Citation : 2010 Latest Caselaw 4358 Del
Judgement Date : 16 September, 2010
* THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment delivered on : 16.09.2010
+ OMP 62/1999
M/S. PROJECTS & EQUIPMENTS CORPORATION
OF INDIA LTD. .......PETITIONER
versus
M/S. AIRTECH PRIVATE LTD. ........RESPONDENT
Advocates who appeared in this case:
For the Petitioner : Mr. C.M. Oberoi, Ms. Surekha Raman &
Mr. Venu Gopal, Advocates
For the Respondent : Mr. Rajiv Mehra, Sr. Adv. With Mr. Ritesh
Sharma, Advocate
CORAM :-
HON'BLE MR JUSTICE RAJIV SHAKDHER
1. Whether the Reporters of local papers may
be allowed to see the judgment ? NO
2. To be referred to Reporters or not? YES
3. Whether the judgment should be reported YES
in the Digest ?
RAJIV SHAKDHER, J. (ORAL)
1. By this order I propose to dispose of the captioned petition which has been filed by
Projects and Equipment Corporation of India Limited (hereinafter referred to in short as
"PEC") under the provisions of Section 34 of the Arbitration and Conciliation Act, 1996
(hereinafter referred to in short as "Arbitration Act") against an Award dated 06.11.1998
passed by the Arbitral Tribunal.
2. The petitioner was the respondent before the Arbitral Tribunal, and had opposed
the claims filed by the respondent herein i.e., Airtech Pvt. Limited. For the sake of
convenience, I would be referring to them as "PEC" & "Airtech". The objections to the
award by PEC pertain to only one claim which involves the encashment of bank guarantee
furnished by Airtech in the sum of Rs.3,50,000/-. There is also an objection filed qua a
consequential relief granted by Arbitral Tribunal with respect to payment of interest. The
Arbitral Tribunal, apart from the claim qua return of money recovered by PEC and grant
of consequential relief of interest thereon, rejected all other claims of Airtech. Similarly,
the counter claims filed by PEC were also rejected by the Arbitral Tribunal. It is not
disputed that neither Airtech filed cross objections against the Award nor has PEC filed
objections vis-à-vis rejection of its claims. Therefore, I am only concerned with the claim
allowed by Arbitral Tribunal qua encashment of the bank guarantee and the interest
granted thereon.
3. For this purpose, it is necessary to briefly advert to the circumstances in the
backdrop of which the disputes arose between the parties.
3.1 PEC in response to an invitation of tender for supply of Sewage Disposal
Equipment (hereinafter referred to as the "Equipment") floated by Dhaka Water Supply
and Sewage Authority (hereinafter referred to in short as "DWASA" ) submitted a bid.
The bid submitted by PEC was accepted which, culminated in an agreement dated
13.12.1994 (hereinafter referred to as the "Contract").
3.2 To be noted, a fact which is not disputed that prior to the submissions of the bid,
communication had taken place between the PEC and Airtech. The reason for the same
was that PEC not being a manufacturer of the Equipment which DWASA showed interest
in buying, it had to seek the help and assistance of Airtech. Consequently, this fact was
revealed to DWASA. The offer of PEC in point of fact was based on the offer of Airtech
made to PEC.
3.3 At the moment, I am not required to deal with the terms of the agreement in detail.
It would suffice for the purposes of this petition to only note that the offer which was
finally accepted by DWASA was structured in a fashion whereby, Airtech undertook to
supply and transport the goods till Benapole, a town situate at the border of India and
Bangladesh; and from thereon it was the responsibility of PEC to ensure that equipment
reached the final destination which was Pagla, Bangladesh. For this purpose, the services
of a local Bangladeshi agent had to be solicited to ensure transportation of goods between
Benapole and Pagla on a fee to be paid by PEC.
4. The terms of the offer which obtained between PEC and DWASA required PEC
to supply the goods against a Letter of Credit (in short, "LC") to be opened by a local
banker of DWASA i.e., one Janata Bank. It is not disputed that the LC was opened by
Janata Bank. It is also not disputed that in terms of Clause 3.2 of the Special Conditions
of the Contract (in short, "SCC"), the supply of the Equipment was to be made by PEC to
DWASA within 180 days. For the sake of convenience, said clause 3.2 is extracted
hereinbelow :-
"Clause 3.2 - The supply of Sewage Disposal Equipment shall be completed in all respect within 180 (one hundred eighty) days from the date of signing the Contract or receipt of Letter of Credit whichever is later."
4.1 In terms of contract, PEC was required to furnish a performance bond in the form
of a bank guarantee, drawn in favour of DWASA. As noticed hereinabove, since Airtech
was inextricably involved in the execution of the contract being the manufacturer of the
equipment, a back to back contract was executed as between PEC and Airtech. This
contract was termed as "Associateship Agreement". The Associateship Agreement was
executed on 23.01.1995. As per the terms of this Associateship Agreement, Airtech was
required to furnish a bank guarantee in favour of PEC, which incidently is the bank
guarantee in question. The said bank guarantee was drawn on State Bank of India,
Nizamuddin Branch, New Delhi (in short, "SBI"). As a matter of fact, this bank guarantee
was furnished by Airtech to PEC on 11.11.1995.
4.2 To complete the narration under the contract obtaining between PEC and
DWASA, a LC was opened by DWASA in favour of PEC on 02.02.1995. The said LC
was valid till 19.07.1995. As per clause 10 of the said LC dated 02.02.1995, it was clearly
indicted that the letter of credit shall become operable only on receipt of a commitment
letter from the Asian Development Bank (in short, "ADB"). In terms of the said clause 10
of the LC, a letter of commitment was issued by ADB on 07.04.1995. Intimation to that
effect was sent to Airtech on 29.04.1995. It is not disputed by the PEC that on
27.04.1995, Airtech wrote to PEC for extension of the validity of the LC for the period of
six months. It appears that based on this request, which was transmitted through PEC,
Janata Bank advised vide communication dated 21.05.1995 that the LC had been extended
till 10.08.1995. Thereafter, several letters were exchanged between Airtech and PEC
whereby, Airtech sought extension of LC as per the terms of the contract. Importantly, by
a letter dated 26.07.1995, Airtech, even while informing PEC that they were trying to
"expedite" delivery with regard to the equipment, indicated to PEC that they should
inform the buyer i.e., DWASA as regards their concern with regard to amendment of the
LC.
4.3 It appears that on 29.09.1995, Janata Bank extended the LC till 15.10.1995, and
thereafter till 04.11.1995.
4.4 It is important to note that in the interregnum, Airtech had written two crucial
letters to PEC. First, being a communication dated 16.10.1995, and the second being: a
communication dated 26.10.1995. By its communication dated 16.10.1995, the Airtech
informed PEC about the difficulties that it had been experiencing vis-à-vis the supplier in
respect of the supply of "chassis" which was evidently required for mounting the
Equipment. Airtech went on to say that the delay was not anticipated by them, and was
totally beyond their control. Airtech ended the communication by calling upon PEC to
request DWASA to extend the LC uptil 30.06.1996. This request was reiterated by
Airtech in their communication dated 26.10.1995. As a matter of fact, Airtech referred to
their earlier communication of 16.10.1995, in the communication of 26.10.1995. The
request was identical, except to the extent that, Airtech found no good reason why the
extension of the LC could not be carried out till 30.06.1996; as according to them, this was
their "first such request".
4.5 In the background of this, PEC communicated to Airtech vide Comunication dated
20.10.1995 that the delivery period for shipment stood extended upto 30.11.1995. They
sought a confirmation in respect of the same from Airtech.
5. It is not disputed that, in the background of the aforesaid circumstances, PEC
failed to deliver the Equipment to DWASA, and consequently, their performance bond
i.e., the bank guarantee furnished to DWASA was invoked and encashed. This triggered
the invocation of the bank guarantee furnished by Airtech in favour of PEC. By a
communication dated 06.11.1995, PEC invoked the bank guarantee furnished by SBI in its
favour. It is pertinent to note by a communication dated 08.11.1995, Airtech disputed the
right of PEC to invoke, and seek encashment of its bank guarantee. As a matter of fact,
Airtech in the said communication, inter alia, objected to the encashment of its bank
guarantee by PEC until such time PEC was able to prove that DWASA had actually
encashed its bank guarantee; in view of the fact that, Airtech's bank guarantee was only a
counter bank guarantee.
5.1 As noted above, parties are ad-idem that DWASA did encash the bank guarantee
furnished by PEC.
6. It is in the background of these facts that the parties referred their disputes to the
Arbitral Tribunal.
7. The Arbitral Tribunal in respect of the issue at hand, in substance, came to the
conclusion that the period of the LC had to run concurrently with the period prescribed for
delivery of the Equipment under the contract; which as noticed hereinabove was 180
days. The Arbitral Tribunal was also of the view, that the fact that, the LC was opened on
02.02.1995, and thereafter extended from time to time till 04.11.1995 could legally be
ignored by Airtech as the LC had to, in accordance with the terms of the contract, run for a
continuous period of 180 days. The relevant observations in regard to the same are
extracted hereinbelow :-
"......Giving a thoughtful consideration to the aforesaid contentions of the learned counsel for both the parties, the contention of learned counsel for the claimant is correct and must be accepted and that of the learned counsel for the respondent has to be rejected as untenable. When the contract does not provide for the delivery of goods in bits at different stages during the total period of delivery, the seller is entitled to deliver the goods at any point of time during subsistence of the total delivery period and in that situation the L/C which is a prompt and ready and immediate mode of payment for the seller for the supply of goods to the buyer, the buyer has to assure in all reasonableness that he opens the LC to safeguard the payment to the seller and the L/C has to be co- extensive with the delivery period and thus should be for a clear period of 180 days before the seller is to take steps for the supply of the goods. When this
assurance on the part of the buyer is the right of the seller, the seller, before taking any steps towards producing / procuring the goods contracted to be sold, must have before his eyes a clear and unambiguous total period of delivery in the L/C in one go and at one point of time, and this is the basic and underlined principle even in the facts of the case in hand regarding delivery and L/C and before the L/C is issued in this manner, the obligations of the seller cannot commence and all other things fall in the background and cannot be considered at all. The seller cannot be called upon by the buyer or even by the respondent in the case in hand to first show his bona fides by taking steps for effecting delivery, as in the circumstances referred to above the payment assurance in the form of a valid operational L/C is a must as a since qua non for the commencement of any obligations of the seller in the matter of production / procurement or delivery of goods.
The matter of guaranteeing payment to the seller for his price of goods as a conditional precedent in the circumstances of the case in hand can be seen from another angle also as the delivery of goods by the claimant is not to be effected in bits at various stages during the period of 180 days, and he can deliver the entire goods at one point of time, he may choose to do so towards the closing time of the delivery period of 180 days and it is quite probable that L/C may lapse by that time, in which case the L/C would not be available to the claimant for his prompt and ready payment and who may have to fall back on a complicated and prolonged process for the recovery of his price. In order to obviate any such complications the buyer has to open the L/C which is valid and operational for the entire delivery period by way of assurance of payment to the seller before the seller takes any steps to produce / procure and deliver the goods.
The claimant never had before his eyes at any point of time the L/C for a total delivery period of 180 days. The initial L/C being for a period shorter than 180 days, the claimant was within its right, to ignore the same and thus could ignore it for the period from 02.02.1995 the date of its issuance till 19.07.1995 the date of its expiry, and even for the period from 21.05.1995 the date of its extension during its continuance upto 30.08.1995 and even for the period from 29.07.1995 the date of second extension to 15.10.1995 or even 04.11.1995, all these periods could be legally ignored by the claimant by looking into the validity of the L/C which had to be or a continuous period of 180 days at one go and at one point of time and no valid L/C ever came into existence which could force the claimant to take steps towards delivery of the
goods and thus his obligations under the contract for the supply of goods did not commence and in view of this, very important factor, the contention of the learned counsel for the respondent propounding the proposition of considering the requisite 180 days period of L/C in a cumulative manner, is bereft of all force and cannot be accepted."
8. Based on their finding with respect to the said issue, the Arbitral Tribunal held that
PEC was in breach of the terms of the Associateship Agreement, and hence was required
to pay the interest. Even though Airtech had demanded interest at the rate of 24% p.a., the
Arbitral Tribunal found the rate to be excessive, and accordingly ordered that interest be
paid by PEC at the rate of 18% p.a. w.e.f. 06.11.1995 i.e., the date when Airtech's bank
guarantee stood invoked and encashed.
9. Mr. Oberoi assisted by Mr. Venu Gopal, who appeared for the Objector/PEC
challenged the findings of the Arbitral Tribunal on the ground that they are perverse. For
this purpose, he has drawn my attention to clause 2.3, 2.7, 2.8 and 3.2 of the SCC of the
contract and clauses 2, 4.7 of the Associateship Agreement and clauses 2, 5, 8, 12 of the
General Terms & Conditions (GCC) of the Associateship Agreement. The finding of the
Arbitral Tribunal that the LC opened by DWASA in favour of PEC had to run for 180
days, and because it did not do so, the obligations of Airtech did not get triggered, was
according to him, contrary to the terms of the Associateship Agreement. Mr. Oberoi
argued that there was no privity of contract obtaining as between the Airtech and
DWASA. These were, according to him, two separate contracts though back- to-back.
The first one involved DWASA and PEC; while the second one was executed between
PEC and Airtech. Mr. Oberoi submitted that even though clause 4 of the Associateship
Agreement, provided that PEC would make payment to Airtech on receipt of money from
DWASA, it did not absolve PEC from making payment to Airtech, had Airtech fulfilled
its part of the obligations under the Associateship Agreement. The obligation of PEC
towards Airtech was independent of any obligation that PEC had towards DWASA.
9.1 In order to buttress his submission, Mr. Oberoi referred me to the letters dated
16.10.1995 and 26.10.1995. These letters have already been noticed by me hereinabove.
Based on the contents of the said communication issued by Airtech, it was submitted by
Mr. Oberoi that, the Arbitral Tribunal could not have come to the conclusion that the
Associateship Agreement obtaining between PEC and Airtech had not become operative.
In view of these facts, it was Mr. Oberoi's contention that the findings of Arbitral Tribunal
were perverse and hence, the award deserved to be set aside.
9.2 Mr. Oberoi also laid stress upon clause 8 of the Associateship Agreement, which
required Airtech to indemnify PEC in respect of any loss suffered by them qua the
contract executed between DWASA and PEC. It was his case that even as per this clause
PEC was entitled to money from Airtech in view of similar amount paid by PEC to
DWASA.
9.3 Mr. Oberoi further argued that if period of LC is calculated from 02.02.1995 till
04.11.1995, it remained open for 220 days and if it is calculated from 07.04.1995 i.e, the
date ADB issued its letter of commitment, the LC remained open for 191 days. Therefore,
the finding of the Arbitral Tribunal, according to him, even on this score was contrary to
the record.
10. As against, Mr. Mehra, Sr. Advocate assisted by Mr. Ritesh Verma addressed
arguments on behalf of Airtech.
10.1 Mr. Mehra briefly confined his submissions to the following. First, even if this
court were to come to a different conclusion, based on the material placed before the
Arbitral Tribunal, it would not provide, in law, a sufficient ground to set aside the award.
In his view, the challenge raised in the captioned petition did not fell within the purview of
Section 34 sub section(2) of the Arbitration and Conciliation Act, 1996 (in short,
"Arbitration Act").
10.2 Second, that in view of clause 16 of the GCC of the Associateship Agreement,
PEC could not rely on any correspondence which was exchanged between the parties as
the same was "null and void" as per the terms of the said clause. This argument was
directed to, the reference made by Mr. Oberoi, to letters dated 16.10.1995 and 26.10.1995.
10.3 Lastly, Mr. Mehra placed reliance on clause 17 of the GCC of the Associateship
Agreement to contend that the contract obtaining between PEC and DWASA was
necessarily an integral and inseparable part of the Associateship Agreement. The
argument being that the terms of the LC and its period of validity, were material for the
purposes of the Associateship Agreement obtaining between PEC and Airtech.
11. I have heard learned counsel for the parties. On reading of the award, in respect
of, the only issue which presently arises between the parties i.e. encashment of the bank
guarantee, it appears that the sum and substance of the finding of the Arbitral Tribunal is
that, in order to trigger the obligations of Airtech to supply the equipment, a valid LC
ought to have come into existence. A valid LC, according to the Arbitral Tribunal, would
be an LC which remained open continuously for a period of 180 days. In this context, the
Arbitral Tribunal noted that even though the LC, which had been decidedly opened on
02.02.1995, was extended from time to time till 04.11.1995 that, by itself was not legal
and hence, the obligation of Airtech under the contract did not get triggered.
11.1 In this context, I may only note an argument of Mr. Oberoi that if the period of the
LC is taken into account from 02.02.1995 to 04.11.1995, then the LC was actually
opened for a period of, 228 days. In the alternative, it was submitted by Mr. Oberoi, as
noticed hereinabove, that if the period were to commence from the date when letter of
commitment was issued by ADB i.e., 07.04.1995, then the LC as a matter of fact remained
open for 191 days.
11.2 Dehors the aforementioned argument, in my opinion there being no privity of
contract obtaining between Airtech and DWASA the argument of Airtech that it was not
legally bound to discharge its obligations under the Associateship Agreement was a
complete red herring. In my view, the Arbitral Tribunal has overlooked this crucial aspect
of the matter. It is not in dispute that PEC offered a bid in respect of tender floated by
DWASA based on the assurance of Airtech that it would manufacture and supply the
Equipment. As noticed above, even though this fact was in the knowledge of DWASA,
parties did not execute a tri-partite contract, instead two separate and independent
contracts were executed notwithstanding the overlap. DWASA, under its contract held
only PEC responsible for discharge obligations provided in the contract executed with it.
The obligations under the agreement obtaining between PEC and DWASA required them
to deliver the equipment at Pagla in Bangaldesh. This obligation of PEC even though
pivoted on Airtech supplying the equipment to PEC at Benapole, which is the border town
between India and Bangladesh; required PEC to engage the services of a local agent to
transport the Equipment from Benapole to Pagla. The Arbitral Tribunal lost sight of the
fact that the LC which DWASA was required to open, had to be in favour of PEC. The
LC was infact opened on 02.02.1995, and thereafter extended from time to time till
04.11.1995. As per the terms of the Agreement i.e., clause 3.2 it was the sole and
exclusive obligation of PEC to ensure that the supply of Equipment was completed within
180 days from the date of signing of the contract or receipt of LC whichever was later in
point of time. In view of this clause, PEC could not have taken a stand qua DWASA that
180 days would not commence from 02.02.1995. In order to ensure discharge of its
obligations, DWASA had sought from PEC a performance bond in the form of bank
guarantee, which PEC had furnished. On failure of PEC to discharge its obligations, one
of the consequences was that DWASA could invoke and encash PEC's bank guarantee.
As against this, the obligations which were undertaken by Airtech were independent of
those which PEC had undertaken qua its agreement with DWASA. This is clear on
reading clause 2 of the GCC of the Associateship Agreement which excluded Airtech's
obligation qua the contract executed between PEC and DWASA to the extent they were
"specifically reserved to be performed or fulfilled by PEC". Therefore, the incorporation
by reference, the terms of contract obtaining between PEC and DWASA in the
Associateship Agreement, would have in no way made Airtech liable to DWASA in the
event of non supply of the Equipment by Airtech. Clause 17 of the GCC would have to be
read in conjunction with clause 2 of the GCC and other terms of the Associateship
Agreement. The findings of the Arbitral Tribunal that the obligations of Airtech did not
commence in terms of their agreement with PEC is, in my view, perverse. Best evidence
of this is, the letters dated 16.10.1995 and 26.10.1995 wherein, Airtech had indicated that
they were unable to make supplies in view of their difficulties with the supplier of
chassis. As a matter of fact, they sought extension of LC till 30.06.1996. It could not
have been a stand of PEC that, if equipment was supplied by Airtech, it would not make
the payments to Airtech in case DWASA were to renege its obligation under the contract
with PEC. The obligation interse PEC and Airtech to that extent were mutual and
exclusive to the obligations obtaining in the contract subsisting between DWASA and
PEC.
11.3 Furthermore, in the context of the above much stress was laid on Clause 4 of the
Associateship Agreement and clause 17 of the GCC. It was sought to be argued that the
obligation to furnish an LC, and to keep it open continuously for a period of 180 days by
virtue of clause 17 of GCC, formed an inseparable part of the Associateship Agreement.
First and foremost, each clause would have to be read in the context of all other clauses
obtaining in Associateship Agreement. Clause 2 of GCC, as observed hereinabove, makes
that crystal clear. In this context let's examine what is envisaged by clause 17 of GCC
and clause 4 of the Associateship Agreement. The opening line of clause 17 stipulates
that only those conditions, which are not agreed to in the Associateship Agreement, shall
stand incorporated. Clause 4 of the Associateship Agreement, on the other hand,
prescribed only the mode and the procedure for payment. The opening words of said
clause 4, which read as follows, make that clear: "PEC shall pay the Associate by the
following procedure". Therefore, the finding of the Arbitral Tribunal that the LC had to
be kept open for a continuous period of 180 days; a term of the contract, could not in my
view have been telescoped into the Associateship Agreement obtaining between PEC and
Airtech.
11.4 It is no one's case, as it cannot be, that the mode of payment to Airtech was by
way of a LC. The terms of payments i.e., clause 4 of the Associateship Agreement clearly
bring to fore that point. Thus, Airtech on supplies being made to PEC was to be paid in
terms of clause 4 which did not envisage payment through LC. A perusal of clause 4 of
the Associateship Agreement, shows that PEC undertook to make payment to Airtech on
receipt of money from DWASA; that by itself could not construed to mean that Airtech, in
law, was not required to commence manufacture of the Equipment since the LC had to
remain valid for a continuous period of 180 days. The entire purpose, it appears, to
provide for a validity period in the LC which, would run concurrently with the period
provided for execution of the contract (obtaining between PEC and DWASA) seems to be
that since, it was a contract for supply of Equipment, the supplies may not perhaps have
been made in one go. Therefore, the period of LC being made co-terminus with the period
of execution of the contract would perhaps have been incorporated to give comfort to
PEC. Clause 3.2 of the SCC to the contract was for the benefit of PEC, and bound only
PEC qua DWASA. It was the obligation of PEC to reach the Equipment to Pagla, for
which it was given 180 days. Clause 3.2 of SCC made it clear that 180 day period would
commence once an LC was opened. It is no one's case that encashment of bank guarantee
took place before expiry of 180 days, which commenced with effect from 02.02.1995.
Which is why, perhaps on 08.11.1995 Airtech wrote to PEC that it could encash its bank
guarantee only if PEC's bank guarantee had been encashed. The fact that LC was not
open for a continuous period of 180 days could not have given an excuse to Airtech to
wriggle out of its promise to perform its obligation under the Associateship Agreement to
supply the Equipment within a period of 180 days.
11.5 As a matter of fact, as per clause 7 of the Associateship Agreement, Airtech was
required to furnish within 30 days of the execution of the said agreement, a detailed
programme for manufacture of the Equipment, taking into account the delivery schedule
stipulated in the contract. Airtech was required to inform PEC on a fortnightly basis the
progress on the manufacture of the Equipment to be supplied under the contract obtaining
between PEC and DWASA. Similarly, under clause 5 and 8 of the GCC of the
Associateship Agreement, Airtech had to reimburse and / or indemnify PEC in respect of
any claim by DWASA. These clauses give intrinsic evidence of the limited inter-linkage
between the contract obtaining between PEC and DWASA on the one hand, and the
Associateship Agreement obtaining between PEC and Airtech, on the other. To infer from
this, that the obligations of Airtech to execute the contract did not commence as the LC
was not opened for a continuous period of 180 days is, in my view, completely contrary to
the terms of the Associateship Agreement. Furthermore, I am also in agreement with Mr.
Oberoi's submission that the case set up by Airtech was that it had commenced in its
obligations under the Associateship Agreement. Mr Oberoi had in this regard placed
reliance on Issue no.8 culled out in the Award. A reading of Issue no.8 would show that
Airtech sought to lay a monetary claim with respect to parts of Equipment which it had
purportedly purchased and / or fabricated. In these circumstances for the Arbitral Tribunal
to conclude that Airtech's obligations had not commenced appears to be contrary to the
record; even though it is another matter that this claim was rejected by the Arbitral
Tribunal.
11.6 Mr. Mehra's submission based on clause 16 of GCC of the Associateship
Agreement that the correspondence obtaining between parties could not be referred to as,
in terms thereof it had to be considered as null and void; is untenable. The reason being
that a bare perusal of clause 16 of the GCC of the Associateship Agreement would show
that it refers to correspondence which is exchanged, between the parties prior to the
execution of the contract, and not post, the execution of the contract.
12. It is well settled that the award can be set aside on the ground of perversity. In this
regard see the observations made in Security Printing and Minting Corporation of India
Ltd & Anr. vs Gandhi Industrial Corporation (2007) 13 SCC 236 paragraph 16 at pages
244 and 245 and ONGC Ltd vs Garware Shipping Corporation Ltd (2007) 13 SCC 434
paragraph 30 at page 441.
13. The findings of the Arbitral Tribunal being perverse, the objections are allowed
and the Award dated 06.11.1998 is set aside.
RAJIV SHAKDHER, J SEPTEMBER 16, 2010 yg
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!