Citation : 2010 Latest Caselaw 1500 Del
Judgement Date : 17 March, 2010
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS(OS)No. 228/2003
17th March, 2010
MUNICIPAL CORPORATION OF DELHI ... Petitioner
Through: Mr. Aaditya Vijay Kumar and Mr. Gaurang
Kanth, Advocates
VERSUS
M/S PRABHAT CONSTRUCTION & ANR ....Respondents
Through: Mr. Raman Kapur, Advocate CORAM: HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be allowed to see the judgment?
2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in the Digest?
% JUDGMENT (ORAL) VALMIKI J. MEHTA, J I.A.7/2007 in CS(OS) No. 228/2003
1. By these objections under Sections 30 and 33 of the Arbitration Act, 1940,
the respondent/applicant challenges the impugned Award dated 29.10.2002 passed CS(OS) 228/2003 Page 1 by the sole Arbitrator. The disputes arose between the parties with respect to
construction of 88 Nos. Type A Staff Quarters at Seelampur Housing Complex
Part-III, Delhi and which was the subject matter of the Agreement dated 6.7.1988.
2. The counsel for the objector has very fairly argued his objections only with
respect to Claim Nos.1 and 3 as dealt with by the Award.
3. Claim No.1 is in effect a declaratory Award with respect to entitlement of
the MCD/non-applicant/petitioner to withhold amounts on account of the claim of
liquidated damages under Clause 2 of the Agreement. The counsel for the
applicant contends that by virtue of Clause 2 read with Clause 25, this was an
excepted matter and consequently, on such excepted matter no Award could have
been passed by the Arbitrator. Before proceeding ahead I must clarify that what I
mean by a declaratory Award, is that the monies are already with the
petitioner/non-applicant and the Award, in fact only in effect justifies the action of
the petitioner and not that by the Award, there is a decree for recovery of this
amount against the applicant/objector. Mr. Kapur has relied upon a Division
Bench judgment of this court reported as Delhi Development Authority Vs. M/s
Sudhir Brothers, 1995 (2) Arb. LR 306 to contend that since the issue was an
excepted matter, the Arbitrator could not have decided the same. I agree that since
similar clauses were in issue in the case of Sudhir Brothers (supra), and thus the
Arbitrator could not have pronounced upon the merits of the imposition of the
CS(OS) 228/2003 Page 2 liquidated damages under Clause 2 inasmuch as this is an excepted matter by
virtue of Clauses 2 and 25 of the Contract. The Award to this extent is set aside.
However, I make it clear that this should not be construed as a direction to the
petitioner to refund and pay the amount(if any) as appropriated by it under Clauses
2 and 25, and, if the objector seeks to recover such amount, the objector will be
entitled to file such proceedings in accordance with law as available to it.
4. Claim No.3 dealt with by the Award pertains to the claim of the objector for
recovery of the amount of Rs.1,39,000/- which has been withheld by the petitioner
on account of various defects which had cropped up in the work. The defects in
this case are as pointed out in Annexure-F to the written statement of the petitioner
filed before the Arbitrator. A reference to the aforesaid Annexure-F shows that
the cost which was incurred was partly towards rectifying the defective work and
partly towards completion of certain work left incomplete by the objector. Since
the non-objector already had Rs.1,00,000/- with it, the Award has held the non-
objector entitle to the balance amount of Rs.39,000/-.
Mr. Kapur on behalf of the objector contended that there was absolutely no
proof which was filed by the petitioner in the arbitration proceedings and
consequently, the Arbitrator was not justified in awarding this amount. Before I
refer to Annexure-F, I may only state that the strict rules of the Evidence Act,
CS(OS) 228/2003 Page 3 1872 do not apply to arbitration by virtue of Section 19 of the Arbitration &
Conciliation Act, 1996 . What the Arbitrator has to see is that whether reasonable
material was available before him so that a legal conclusion can be arrived at.
Viewed in this regard, when we see the contents of Annexure-F, it becomes clear
that the contents are basically towards labour charges and a labour rate is given.
Labour rate is a fixed rate or statutory rate for which only routine statement is
enough. Further, another item as found in Annexure-F is cement and the rate of
cement has been taken. I may note that cement was one of the items which was
supplied by the petitioner to the objector for performance in the contract at a
particular rate and thus the rate of cement is also such a thing for which no
additional proof is required. Similarly, other items have been given by a specific
rate. In my opinion, the expenses incurred for rectification of the defective and
incomplete work is enough evidence, in the facts of this particular case, because of
the nature of the expenditure being such, the Arbitrator was entitled to consider
the evidence in the form of rates which was filed before him. In my opinion,
therefore, there is no merit in objection with regard to Claim No.3.
5. As already stated by me above, Mr. Kapur, on instructions from of Mr.
Arvind Grover the partner of the respondent firm, does not press any other
objection. With these observations, the application stands disposed of . The
CS(OS) 228/2003 Page 4 Award is made rule of the Court. Let a decree be drawn in terms of the Award
subject to the modification as given qua Claim No.1.
VALMIKI J. MEHTA, J
March 17, 2010
ib
CS(OS) 228/2003 Page 5
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!