Citation : 2010 Latest Caselaw 1677 Del
Judgement Date : 25 March, 2010
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P. No.327/2003
Date of decision : March 25, 2010
SH. BHARAT LAL ... Petitioner.
Through: Mr. Sanjay Bansal, Advocates
VERSUS
MUNICIPAL CORPORATION OF DELHI & ORS ....Respondents
Through: Ms. Mansi Gupta, Advocate
Sh. Kanan,Executive Engineer
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be allowed to see the judgment?
2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in the Digest?
% JUDGMENT(ORAL)
VALMIKI J. MEHTA, J
1. In this petition under Section 34 of the Arbitration and Conciliation Act,
1996,the petitioner challenges the Award only as regards Claim Nos. 5 and 7.
2. Claim No. 5 was the claim for enhancement of cost of labour and material
under Clause 10CC of the contract. It is an undisputed fact that the stipulated date
OMP-327-2003 Page 1 of completion was 19.5.1993 but the actual date of completion was 24.6.1996.
There is therefore an admitted delay which was caused in the completion of the
work. The Arbitrator while dealing with this claim, on the one hand gives a finding
that the petitioner did not produce any document to show that the competent
authority has granted extension without levy of compensation, but in the same
breath, he has given a finding that the respondent did not levy any
compensation/liquidated damages under Clause 2 of the
Agreement. These are clearly mutually inconsistent findings. Once the Arbitrator
has found as a fact that no compensation/liquidated damages were imposed by the
respondent under Clause 2 of the Agreement, the petitioner consequentially is not
guilty of delay in the performance of the work. If the petitioner was guilty of delay
in the performance of his obligations, then, the respondent would definitely have
imposed liquidated damages and which it has not. Consequentially, therefore, the
petitioner is entitled to payment of higher cost which it had incurred for material
and labour under Clause 10 CC. The Award with respect to Claim 5 is therefore
set aside and the matter is remanded back to the Arbitrator for a fresh decision on
this claim in accordance with law. In case, the Arbitrator holds that the petitioner
is not guilty of delay inter-alia because no liquidated damages have been imposed
by the respondent, then in such circumstances, the Arbitrator will consider the
awarding of an amount under Clause 10CC to the petitioner.
OMP-327-2003 Page 2
3. Claim No. 7 is also related to Claim No.5 in that, this Claim No 7. was
towards expenses incurred in the extended period towards maintaining
establishment like Engineer, Head Mistri, Supervisor, Chaukidars, Vibrator etc.
This claim has also been denied by the Arbitrator by holding that the claimant
failed to produce documentary proof to show that the respondent is guilty for all
the delays and that competent authority has not granted extension without levy of
compensation. As already discussed under Claim No.5, the competent authority
has in fact not levied any compensation under Clause 2, and which would have
been the case, if, the petitioner was guilty of delay. Accordingly this claim is also
remanded back to the Arbitrator for a fresh decision in accordance with law on the
same basis as Claim No. 5.
In case, the Arbitrator holds the petitioner entitled to the Claims 5 and 7,
then the Arbitrator will also consider the prayer of the petitioner for grant of
interest on this claim in accordance with law.
4. With the aforesaid observations, the Award to the extent of Claim
Nos. 5 and 7 is set aside and sustained so far as the other claims as adjudicated.
The records of the case which are presently in this court be sent back by special
messenger to the Arbitrator to pass a fresh Award in accordance with law with
OMP-327-2003 Page 3 respect to Claim Nos. 5 and 7. The petition stands disposed of. Parties are left to
bear their own costs.
VALMIKI J. MEHTA, J
March 25, 2010
ib
OMP-327-2003 Page 4
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!