Citation : 2010 Latest Caselaw 1499 Del
Judgement Date : 17 March, 2010
UNREPORTABLE
* IN THE HIGH COURT OF DELHI AT NEW DELHI
FAO No.60/2010
Date of Decision: March 17, 2010
NATIONAL HIGHWAYS AUTHORITY OF INDIA ..... Appellant
Through Mr. Rajiv Kapoor, Advocate
versus
BRIDGE & ROOF CO INDIA LTD ..... Respondent
Through Mr. P.C.Markanda, Senior Advocate
with Mr. Rajesh Markanda, Advocate
CORAM:
HON'BLE MISS JUSTICE REKHA SHARMA
1. Whether the reporters of local papers may be allowed to see the
judgment? No
2. To be referred to the reporter or not? No
3. Whether the judgment should be reported in the 'Digest'? No
REKHA SHARMA, J. (ORAL)
The appellant and the respondent are Government
Undertakings. Both belong to the same clan and yet are locked in
litigation with each other. Initially, the disputes between them were
referred to the Disputes Review Board (hereinafter referred to as
the DRB). The DRB in its order dated December 24, 2008 has held
that the termination of the contract by the appellant with the
respondent was not in order. It has also held that there was no valid
contract between the two after May 21, 2008 and, therefore, the claim
put up by the respondent for the period beyond May 21, 2008 was not
tenable. It appears that the respondent was not satisfied with the
latter part of the finding of the DRB and, therefore, it invoked the
arbitration clause resulting in the constitution of the Arbitral Tribunal.
One of the disputes which has been raised before the Arbitral
Tribunal, is whether consequent to the termination of the contract by
the appellant, the respondent was entitled to release of its plant,
machinery and equipment. The respondent moved an application
before the Arbitral Tribunal under Section 17 of the Arbitration and
Conciliation Act, 1996 praying for an interim order for the release of
its plant, machinery and equipment held by the appellant. The
Arbitral Tribunal by its order dated May 14, 2009 directed the
appellant to release the same subject to the respondent furnishing an
additional Bank Guarantee of Rs.18 crores. However, by a
subsequent order dated November 13, 2009 the Arbitral Tribunal has
varied its earlier order dated May 14, 2009, in as much as it has
directed the appellant to release the plant, machinery and equipment
without furnishing the bank guarantee of Rs.18 crores. The revised
order has been passed on account of the fact that the appellant is
already having adequate security in the form of Bank Guarantee of
Rs.35 crores from the respondent.
It is submitted by learned counsel for the appellant that the
Arbitral Tribunal could not have passed any order with regard to the
release of plant, machinery and equipment, as it has yet to decide
whether the disputes raised by the respondent are at all arbitral.
According to the counsel, the decision of the DRB had attained finality
and, therefore, the respondent could not have invoked the arbitration
clause.
The question whether the finding of the DRB had attained
finality and in view thereof, the Arbitral Tribunal has no jurisdiction to
adjudicate upon the disputes raised by the respondent, is a matter
which falls within the domain of the Tribunal. The Tribunal itself has
said in the impugned order that it will deal with the said aspect of the
matter at an appropriate stage. In so far as the order of the Tribunal
directing the appellant to release the plant, machinery and equipment
is concerned, it seems to have been passed keeping in view the fact
that the appellant till date has not raised any counter-claim against
the respondent and that a Bank Guarantee of Rs.35 crores furnished
by the respondent is already lying with the appellant. I find no
infirmity in the order so passed by the Arbitral Tribunal. There is no
merit in the appeal. The same is dismissed.
REKHA SHARMA, J.
MARCH 17, 2010 ka
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!