Citation : 2011 Latest Caselaw 2078 Del
Judgement Date : 19 April, 2011
*IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of decision: 19th April, 2011
+ W.P.(C) 8647/2007
JINGLE BELL AMUSEMENT PARK P. LTD. ..... Petitioner
Through: Mr. V.K. Goel, Advocate
Versus
NORTH DELHI POWER LTD. ..... Respondent
Through: Mr. Vikram Nandrajog & Mr. Sushil
Jaswal, Advocates
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? YES
2. To be referred to the reporter or not? YES
3. Whether the judgment should be reported YES
in the Digest?
RAJIV SAHAI ENDLAW, J.
1. The writ petition was filed impugning the demand of `34,34,594.77
towards arrears of electricity and of late payment surcharge of
`5,22,873.64 thereon. However, when the writ petition came up before
this Court on 28th November, 2007, the counsel for the respondent
informed that erroneously double billing had been effected for the period
of March, 2004 to February, 2005 and the amount due from the petitioner
was `21,98,207/- only. Notice of the petition was issued and subject to the
petitioner depositing `10,00,000/- with the respondent and paying the
current consumption charges, recovery of the balance amount claimed by
the respondent and disconnection of electric supply for non payment
thereof was stayed. Pleadings have since been completed. The interim
order was made absolute on 22nd May, 2009. The counsels for the parties
have been heard.
2. It is not in dispute that a non domestic electric connection of 80 KW
bearing K No.43100137786 was energized at the premises of the petitioner
on 30th November, 2002. It is the case of the respondent that the
multiplying factor of the said meter was to be of 12 but inadvertently the
bills were raised with the multiplying factor of 1 only. The counsel for the
respondent in this regard during the course of hearing has handed over a
copy of the Meter Installation Protocol Sheet stated to be bearing the
signatures of the petitioner and also showing the multiplying factor of the
meter to be 12. The counsel for the petitioner of course controverted the
same. It is also not in dispute that the petitioner in February, 2003 applied
for additional load of 60 KW taking the total load to 140 KW and the
additional load was energized in March, 2004. It is the case of the
respondent that only while sanctioning the enhanced load to the petitioner,
it came to light that the petitioner was being billed with a multiplying
factor of 1 instead of 12 and accordingly, the multiplying factor was
changed to 12 with effect from August, 2003 and the demand impugned in
this petition was raised for escaped assessment owing to application of
wrong multiplying factor for the period 30th November, 2002 till July,
2003.
3. The counsel for the respondent has taken a preliminary objection to
the maintainability of this petition. It is urged that the dispute raised is a
billing dispute and as per the dicta of the Division Bench of this Court in
Ram Kishan Vs. NDPL 130 (2006) DLT 549 (DB) , the alternative remedy
under Sections 42(5) or 42(6) of the Electricity Act, 2003 being available,
the writ petition is not maintainable.
4. The counsel for the petitioner while not controverting that the
dispute is a billing dispute has however justified the maintainability of this
writ petition on the ground of the demand being barred by time. It is
contended that electricity dues for the period 30 th November, 2002 to July,
2003 could not have been claimed after two years therefrom as has been
done. Reliance is placed on Section 56(2) of the Act.
5. The question as to when the electricity charges become first due is
no longer res integra. The Single Judge of this Court in H.D. Shourie Vs.
Municipal Corporation of Delhi 32 (1987) DLT 73 held that the electricity
charges become due and the limitation for recovery thereof commences
only when the bill therefor has been raised. The Division Bench in appeal
reported as MCD (DESU) Vs. H.D. Shourie 53 (1993) DLT 1 reiterated
that liability to pay accrues when liability is quantified and bill is raised.
6. The counsel for the petitioner has however contended that in the
present case it is not as if the bill for the period 30 th November, 2002 to
July, 2003 had not been raised; that bills were raised and paid; that the
claim now of the respondent is that the bills raised were not for the amount
due but was for something less. He contends that once the consumption
for a particular period has been computed and the bill raised, the
subsequent demand for the same period would be covered by Section 56(2)
of the Act and is recoverable only within two years and not thereafter.
7. The counsel for the respondent has met the aforesaid prima facie
attractive argument of the petitioner by contending that the present is a
case of an "escaped demand" and by further contending that the matter is
no longer res integra. Reliance is placed on Swastic Industries Vs.
Maharashtra State Electricity Board (1997) 9 SCC 465 upholding the
order of the National Consumers Dispute Redressal Commission holding
that even where the electricity distribution company had woken up after
nine years to make the claim, the electricity dues have to be paid.
8. Though the Supreme Court in the judgment aforesaid did use the
expression "escaped billing" but a reading of the judgment does not show
that in that case, for the period for which the billing had escaped attention,
bills had been raised, as is the case here. The said judgment cannot thus be
said to be a judgment on the distinction sought to be made by the petitioner
in the present case.
9. The counsel for the respondent next invited attention to the judgment
dated 24th April, 2009 of the Division Bench of this Court in LPA No.
356/2007 titled NDPL Vs. Delhi Bottling Company Ltd. In this case, the
challenge was to a supplementary bill for the period for which the bill had
earlier been raised. The argument of NDPL before the Division Bench was
that the principle of "escaped billing" had been approved by the Supreme
Court in Swastic Industries (supra). The Division Bench relying upon
Bharat Barrel and Drum Manufacturing Company Pvt. Ltd. Vs. The
Municipal Corporation of Greater Bombay AIR 1978 Bombay 369 held
that there is no limitation for making the demand by way of a
supplementary bill and Section 24 of the Electricity Act, 1910 empowers
issuance of such demand. It was held that the distribution company could
not be said to have abandoned its right to recover the charges which were
due to it and which had earlier been not claimed. It was further held that
the principle of constructive res judicata also would not apply to a case of
supplementary demand for misuse charges not claimed earlier.
10. The counsel for the respondent has also invited attention to a
detailed judgment of the High Court of Jharkhand in M/s Tata Steel Ltd.
Vs. Jharkhand State Electricity Board AIR 2008 Jharkhand 60 laying
down that if the sum demanded was not shown as due at any time earlier,
there could be no question of the said amount being at in earlier point of
time due from the consumer. It was further held that the amount of short
payments became due only after realization of mistake and the assessment
of the short-charged amount, and on raising the bill therefor.
11. I am in respectful agreement with the view taken by the High Court
of Jharkhand. The case here of the respondent is that though the electricity
consumed by the petitioner from 30th November, 2002 to July, 2003 was
more; that the bill was raised for a lesser consumption owing to the
inadvertent application of a wrong multiplying factor. Thus, the entire
electricity claimed to have been consumed by the petitioner cannot be said
to have been billed by the respondent. To that part of the electricity
consumed and for which no bill was raised, the dicta in H.D. Shourie
(supra) will clearly apply. H.D. Shourie cannot be read in a restrictive
way to hold that even if the units consumed are say 100 but bill is
erroneously raised for 10 units only, the claim for the balance 90 units for
which no bill has been raised would also stand barred by time.
12. I find that the Division Bench of the Bombay High Court in Rototex
Polyester v. Administrator, Admn. Of Dadra & Nagar Haveli Electricity
Dept. MANU/MH/0760/2009 in identical facts held that in case the
consumer is under-billed on account of clerical mistake such as where the
multiplication factor had changed, but due to oversight the department
issued bills with 500 as multiplication factor instead of 1000, the bar of
limitation cannot be raised by the consumer. It was held that the revised
bill amount would become due when the revised bill is raised and Section
56(2) of the Act would not come in the way of recovery of the amount
under the revised bills.
13. Having held against the petitioner on the aspect of limitation, this
writ petition is not maintainable owing to the alternative remedies available
under Section 42(5) or 42(6) of the Act.
14. The petition is accordingly disposed of. However, since the petition
remained pending in this Court for considerable time and interim relief was
also granted to the petitioner, it is further directed:
(i) that subject to the petitioner taking the alternative remedies
under Section 42(5) or 42(6) as it may deem expedient within
30 days of today, the same shall be entertained without any
plea of limitation.
(ii) that the petitioner shall be entitled to apply for interim relief
before the alternative fora and till the decision by the said
alternative fora on the application of the petitioner for interim
relief, the interim order granted in this petition shall continue
in force. However, thereafter it shall be as per the order of the
said alternative fora.
No order as to costs
RAJIV SAHAI ENDLAW (JUDGE) APRIL 19th, 2011 „gsr‟...
W.P.(C) 8647/2007 Page 10 of
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!