Citation : 2010 Latest Caselaw 2744 Del
Judgement Date : 24 May, 2010
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ W.P.(C) No.3631/2010
%
Date of Decision: 24.05.2010
Delhi Development Authority .... Petitioner
Through Mr.Arun Birbal, Advocate.
Versus
Sh.Om Prakash .... Respondent
Through Mr.Siddharth Joshi & Santosh Kumar,
Advocates.
CORAM:
HON'BLE MR. JUSTICE ANIL KUMAR
HON'BLE MR. JUSTICE MOOL CHAND GARG
1. Whether reporters of Local papers may be YES
allowed to see the judgment?
2. To be referred to the reporter or not? NO
3. Whether the judgment should be reported NO
in the Digest?
ANIL KUMAR, J.
*
The petitioner has impugned the order dated 27th May, 2009
passed by the Central Administrative Tribunal, Principal Bench, New
Delhi in O.A.No.2104 of 2008, titled as „Om Prakash v. Delhi
Development Authority & another‟, allowing the application of the
respondent for quashing the charges framed against the respondent on
the basis of a quality control report which was made without any
inspection of the actual site.
The respondent was a Superintending Engineer and he had
challenged the Charge Memorandum dated 24th March, 2008 initiated
against him under Regulation 27 of DDA (Conduct, Discipline & Appeal)
Regulations, 1999.
The charge pertained to the period 1993-95 when the respondent
was posted as an Executive Engineer-RPD-10. The alleged irregularities
were imputed against the petitioner on the basis of inspection of the
quality control cell on 14th July, 1995 of the similar work as was
executed under the supervision of the petitioner and not the work
which was got executed by the petitioner. The misconduct against the
respondent in the charges was as followed:-
"While making payment in R/A bill Shri Om Prakash E.E. (Now S.E.) committed the following irregularity in respect of above mentioned work:-
Shri Om Prakash E.E.(Now S.E.) failed to take timely action for removal of efflorescence and rectification of defective plaster at the initial stage of the execution of the work as pointed by Q.C. Cell, DDA thereby putting Deptt. to a financial loss of Rs.5,42,647/-.
Shri Om Prakash E.E. (Now S.E.) by his above act failed to maintain devotion to duty and acted in a manner unbecoming of a Govt. servant thereby contravened Regulation 4 (1)(i) & (iii) of DDA Conduct, Disciplinary and Appeal Regulations, 1999 as made applicable to the employees of DDA."
The charges framed against the respondent were challenged by
him primarily on the ground that the whole basis of the alleged
irregularities was the general report prepared by the quality control cell
of the adjoining site and not pertaining to the site which was under the
respondent as an executive engineer.
The petitioner relied on an Inspection Note enclosed with letter
dated 28th may, 1995 from the executive engineer, quality control cell
addressed to the respondent categorically admitting that the defects
were noticed in a similar type of work at the adjoining site. The relevant
extract is as under:-
"As per the program, the inspection team inspected the site on 14.07.1995. During the discussion, at the site EE/RPD- 10 pointed that the work as completed on 5.1.95. Since the quality control inspections are to be conducted within six months from the date of completion, the work could not be inspected in detail. However, the defects notices in a similar type of work at the adjoining site are mentioned below, to take care of these defects and other defects before finalizing the bills."
The respondent also relied on the fact that on the date of
inspection i.e. 14th July, 1995, he was under orders of transfer from
that Division and he had handed over the charge on 18th July, 1995.
The respondent also contended that the memorandum regarding defects
was received in the Division after he was transferred and the petitioner
has failed to disclose as to what happened during intervening period
from 1995 till 15th November, 2006, when a letter was received from the
Chief Engineer, Rohini Zone. The respondent had challenged the
framing of charge against him on the ground that relevant documents
for framing the charge were not supplied to him and the fact that
houses were defectives in the quality was pointed out as the houses
were lying vacant for 8 years up to 2003 on account of non-availability
of water and electricity. The respondent had also raised the plea that
maintenance after completion of work in 1995 was not done by the
successor after handing over the charge of the Division in July 1995.
The Tribunal noted the un-explained delay from 1995 till 2006
and relied on various judgments. Taking into consideration the fact that
the basis of alleged defectives work was the inspection report by the
quality control cell which not based on inspection of the work which
was under the supervision of the respondent but was based only on the
assumption that if there had been defects in the adjoining work,
therefore, the work which was got executed by the petitioner must also
be defective, has quashed the charge memo against the respondent.
Learned counsel for the petitioner has very emphatically
contended that the charge against the respondent could not be quashed
and has relied on the decision of the Supreme Court in Civil Appeal
No.16353 of 2000, titled as „DDA v. I.J.Mongia‟, decided on 16th
February, 2001 holding that in case of quality of construction which is
alleged to sub standard, merely because the Delhi Development
Authority was negligent in proceedings against the delinquent officer,
could not be a ground for quashing or setting aside the disciplinary
action against the officer concerned. The Supreme Court had held that
in some cases delay in taking departmental proceedings may cause
serious prejudice to the delinquent officers and in appropriate cases the
Court may interfere but where sub standard houses are constructed,
material of the sub standard houses would always be available and it
would be open to the DDA to take action. The case of the respondent,
however, is a distinguishable as report of the quality control cell is not
based on the actual inspection of the houses which were under the
supervision of the respondent as an executive engineer/RPD-10 which
is admitted by the quality control cell in its letter dated 28th May, 1995.
It has been categorically admitted that the inspection was carried out of
the similar type of work at the adjoining site and not of the site which
was under the respondent. In the circumstances, it could not be held
even prima facie that work was defective and so therefore, charge
against the respondent that he failed to take timely action for
efflorescence and rectification of defectives plaster is not made out to
entail framing any charge of misconduct.
Learned counsel for the petitioner has also failed to give any
explanation that if the respondent was transferred from the Division on
14th July, 1995 and according to the averments of the respondent
which have not been denied by the petitioner that houses were lying
vacant for 8 years, and no maintenance work was carried out by the
successor of the respondent, even prima facie it cannot be inferred that
the respondent failed to take timely action for removal of efflorescence
and rectification of defectives plaster at the initial state of the execution
of the work. Since the inspection was not carried out, it could not be
held as to how the quality control cell could come to the conclusion that
the rectification of the defectives plaster at the initial state of the
execution of the work had not been done and it could be attributed to
the respondent. Ratio of the case of „DDA v. I.J.Mongia‟ is not applicable
to the present facts and circumstances of the case as the allegations of
sub standard work cannot be imputed to the respondent.
In the entirety of the facts and circumstances, the learned
counsel for the petitioner has failed to make out any such illegality,
irregularity or perversity in the order of the Tribunal, which would
require any interference by this Court in exercise of its jurisdiction
under Article 226 of the Constitution of India. The writ petition in the
facts and circumstances of the case, is without any merit, and it is
therefore, dismissed.
ANIL KUMAR, J.
MAY 24, 2010 MOOL CHAND GARG, J. „VK‟
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!