Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Ashoka Electrical ... vs Govt. Of Nct Of Delhi & Ors.
2010 Latest Caselaw 4720 Del

Citation : 2010 Latest Caselaw 4720 Del
Judgement Date : 6 October, 2010

Delhi High Court
M/S. Ashoka Electrical ... vs Govt. Of Nct Of Delhi & Ors. on 6 October, 2010
Author: S. Muralidhar
        IN THE HIGH COURT OF DELHI AT NEW DELHI

             W.P.(C) No. 12556-57 of 2004 & CM No. 8714 of 2004

                                        Reserved on: September 21, 2010
                                        Decision on: October 6, 2010

      M/S. ASHOKA ELECTRICAL INDUSTRIES
      & ORS.                                        ..... Petitioners
               Through: Ms. Radhika Chandershekhar, Advocate.

             versus

      GOVT. OF NCT OF DELHI & ORS.                  ..... Respondents
               Through: Ms. Renuka Arora, Advocate.

      CORAM: JUSTICE S. MURALIDHAR

      1. Whether reporters of the local news papers
         be allowed to see the judgment?                        No
      2. To be referred to the Reporter or not?                 No
      3. Whether the judgment should be reported in the Digest? No
                            JUDGMENT

06.10.2010

1. The short prayer in this writ petition is for a direction to the Respondent

No. 3 Delhi State Industrial Development Corporation Limited („DSIDC‟)

to extend the benefit of the general amnesty scheme to the Petitioners in

respect of Plot No. 201, Pocket-K, Sector2, admeasuring 150 sq.m. in the

Bawana Industrial Area (hereafter „the plot in question‟). The Petitioner

also challenges the letter dated 15th December 2003 issued by the DSIDC

cancelling the Petitioners‟ allotment of the plot in question.

2. The Petitioner had earlier filed Writ Petition (C) Nos. 7917 & 7918 of

2004 in this Court challenging the cancellation of allotment. This Court

recorded the statement of the learned counsel for the Petitioners that "in

view of the amnesty scheme brought into force on 28 th April 2004, the

Petitioner should be permitted to avail of the said scheme as the Petitioner

was only short of Rs. 3,000/- to avail of the amnesty scheme." This Court

by its order dated 17th May 2004 left it open to the Petitioners to apply

under the amnesty scheme and seek condonation of delay in so far as the

amount of ` 3,000/- was concerned. It was further directed that "the

Respondent shall consider the case of the Petitioner in accordance with the

norms".

3. Thereafter the Petitioners tendered ` 3,000/- and also submitted a fresh

application on 14th June 2004 to the DSIDC. The Petitioners state that they

learnt that the DSIDC had refunded the loan amount advanced by the Delhi

State Finance Corporation („DFC‟) to the Petitioners for the purchase of the

plot in question. Thereafter, the Petitioners got bank drafts in the sum of ` 2

lakhs and another draft in the sum of `10,000/- in favour of the DSIDC

prepared and submitted them to the DFC for onward submission to the

DSIDC. The DSIDC however returned the drafts and in the circumstances

the Petitioners again approached this Court with this petition.

4. In its order dated 30th July 2004, this Court recorded that the Petitioners

had brought a total sum of ` 2,10,000/- to the Court and that the Petitioners

were willing to pay the balance amount as well. It was then directed that the

Petitioners should approach the DSIDC to ascertain the balance amount and

thereafter deposit the entire balance amount within two days.

5. The Petitioners subsequently filed documents to show that the order

dated 30th July 2004 was complied with. In its reply to the writ petition, it

is pointed out by the DSIDC that the Petitioner failed to pay the installment

amounts to the DFC as per the loan agreement. Consequently, the DFC

informed the DSIDC that the loan amount should be refunded to it along

with the margin money deposited by the Petitioner with the DSIDC. This

led to the impugned order dated 15th December 2003 of the DSIDC

cancelling the allotment.

6. It is pointed out by the DSIDC that the allotment letter dated 23rd October

2000 sent to the Petitioners intimating the cost to be ` 4200/- per sq.m. was

only a tentative rate and was subject to change. In terms of the revised rate,

the total cost of the plot worked out to ` 6,30,000/-. The Petitioners had

deposited ` 3,15,000/- up to 25th September 2001 and this was only 50% of

the cost. As regards the payment of ` 1,35,000/- claimed to have been made

by the Petitioners, the DSIDC denied receiving any such payment. The

DSIDC has enclosed the relevant extracts from the accounts.

7. This Court finds that the only explanation offered by the Petitioners for

the delay in making the payment within time was that no demand has been

raised and, therefore, they could not deposit the amount. It is pointed out by

the DSIDC that an advertisement was issued in the newspapers on 17th

August 2003 indicating the time within which objections to the revision of

rates had to be filed. It is pointed out that it was for the Petitioners to

ascertain the balance amount and pay it within the extended time. There

could not be an indefinite extension of time for making payment. The

refund having been made by the DSIDC to the DFC on 15th December 2003

itself, the unilateral payment made thereafter by the Petitioners to the DFC

was to no avail.

8. It appears that the Petitioners failed to follow up the matter promptly and

diligently. In fact, the Petitioners claim not to have been aware of the fact

that the DFC had cancelled the loan and the DSIDC had refunded the

amount to the DFC. In the circumstances if the allotment was cancelled, the

DSIDC cannot be faulted. It is not possible to have an indefinite extension

of time for making payments as these are covered by the terms and

conditions of the allotment. The explanation offered by the DSIDC for not

considering the case of the Petitioners for restoration of allotment appears

to be a plausible one and does not suffer from any legal infirmity.

9. For the aforementioned reasons, this Court is not inclined to entertain this

writ petition and grant the reliefs as prayed for. It will be open to the

Petitioners to seek from the DSIDC refund, in accordance with law, of

whatever monies that have been paid to the DSIDC pursuant to the order

dated 30th July 2004 of this Court. The DSIDC shall process such request in

accordance with the extant rules and refund to the Petitioners the admissible

amount together with interest, if any, thereon within four weeks thereafter.

10. With the above observations, the writ petition and the application are

dismissed.

S. MURALIDHAR, J OCTOBER 6, 2010 dn

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter