectation has been taken in the writ
petition and, therefore, at this stage of arguments, without there being a
foundation in the pleadings, no such case can be permitted to be set up.
In any event, Mr Tripathi submitted that mere submission of a Deed of
Joint Undertaking did not amount to substantial compliance with the
tender conditions. The Deed of Joint Undertaking had to be in the
prescribed format. Material deviations from the said format entailed that
the Deed of Joint Undertaking was not compliant in terms of clause 21 of
the ITB and Item No.4 of the Bid Data Sheet (BDS), Section-III (clause
1.5.2).
5. Mr Gaurav Banerjee, the learned ASG, appearing on behalf of
the respondent No.3 (BHEL), also submitted that as the bid was not
substantially responsive on account of the Deed of Joint Undertaking not
being in terms of the tender conditions, there was no option with the
respondent No.2 (NTPC) but to reject the bid of the petitioner No.1.
6. Dr A.M. Singhvi, the learned senior counsel, appearing on
behalf of the respondent No.4 (ALSTOM Bharat Forge Power Limited)
and Mr Rajiv Nayyar, the learned senior counsel, appearing on behalf of
the respondent No.5 (Toshiba Corporation Power Systems Company),
submitted that the bid made by the petitioner No.1 had been validly
rejected by the respondent No.2. At this juncture, it may be pointed out
that the respondent Nos. 3 to 5 have been found to be L-1, L-2 and L-3
on the opening of their price bids and as per clause 31 of the Instructions
to Bidders (ITB), each one of them is to meet part of the project in the
ratio of 2:2:1.
7. The National Thermal Power Corporation (Respondent No.2)
had invited bids for the supply and installation of 11 Steam Turbine
Generator (STG packages) for its various super-thermal power projects.
The bids were to be in two stages. The first stage comprised of Techno-
Commercial Bid and the second, the Price Bid. It is only those parties
which cleared the Techno-Commercial stage, who would be entitled to
submit their Price Bids in Stage-II. As noted above, the petitioners are
aggrieved by the fact that the petitioner No.1 has not been allowed to
continue to the second stage by virtue of the rejection letter dated
18.08.2010, whereby the petitioner No.1's bid was rejected on the ground
of it being non-responsive in terms of clause 21 of the ITB read
alongwith Item No.4.0 of the BDS, Section III. We may also point out
that another bidder, namely, Power Machines OJSC, Russia was also
found to be non-responsive at the Techno-Commercial Stage and had not
been permitted to participate in the second stage, that is, of the Price Bid.
8. The petitioner No.1, of which the petitioner No.2 is a share
holder, entered into a joint venture agreement with Mitsubishi Heavy
Industries Limited. A joint venture company - L&T MHI Turbine
Generators Private Limited - was formed. The petitioner No.1 and its
affiliates were to maintain a share-holding in the joint venture company
of 51% and MHI was to maintain its share-holding at 49%.
9. The said tender was floated by the respondent No.2 (NTPC)
through an invitation to bid dated 16.10.2009. On 11.02.2010, the
petitioner No.1 submitted its bid using Route No.5 of the Bid Data Sheet
(BDS) of the tender documents which was titled as "Indian JV Promoters
holding at least 51% equity in a joint venture company for manufacturing
super critical Steam Turbine Generator Sets in India between the Indian
Company and the qualified Steam Turbine Manufacturer". As pointed
out above, there was correspondence exchanged between the petitioner
No.1 and the respondent No.2 with regard to the petitioner No.1's bid on
various issues. However, there was no mention of the Deed of Joint
Undertaking being non-compliant.
10. The entire controversy, as mentioned above, rests on the
question of the Deed of Joint Undertaking being compliant or not.
Clause 4 of the Instructions to Bidders (ITB) deals with the Content of
Bidding Documents. Clause 4.1 stipulates that the facilities required,
bidding procedures, contract terms and the technical requirements are
prescribed in the bidding documents and that the bidding documents
include Sections I to VII. The said Section VII pertains to Forms and
Procedures and Item No.13 thereof refers to the Form of Deed of Joint
Undertaking for Qualifying Requirement. Clause 4.2 of the said ITB
stipulates that the bidder is expected to examine all instructions, forms,
terms, conditions, specifications and other information in the bidding
documents. It is also provided that failure to furnish all information as
per the bidding documents or submission of a bid not substantially
responsive to the bidding documents in every respect would be at the
bidder's risk and could result in the rejection of its bid. Therefore, it is
clear that the form of Deed of Joint Undertaking for qualifying
requirement was an integral part of Section VII (Forms and Procedures)
and consequently of the bidding documents. It is also clear that the
bidder was warned that failure to furnish all information required as per
the bidding documents or submission of a bid not substantially
responsive to the bidding documents in every respect would be at the
bidder's risk and could also result in rejection of its bid.
11. An argument had been advanced on behalf of the petitioners
that just as other clarifications were being sought with regard to the bid
made by the petitioner No.1, a clarification could very well have been
sought with regard to the Deed of Joint Undertaking which was
submitted alongwith the Techno-Commercial Bid in case the respondent
No.2 felt that the said document was not compliant. Clause 20 of the
ITB deals with Clarification of Bids and clause 20.1 makes it clear that
during bid evaluation, the employer (respondent No.2) may, at its
discretion, ask the bidder for a clarification of its bid. The request for
clarification and the response shall be sought in writing and no change in
the price or substance of the bid shall be sought or permitted. Thus,
while the respondent No.2 could, at its discretion, ask for a clarification
of its bid, such request for clarification was to be in writing and more
importantly it could not relate to a change in the price or substance of the
bid. In other words, if the bid was not substantially compliant, then it
could not be corrected through the route of clause 20 by seeking
clarifications of the bid.
12. Clause 21 of ITB is crucial for our purposes and the same
reads as under:-
"21. Preliminary Examination of Stage-I (Techno-
Commercial) Bid:
The Employer will examine the bids to determine whether they are complete, whether required securities have been furnished, whether the documents have been properly signed and whether the bids are generally in order.
21.2 Prior to the detailed evaluation, the Employer will determine whether each bid is generally complete, acceptable and is substantially responsive to the bidding documents. For purposes of this determination, a substantially responsive bid is one that conforms to all the terms, conditions and specifications of the bidding documents without material deviations, objections, conditionalities or reservations. A material deviation, objection, conditionality or reservation is one (i) that affects in any substantial way the scope, quality or performance of the contract; (ii) that limits in any substantial way, inconsistent with the bidding documents, the Employer‟s rights or the successful Bidder‟s obligations under the contract; or (iii) whose rectification would unfairly affect the competitive position of other Bidders who are presenting substantially responsive bids.
21.3 Critical Provisions No deviation, whatsoever, is permitted by the Employer to the provisions relating to following clauses.
(a) Governing Laws (Clause 5 of GCC, Section IV).
(b) Settlement of Disputes (Clause 6 of GCC, Section IV).
(c) Terms of Payment (Clause 12 of GCC, Section IV).
(d) Performance Security (Clause 13.3 of GCC, Section IV).
(e) Security for Deed(s) of Joint Undertaking (Clause 13.4 of GCC, Section IV).
(f) Taxes and Duties (Clause 14 of GCC, Section IV).
(g) Completion Time Guarantee (Clause 26 of GCC, Section IV).
(h) Defect Liability (Clause 27 of GCC, Section IV).
(i) Functional Guarantee (Clause 28 of GCC,
Section IV).
(j) Patent Indemnity (Clause 29 of GCC, Section IV).
(k) Limitation of Liability (Clause 30 of GCC, Section IV).
(l) Price Adjustment (Appendix-2 to Form of Contract Agreement, Section-VII)
(m) Phased Manufacturing Programme (Clause 20 of GCC, Section V)"
13. An argument had been raised on behalf of the petitioners that
the critical provisions or the no deviation provisions have been set out in
clause 21.3. While security for the Deed of Joint Undertaking has been
mentioned in clause 21.3 (e), there is no mention of the Deed of Joint
Undertaking itself and thus, if there were deviations in the Deed of Joint
Undertaking, they were not critical and, therefore, could be corrected
during the evaluation process of Stage-I (Techno-Commercial).
However, this argument does not appeal to us. This is because clause
21.2 makes it clear that for the purposes of determination of a bid being
substantially responsive to the bidding documents, it must conform to all
the terms, conditions and specifications of the bidding documents
without "material deviations, objections, conditionalities or
reservations". The said clause itself defines what is meant by a material
deviation, objection, conditionality or reservation as being (i) which
affects in any substantial way the scope, quality or performance of the
contract; (ii) which limits in any substantial way, inconsistent with the
bidding documents, the employers rights or the successful bidder's
obligations under the contract; or (iii) whose rectification would unfairly
affect the competitive position of the other bidders who are presenting
substantially responsive bids.
14. At this stage, it would be necessary to refer to the copy of the
DJU as originally submitted by the petitioner No.1, alongwith the
petitioner No.1's Techno-Commercial bid on 12.02.2010. A copy of the
same was handed over by the learned counsel for the respondent No.2 on
14.09.2010, at the time of hearing of the application for interim orders.
In that copy, which was taken on record on that date, the learned counsel
for the respondent No.2 had taken care to indicate in red as also to
underline as well as strike out those portions which were added by the
petitioner to the original format and those portions which were omitted,
respectively. The said document handed over by the learned counsel for
the respondent No.2 had been taken on record as there was no objection
by the learned counsel for the petitioners with regard to its authenticity.
The said document indicates that full scale changes have been made to
the DJU as prescribed under the bid document and, as observed in the
order dated 14.09.2010, the Deed of Joint Undertaking submitted by the
petitioner No.1 alognwith its Techno-Commercial Bid on 12.02.2010
was virtually a different document. By way of sample, as we did at the
interlocutory stage, we are reproducing paragraphs 4, 5, 6, 7 and 8 of the
Deed of Joint Undertaking submitted by the petitioner No.1 on
12.02.2010. The portions which have been added are shown in bold and
are underlined. The portions which had been deleted are shown as
having been struck out.
"4. That in consideration of the award of the Contract by the Employer to the Contractor, we, the Qualified Steam Turbine Generator Manufacturer, the *Qualified Generator Manufacturer, JV Company and the Contractor, do hereby declare and undertake that we shall be jointly and severally responsible to the Employer for the execution and successful performance of the Generator and its auxiliary equipments as per Annexure-I. We, the Qualified Steam Turbine Generator Manufacturer, JV Company and the Contractor, do hereby further declare and undertake that we shall be jointly and severally responsible for the successful performance of all the contractual obligations under the said Contracts Provided, however, Notwithstanding anything to the contrary in this undertaking or the contract, such joint and several liability shall be expressly conditioned and subject to the Qualified Steam Turbine Manufacturer and the Qualified Generator Manufacturer having no liability to the Employer except in the event that, the following conditions are all met: (i) the equipment other than the products supplied by the Qualified Steam Turbine Manufacturer or/and the Qualified Generator Manufacturer in the plant meets the performance guarantees as
specified in the heat balance diagrams for guaranteed gross output and guaranteed heat rate, (ii) the contractor carries out the erection, commissioning and testing in accordance with the procedures furnished by the Qualified Steam Turbine Manufacturer and the Qualified Generator Manufacturer and (iii) such liability directly results solely from a material defect in the engineering, designs, material and workmanship in the product supplied by the Qualified Steam Turbine Manufacturer or/and the Qualified Generator Manufacturer.
5. Subject to the forgoing article 4, In case of any breach of the Contracts resulting solely & exclusively from the Engineering and supply of STG and integral Auxiliaries, committed by the Contractor , we the Qualified Steam Turbine Generator Manufacturer, JV Company and the *Qualified Generator Manufacturer do hereby undertake, declare and confirm that we shall be fully responsible for the successful performance of the Steam Turbine and Generator and their integral auxiliaries equipments including thermal performance and guaranteed parameters and undertake to carry out all the obligations and responsibilities under this Deed of Joint Undertaking in order to discharge the Contractor's obligations and responsibilities with respect to performance of the STG and integral auxiliaries stipulated under the Contracts. Further, if the Employer sustains any loss or damage on account of any breach of the Contracts, resulting solely and exclusively from the Engineering and supply of STG and integral auxiliaries by the contractor we the Qualified Steam Turbine Manufacturer, JV company and the *Qualified Generator Manufacturer and the Contractor jointly and severally undertake to promptly indemnify and pay such losses / damages caused to the Employer on its
written demand without any demur, reservation, contest or protest in any manner whatsoever.
6. Notwithstanding anything to the contrary in this undertaking and the contract, the total and aggregate liability of the Qualified Steam Turbine Manufacturer, the JV Company and the Qualified Generator Manufacturer respectively under or in connection with the Contract and this undertaking shall not be more than the amount equivalent to the respective value of service & equipment/ components supplied by the Qualified Steam Turbine Manufacturer, the JV Company and the Qualified Steam Generator Manufacturer. This is without prejudice to any right of Employer against the Contractor under the Contract and all guarantees.
7. Notwithstanding anything to the contrary in this undertaking and the contract, the Qualified Steam Turbine Manufacturer, the JV Company and the Qualified Generator Manufacturer shall in no event be liable to Employer by way of Indemnify or by reason of any breach of the contract or in tort, negligence, strict liability or otherwise for loss of use of Plant or any part thereof, loss of production, loss of profit or interest cost or loss of revenue or loss of any contractor, or for any indirect, special, incidental or consequential loss or damage that may be suffered by Employer arising out of or in connection with this undertaking and the Contract.
This is without prejudice to any right of Employer against the Contractor under the Contract and all guarantee.
The liability of the Qualified Steam Turbine Generator Manufacturer and JV Company shall be limited to an amount equivalent to US$122 (One hundred Twenty Two) Millions for each Turbine Generator Set to be supplied by the
Bidder/Contractor (to be finalized before Notification of Award). *The liability of the Qualified Generator Manufacturer, hereunder shall, however be limited to an amount equivalent to US$ 18(Eighteen) Millions for each Genrator Set to be supplied by the Bidder/ Contractor to be finalized before Notification of Award). This is without prejudice to any right of Employer against the Contractor under the Contract and all guarantees.
8. Without prejudice to the joint and several obligations of the Contractor, the Qualified Steam Turbine Generator Manufacturer, JV Company and the Qualified Generator Manufacturer hereunder, the analysis/investigations of the non-performance of the equipment manufactured by the Contractor may initially be carried out by the Contractor, within a period of 15 days from the date of reference of the problem by the Employer before the Employer approaches Qualified Steam Turbine Generator Manufacturer and the *Qualified Generator Manufacturer for any such analysis/ investigation. It shall not be necessary or obligatory for the Employer to first proceed against the Contractor before proceeding against the Qualified Steam Turbine Generator Manufacturer, JV Company and the Qualified Generator Manufacturer, nor any extension of time or any relaxation given by the Employer to the Contractor shall prejudice any right of Employer under this Deed of Joint Undertaking to proceed against the Qualified Steam Turbine Generator Manufacturer, JV Company, the *Qualified Generator Manufacturer and Contractor."
15. Let us take the first deviation which is noticed in paragraph 4
of the Deed of Joint Undertaking. A proviso has been added indicating
that notwithstanding anything to the contrary in the undertaking or the
contract, the joint and several liability shall be expressly conditioned and
be subject to the qualified steam turbine manufacturer and the qualified
generator manufacturer having no liability to the employer (respondent
No.2) except in the event that the conditions mentioned therein are met.
This is a clear conditionality and reservation which limits, in a
substantial way, inconsistent with the bidding documents, the rights of
the employer (respondent No.2). Furthermore, in paragraph 5 of the
Deed of Joint Undertaking, inter alia, the words "without any demur,
reservation, contest or protest in any manner whatsoever" appearing at
the end of the said paragraph have been deleted. Entirely new
paragraphs 6 and 7 have been inserted and the existing paragraph has
been deleted.
16. There were other similar alterations in the Deed of Joint
Undertaking submitted by the petitioner No.1 on 12.02.2010. The rights
of the employer (respondent No.2) have been seriously diluted and the
obligations which were originally cast upon the bidder and its joint
venture partners have been reduced. This would certainly amount to a
material deviation as contemplated in clause 21.2 of ITB which are
inconsistent with the bidding documents and materially affect the
respondent No.2's right as well as the bidder's obligation under the
contract. It is, therefore, clear that the Deed of Joint Undertaking
furnished by the petitioner No.1 alongwith its Techno-Commercial Bid
on 12.02.2010 was not substantially responsive / compliant. Thus, even
if it be assumed that the Deed of Joint Undertaking did not fall in the
category of zero deviation documents, it was not even substantially
compliant.
17. We may notice the contents of clause 21.4 of the ITB which
specifically stipulates that the employer's determination of a bid's
responsiveness is to be based on the contents of the bid itself without
recourse to extrinsic evidence. If a bid is not substantially responsive, it
will be rejected by the employer and might not substantially be made
responsive by the bidder by correction of the non-conformity. It was
contended by Mr Parag Tripathi on behalf of the respondent No.2 that the
revised Deed of Joint Undertaking dated 17.06.2010 furnished by the
petitioner No.1 on 28.06.2010, would amount to extrinsic evidence and
the same cannot be taken into consideration. In substance, the
submission of Mr Tripathi was that a bid, which was not substantially
responsive, in the first instance, cannot be permitted to be made
responsive substantially by correction of the non-conformity. We agree
with this submission of Mr Tripathi. Clause 21.4 of the ITB requires that
the employer in determining the responsiveness of a bid should only look
at the contents of the bid itself and not take recourse to extrinsic
evidence. The bid by itself included the non-compliant Deed of Joint
Undertaking. The correction of this non-conformity is not permissible in
view of clause 21.4 of ITB and, therefore, the Deed of Joint Undertaking,
which was non-compliant, cannot be made compliant subsequently by
submission of a revised Deed of Joint Undertaking in the prescribed
format.
18. In view of the foregoing, it is clear that the action taken by the
respondent No.2 in rejecting the petitioner No.1's bid on the ground that
it was not responsive in terms of clause 21 of the ITB read alongwith
Item No.4.0 of the Bid Data Sheet (BDS), Section-III, cannot be faulted.
The argument advanced by the learned counsel for the petitioners that if
the Deed of Joint Undertaking was non-compliant, then the respondent
No.2 ought to have rejected the bid straightaway and not led the
petitioners up the garden path, as it were, is not tenable, because, first of
all, the foundation for a plea of promissory estoppel or legitimate
expectation has not been laid out in the pleadings. Secondly, the
question of such a plea does not, at all, arise inasmuch as the tender
conditions are clear on this aspect of the matter and there has been no
waiver of the same on the part of the respondent No.2. The issue of
alleged change of stance on the part of the respondent No.2 has been
adequately explained by Mr Tripathi appearing on its behalf by
submitting that the non-compliance of the Deed of Joint Undertaking was
a live issue and this led to the respondent No.2 even taking the opinion of
the Attorney General with regard to the same. In the counter-affidavit
filed on behalf of the respondent No.2, it has been categorically stated
that the Attorney General of India had opined that the revised Deed of
Joint Undertaking cannot be accepted after the tender had been opened as
it would prejudice the other bidders and that such a decision could be
exposed to serious legal challenge in court. Of course, the opinion of the
learned Attorney General is not binding on this court, but, it does
demonstrate the fact that the respondent No.2 was considering the issue
with regard to the Deed of Joint Undertaking. As such, it cannot be
contended that the respondent No.2 took a complete somersault in its
approach to the Deed of Joint Undertaking and consequently to the bid
submitted by the petitioner No.1.
19. The result of this discussion is that the writ petition has no
merit and the same is dismissed. The parties are left to bear their own
costs.
BADAR DURREZ AHMED, J
MANMOHAN SINGH, J
August 08, 2011 dutt
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!