Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Gas Authority Of India Ltd. vs M/S Bansal Contractors (India) ...
2010 Latest Caselaw 4799 Del

Citation : 2010 Latest Caselaw 4799 Del
Judgement Date : 18 October, 2010

Delhi High Court
Gas Authority Of India Ltd. vs M/S Bansal Contractors (India) ... on 18 October, 2010
Author: Vipin Sanghi
*     IN THE HIGH COURT OF DELHI AT NEW DELHI

+                     Date of Decision: 18.10.2010

%                             O.M.P. No.149/2004


      GAS AUTHORITY OF INDIA LTD.           .....Petitioner
                     Through:   Mr. Rajiv Bansal & Mr. Amandeep,
                                Advocates

                     versus


      M/S BANSAL CONTRACTORS (INDIA) LTD. .....Respondent
                     Through:  Mr. R.D. Shah & Mr. Anil Aggarwal,
                               Advocates

      CORAM:
      HON'BLE MR. JUSTICE VIPIN SANGHI

      1. Whether the Reporters of local papers may
         be allowed to see the judgment?                 :       No

      2. To be referred to Reporter or not?              :       Yes

      3. Whether the judgment should be reported
         in the Digest?                                  :       Yes


VIPIN SANGHI, J. (Oral)

1. This petition has been preferred under Section 34 of the

Arbitration & Conciliation Act, 1996 (the Act) to challenge the award

dated 11.08.2003 passed by Sh. Harish Chandra, sole arbitrator,

whereby various claims of the respondent/contractor have been dealt

with by the learned arbitrator.

2. The primary objection raised by learned counsel for the

respondent at the time of making his submissions is that the arbitral

tribunal has committed a patent illegality in not accepting the

submission of the petitioner/objector that there was accord and

satisfaction and consequent discharge of the contract, inasmuch, as

the respondent had given a no dues certificate dated 19.09.1999

(which has been noted by the arbitral tribunal at various places as

14.09.1998 in the impugned award), and the respondent had failed to

even plead, much less prove that the said no dues certificate had been

issued under coercion or undue influence.

3. The submission of Mr. Bansal is that the payment of the final

bill had been made to the respondent contractor on 14.09.1999. The

said no dues certificate had been issued five days later i.e. on

19.09.1999. The petitioner, on 27.10.1999, issued a communication

merely stating that the petitioner had made some deductions

incorrectly. Even at that stage the respondent/contractor had not

taken the stand that the no dues certificate was issued under coercion

or undue influence. He submits that the tribunal while dealing with the

issue has completely omitted the notice the fact that coercion or

undue influence were never pleaded by the respondent/contractor,

neither contemporaneously on 27.10.1999, nor before the tribunal.

4. Mr. Bansal further submits that the petitioner had moved an

application at the initial stage of the arbitration i.e. on 30.032001

requiring the tribunal to decide the issue of maintainability of the

claims of the respondent/contractor as a primary issue as, according to

the petitioner, the respondent/contractor had issued a no dues

certificate. However, the arbitral tribunal did not decide the said issue

as a primary issue and kept the same pending for determination only

after hearing the arguments of all the claims raised by the

respondent/contractor.

5. I have gone through the arbitral award on the aforesaid

aspect. The aforesaid submission of learned counsel for the petitioner

is founded on the premise that a no dues certificate can be assailed by

the author of such a certificate only if the author/contractor is able to

establish the existence of coercion or undue influence. However, a

perusal of the impugned award shows that there are various other

factors which have weighed with the arbitral tribunal in rejecting the

reliance placed on the said no dues certificate by the petitioner. I must

hasten to add that the arbitral tribunal has also held that the said no

dues certificate was indeed signed under pressure, coercion and undue

influence. The following aspects need to be noted in the facts of this

case:

(i) The no dues certificate was issued in accordance with Clause

94.4 of the general conditions of contract. 94.4(b) mandates

that a "No Claim Certificate" shall accompany the final bill. It,

therefore, follows that whether or not the contractor agrees with

the final measurement/rates that the petitioner employer may

agree to treat as the basis for computing the amount due, and

whether or not the contractor agrees with the deductions that

the petitioner employer may make for whatsoever reason, the

contractor is obliged to give a no claim certificate along with the

final bill and without such a certificate, the submission of the

final bill itself would be defective and may not be processed by

the petitioner employer.

(ii) The no dues certificate was issued for an amount of

Rs.8,68,551/-. The said certificate stated that the contractor had

received the sum of Rs.8,68,551/- (Rupees Eight Lakhs Sixty

Eight Thousand Five Hundred and Fifty One Only) "in full and

final settlement of all the payment due to us for construction of

Club Building & Shopping Complex at UPPC Nagar, Dist. Atawah,

UP executed by us under the contract agreed between us and

giving including all amount payable to us as per the contract, we

hereby unconditionally and without any reservations whatsoever

certify that with this payment we shall have not claim

whatsoever described. On aim account whatsoever from against

the aforesaid job executed by us use full fledge ok claim

unequivocally that with this payment we have received all the

amounts payable to use and have no outputs of any description

what so ever regarding the amount wanted out of payable by us

and the amounts receive by us and that we shall be continued be

bound by the time and concidile of the agreement as regards the

performance of the Contract. However, even according to the

petitioner the petitioner made payment of a sum of Rs.9.02 Lacs

on 14.09.1999 to the respondent. If full and final payment had

been made by the petitioner on 14.09.1999 for the amount of

Rs.9.02 Lacs, where was the occasion for the respondent

contractor to issue a no dues certificate five days later for a

lesser amount of Rs.8.68 Lacs?

(iii) Admittedly the petitioner made further payments to the

respondent contractor after 22.12.1999 i.e. Rs.5,65,244/-

towards escalation bill. A further amount was paid on

08.03.2000. The aforesaid clearly shows that the no dues

certificate which in categorical terms stated that the amount of

Rs.8.68 Lacs had been received in full and final satisfaction of all

claims, and that no amount was due from the petitioner was not

worth the paper it was written on. Though the evidence brought

on record in this respect has not been discussed in the award

itself, my attention has been drawn to an affidavit by way of

evidence filed by the respondent, namely, the affidavit of Nav

Rattan Tripathi, who was working as the Project In-charge of the

respondent for the work in question. In this affidavit he has

stated as follows:

"(a) That I was authorised by Sh. S K Bansal, Director, New Delhi to collect the cheques of certain payments due under the works contract for construction of club building and shopping centre complex of G.A.I.L. at Dibiyapur. I went to GAIL office to collect the cheque payments on the 14th Sep 1999 as usual. The Dy.

Manager Sh. P.K. Singh of GAIL told me that the cheque No.953725 dt. 9.9.99 was ready for delivery but could not be given to me unless and until a certificate of full and final settlement is given to him. I replied that in addition to this payment, the payment for

served extra items & claims for Rs.68,25,192/- is due to be paid as per my HO letter dt. 3.9.98 and also Escalation Bill for materials and labour.

(b) The Dy. Manager of the Authority gave a threat to me on 14.9.99 that if the prescribed certificate of settlement was not given to him, he would not hand over the cheque dt. 9.9.99 for Rs.9,02,651/- and would stop the payments of Running Bills of other two contracts and also recommend for non-grant of extention of time and stop the payment of Escalation Bill. He refused to hand over the cheque dt. 9.9.99 asking me to cally Sh. S K Bansal Director.

(c) That I called Sh. S K Bansal Director of my Company on 14.9.99 who also protested for such full and final certificate but he was given the same threat to him and the Dy. Manager (Finance) gave a typed certificate to me in the presence of Sh. S K Bansal to write and sign in my own hand-writing. The labourers and the material suppliers had been giving a threat to go on strike under the two other contracts for construction of 34C-type quarters and one Hostel Building (started in March 99) due to non-payments and therefore I and Sh. S K Bansal signed the No Demand certificate on 14 Sep 99 under duress and undue influence exercised by the Dy. Manager (Finance) of the Authority.

(d) That the Dy. Manager (Finance) released the last payment under this contract on 8.3.2000 towards the Escalation bill for Rs.5,67,344.00 after the Extention of time was communicated on 22 Dec 1999 by the Authority."

6. The arbitral tribunal in the impugned award, while rejecting

the aforesaid primary objection of the petitioner, has held as follows:

"I have gone through the pleadings of both sides as well as their arguments. Courts have agreed that the decision whether there was a

full and final settlement is within the jurisdiction of the Arbitrator. There are judgments to the effect that once full and final settlement has taken place, the cases should not be reopened and no further claims can be made. At the same time, there are judgments to the effect that when No Claim Certificates do not fulfill the requirements of full and final settlement they are not binding. A study of these judgments shows that the NOC is considered as and estoppel on further claims where the NOC has been preceded by discussions of disputes, if any, and both Claimant and Respondent have come to an agreed amount as the payment due. In such cases, the receipt is signed by the Claimant as full and final settlement for the amount to which both the parties have agreed. However, where a No Claim Certificate has been signed without the parties coming to an agreed amount or where the Claimant is not aware of the total amount (and break up of the amount) he is being paid or where the No Claim Certificate is merely by way of a precondition for processing of bills, the Courts do not favour rejection of consideration of claims merely on the basis of a No Claim Certificate.

In the present case, the final bill was required to be submitted along with the No Claim Certificate as a pre-requisite for examination and processing of the bill. It could not be understood to be an Agreement to the amount of the final bill as passed by the Respondents, as the bill was still to be scrutinized. Claims existed before the final bill was passed regarding liquidated damages, escalation, extra items, deduction items etc. and there is no evidence to show that a consensus was arrived at these disputes. Even after the "final bill" was paid on 14.9.99, the disputes continued. The Claimants - BCIL represented on 29.10.1999 against recovery of liquidated damages etc. and Respondents - GAIL held meetings on 20.12.99, during which the Consultants Raj Rewal Associates put on record that they had recommended extension of time without liquidated damages initially as well as on subsequent review. The Contractor also

agreed to withdraw all other items subject to reconsideration of time extension without liquidated damages. No consensus was arrived at. The extension of time with 8% compensation was finally granted to the Claimants - BCIL on 22.12.99. Final escalation was paid on 16.2.2000. It is obvious that under these circumstances, the No Claim Certificate, signed on 14.9.99, cannot be treated as full and final settlement and as an Agreement between Claimants and the Respondents.

7. It is well-settled that the arbitral tribunal is the master of the

facts and the award made by the arbitral tribunal cannot be interfered

with in proceedings under Section 34 except on the specific grounds

provided for under the law and as interpreted by the Supreme Court in

the case of ONGC vs. Saw Pipes (2003) 5 SCC 705. From the

aforesaid extract, it cannot be said that the arbitral tribunal has

committed any patent illegality or that the award is not in accordance

with the law. The award on this aspect cannot be said to be an award

opposed to the public policy.

8. The practice of the petitioner requiring the submission of a no

claim certificate/no due certificate along with the final bill itself

appears to be pernicious. The said requirement, by itself, is a clear

indicator of the fact that the contractor has been subjected to coercion

and undue influence as the contractor is left with no option, but to

submit such a certificate so as to get whatever payment the petitioner

employer is willing to release, even if, according to the contractor the

said amount is not the complete amount.

9. Moreover the fact, that repeatedly further payments were

made to the contractor even subsequent to the signing of the no dues

certificates, shows that there was no sanctity attached to the said no

dues certificate. If it were actually a no dues certificate, prepared after

taking full and complete accounts between the parties, there would

have been no occasion to make any further payment to the contractor

after the issuance of the no dues certificate. Consequently, I reject the

aforesaid submission of Mr. Bansal.

10. Mr. Bansal has also raised objections to the award on claim

Nos.4, 7 & 10. Claim No.4 had been made for the amount of

Rs.85,904/- to seek reimbursement of deductions made against the

alleged shortcomings in the execution of the works. The learned

arbitrator has noted that most of the defects, which were belatedly

pointed out by the petitioner, were in items of finishing. One of the

items of deduction of Rs.34,000/- was on account of mosaic tiles for

which no details were available in the inspection notes. Taking into

account the aforesaid position, the learned arbitrator awarded an

amount of Rs.40,000/- as excessive recovery. From the award it

cannot be said that the same is, in any way, unreasonable. I,

therefore, find no merit in this submission and reject the objections

raised to claim No.4.

11. Claim No.7 had been made by the respondent contractor for

reimbursement of deductions made towards rectification done by

another contractor, namely, S.B. Construction. The respondent had

provided MDF door frames according to the item in the contract. They

had been purchased from the various authorized dealers as approved

by the petitioner's architect. Defects pointed out also been rectified.

However, the petitioner got the MDF door frames replaced by wooden

frames without notice to the respondent and deducted the amount

from the respondent's bill. The arbitrator noticed that the supplies had

been made through approved bills and there was no complaint during

construction and even during the routine checks. He also notes that

only after the MDF door frames had been received and fixed, orders

were issued on 27.10.1997 not to use MDF shutters as the material

itself was defective. As no notice was issued to the contractor prior to

replacement at its risks and costs the learned arbitrator allowed the

claim to the extent of Rs.87,084/-. Here again I see no merit in the

objection raised by the petitioner to the said award. The MDF doors

were not replaced because of any deficiency in the service of the

respondent but because of inherent defect in the material. Neither is

there any patent illegality nor can it be said that the arbitrator has

adopted a legal principal which is opposed to public policy of India.

12. So far as the objection to the award made on claim No.10 is

concerned, once again I find no merit in the submission of Mr. Bansal.

The claim No.10 had been made to seek refund of the amount of bank

guarantee of Rs.1,24,323/-. In response to the said claim, the stand

taken by the petitioner in its notice was that the work was under CTE

observations and the same was yet to be received. The learned

arbitrator has held that the petitioner GAIL had already made all the

deductions in response to CTE's observations and, therefore, directed

refund of the full amount of bank guarantee of Rs.1,24,323/-.

13. The submission of the petitioner is that a deduction of about

Rs.30,000/- had been made from the aforesaid amount of Rs.1,24,323/-

and consequently the arbitrator ought to have allowed the deduction

to that extent. However, there is no pleading to the aforesaid effect

found in the reply filed by the petitioner before the arbitral tribunal.

The issue with regard to the deduction not having been raised before

the tribunal, the same has not been even adjudicated upon and,

therefore, there can be no justification for making any deductions for

the bank guarantee amount. In my view, the award of claim No.10

cannot, therefore, be assailed.

14. Accordingly, this petition is dismissed, leaving the parties to

bear their respective costs.

VIPIN SANGHI, J.

OCTOBER 18, 2010 rsk

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter