Citation : 2010 Latest Caselaw 4715 Del
Judgement Date : 6 October, 2010
*IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of decision: 6th October , 2010.
+ W.P.(C) No.6585/2007
%
INDERJIT SINGH ..... PETITIONER
Through: Mr. Kapil Sankhla, Advocate.
Versus
NORTH DELHI POWER LTD. ..... RESPONDENTS
Through: Mr. K. Datta & Ms. Manish Srivastava,
Advocates.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? NO
2. To be referred to the reporter or not? NO
3. Whether the judgment should be reported NO
in the Digest?
RAJIV SAHAI ENDLAW, J.
1. The petition impugns the speaking order dated 3 rd November, 2006 of
the respondent finding the petitioner guilty of Dishonest Abstraction of
Energy (DAE) and consequent demand for `2,44,647/-. This Court while
issuing notice of the petition on 11th September, 2007 restrained the
respondent from enforcing the demand impugned, subject to the petitioner
depositing a sum of `50,000/- with the respondent. The said amount was
reported to have been deposited and the interim order was made absolute on
22nd May, 2009. The respondent has filed a counter affidavit and to which a
rejoinder has been filed by the petitioner. The parties were referred to the
continuous Lok Adalat of this Court but no settlement could be arrived at.
The counsels have been heard.
2. The dispute relates to the electricity connection for domestic purposes
installed in the premises of the petitioner at RA-73, Inderpuri, New Delhi.
Besides the said domestic electricity connection, the said premises is also
provided with a commercial electricity connection for the shop run by the
petitioner on the ground floor of the property.
3. The case of the petitioner is that the domestic electricity connection
and to which the dispute pertains was burnt at 2330 hours in the night on 15 th
September, 2006 and on immediate reporting by the petitioner, officials of
the respondent reached the premises at 0115 hours in the night and made the
electricity supply direct with the assurance to replace the burnt meter;
however the officials of the Enforcement Assessment Cell, Keshavpuram,
Lawrence Road, Delhi of the respondent visited the premises of the
petitioner on 16th September, 2006 i.e. the very next date and gave a show
cause notice to the petitioner unnecessarily booking the petitioner under
Sections 126 & 135 of the Electricity Act, 2003; the petitioner appeared
before the concerned official of the respondent on 25 th September, 2006 but
the respondent without regard to the submissions of the petitioner passed the
impugned speaking order and raised the impugned demand. The petitioner
denies that he has indulged in any DAE of which he has been found guilty.
4. The respondent in its counter affidavit admits receipt of a complaint
of burning of the electricity meter from the petitioner in the night on 15th
September, 2006 but pleads that on visit the electricity meter was found to
be in a smoky condition with the neutral terminal burnt; the respondent
admits that the electricity connection was made direct in the night with a
view to restore electricity supply to the petitioner immediately to avoid
inconvenience and in accordance with Regulation 17(vii) of the DERC
(Performance Standards - Metering & Billing) Regulations, 2002, an
inspection team visited the premises of the petitioner on the next day and
carried out the inspection in the presence of the petitioner to ascertain if
there existed any kind of theft/tampering/DAE; it is pleaded that during the
said inspection the following irregularities were found:-
"a. Meter box hinges had been tampered.
b. Both meter box seals had been tampered.
c. Meter terminal seal had been tampered.
d. Both the half seals of the meter had been tampered.
e. All sticker seals had been tampered and re-fixed.
f. The said domestic electricity connection was being misused for
commercial purposes."
5. It is yet further pleaded that the inspecting team discovered the
connected load of 7.76 kW as against the sanctioned load of 0.50 kW and
accordingly a case of DAE booked and show cause notice issued.
6. The counsel for the petitioner has contended that the demand
impugned has been raised without arriving at any finding of DAE. It is urged
that merely from the observations of the box hinges and the seals having
been found tampered, no inference of DAE can be drawn. Reliance in this
regard is placed on (i) Udham Singh Vs. BSES Rajdhani Power Ltd. 136
(2007) DLT 500; (ii) Jagdish Narayan Vs. NDPL 140 (2007) DLT 307; and
(iii) J.K. Steelomelt (P) Ltd. Vs. BSES Rajdhani Power Ltd. 140 (2007)
DLT 563.
7. It is contended that the respondent did not carry out any other tests to
reach a finding of DAE; it is urged that accu-check was not done. It is yet
further urged that the findings of breaking of hinges of the meter box and of
seals being tampered are not presumptive of DAE in as much as the meter
was burnt and the same could have happened even
during burning of the meter or while making the supply direct. It is yet
further contended that the findings of the electricity connection being used
for commercial purposes are without regard to the fact that another
commercial electricity connection existed in the premises.
8. It was enquired from the counsel for the petitioner whether the meter
of the petitioner was sent to NABL accredited laboratory as required under
the Regulation 52 (viii) of Delhi Electricity Supply Code and Performance
Standards Regulations, 2007. The counsel for the petitioner replies in
negative. The counsel for the respondent however informs that the procedure
of sending the meter to NABL accredited laboratory has been introduced for
the first time in the 2007 Regulations and there was no such requirement
under the 2002 Regulations in force at the relevant time.
9. The counsel for the respondent has opposed the argument of the
petitioner of the possibility of the hinges and the seals being broken during
the burning of the meter by stating that the respondent does not admit that
the meter had burnt and has pleaded that the meter was in a smoky condition
with only the neutral terminal burnt. On enquiry as to why the meter was
not sent for accucheck, the counsel for the respondent states that since it is
the case of the petitioner himself that the meter had burnt and was not
functioning, a non-functional meter could not be sent for accu-check. The
counsel for the petitioner rejoins by contending that the respondent cannot
on the one hand state that the meter was not burnt and on the other hand
contend that accucheck was not carried out owing to the meter having got
burnt.
10. The counsel for the respondent also draws attention to the reply given
by the petitioner to the show cause notice and contends that the petitioner
did not reply to the specific charges and merely stated that the meter seals
must have shrunk and must have sustained damage. Reliance is placed on
J.M.D. Alloys Ltd. Vs. Bihar State Electricity Board (2003) 5 SCC 226
contending that the said judgment has not been noticed in any of the
judgments cited by the counsel for the petitioner and that the Apex Court has
laid down that the tampering of the seal is enough to a conclude DAE. It is
argued that the respondent has proceeded against the petitioner in
accordance with the Regulations and the law; that the petitioner has availed
of the hearing had no substantive reply to the allegations and thus no case
for interference in writ jurisdiction has been made out. With reference to the
judgments cited by the counsel for the petitioner, it is urged that those were
cases where one or maximum two seals were found tampered but in the
present case all the seals were found tampered and thus the said judgments
will not apply.
11. This Court in Udham Singh (supra) with reference to the 2002
Regulations held that mere irregularity in meter seals or breakage of glass
etc. do not justify issuance of a show cause notice for DAE; the assessing
officer is required to observe the consumption pattern before making out a
case for DAE. It was further held that in the absence of any collateral
evidence, the only basis for DAE could be the consumption pattern and in
the absence of DAE having been established from the consumption pattern,
no case for DAE can be made out. It was further held that when the meter is
not checked for accuracy or defects, the findings of DAE were flawed.
12. In Jagdish Narayan (supra) it was held that in order to draw a
presumption of DAE against a consumer, it first must be shown that an
artificial means or means not authorized by the Board or licensee existed for
the abstraction, consumption or use of electricity by the consumer - till such
time this initial burden is discharged by the supplier of electricity, burden of
proof does not shift to the consumer. It was further held that mens rea or
intention of the consumer to dishonestly abstract electricity must be proved
"conclusively" to bring home the charge of DAE - that can be established
only by showing that the consumer was responsible for tampering the meter
by some visible means and the external manifestations of tampering
can only raise a suspicion which cannot take the place of proof. In this
judgment it was observed that an accu-check meter can be deployed to find
out if the meter indicates recording lesser units and the analysis of
consumption pattern is merely corroborative and not substantive evidence of
DAE. The judgment of the Apex Court in J.M.D. Alloys Ltd. (supra) cited
by the counsel for the respondent was also considered in Jagdish Narayan
and was held to have been rendered in the context of an industrial consumer
and in a different set of facts and not applicable.
13. In J.K. Steelomelt (P) Ltd. (supra) also it was held that it is one thing
to plead that the connected load is more than the sanctioned load but is
another to say that in fact the connected load has been used throughout and
merely because the connected load is more than the sanctioned load cannot
lead to an automatic presumption of DAE.
14. It would thus be seen that the counsel for the respondent is not right in
contending that the judgment of the Apex Court in J.M.D. Alloys Ltd. has
not been considered in any of the aforesaid judgments.
15. In so far as the counsel for the respondent has tried to distinguish the
judgment aforesaid on the basis of the number of seals tampered with, as
would be apparent from the above discussion, it is not the number of seals
which is determinative. What has been laid down in the judgments of this
Court is that there should be some conclusive evidence of DAE having been
intentionally practiced by the consumer. In the present case also, there is
none. Inspite of the case having remained pending for a considerable long
time, the respondent has not even pleaded that the subsequent consumption
against the electricity connection also justifies a case of DAE. There is also
no discussion in the speaking order impugned, with reference to the other
commercial electricity connection in the premises i.e. whether load found
was connected to the other meter or not and if not as to what was the load
connected to the other commercial meter. In view of the said fact, no
reliance can be placed on the case of the respondent of higher connected
load also.
16. Thus, following the judgments aforesaid, the case made out by the
respondent against the petitioner of DAE cannot be sustained. The speaking
order dated 3rd November, 2006 is quashed/set aside. Axiomatically, the
demand in pursuance thereto is also quashed/set aside. The petitioner has
become entitled to refund of `50,000/- deposited as a condition for the
interim stay. Since the respondent has enjoyed the sum of `50,000/- for the
last approximately three years, the respondent is liable for payment of
interest thereon to the petitioner. A lump sum amount of `12,000/- towards
interest on `50,000/- for the last three years is awarded. The respondent is
directed to adjust the sum of `62,000/- in the future bills of the petitioner
against either of the connections.
17. The petition is disposed of. The respondent to also pay costs of
`10,000/- of this petition to the petitioner. If the cost is not paid within four
weeks, the same to be also included in the amount to be adjusted as
aforesaid.
RAJIV SAHAI ENDLAW (JUDGE) 6th October, 2010 pp..
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!