Citation : 2010 Latest Caselaw 1327 Del
Judgement Date : 10 March, 2010
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP No. 280/2003
10th March, 2010
M/S GAIL (INDIA) LTD. ...Petitioner
Through: Mr. Rajiv Bansal, Advocate
VERSUS
BELL CERAMICS PVT. LTD & ORS ....Respondents
Through: None CORAM: HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be allowed to see the judgment?
2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in the Digest?
% JUDGMENT (ORAL) VALMIKI J.MEHTA, J
1. This petition under Section 34 of the Arbitration and Conciliation Act,
1996 challenges the Award dated 17.2.2003 passed by the sole Arbitrator.
The dispute is between the petitioner as the supplier of Gas and the
respondent as the consumer. The dispute pertained to the entitlement of
transportation charges by the petitioner and against the respondent for the
supply of the Gas.
OMP 280/2003 Page 1
2. The facts of the case are that since the respondent had laid down its
own pipeline for receiving gas, the present petitioner was not charging the
usual transportation charges from the respondent/consumer. There were a
total of five Agreements between the petitioner and the respondent and
which are dated 28.4.1993, 24.8.1993, 24.5.1994, 11.6.1996 and 10.2.1999.
By the first four Agreements, the respondent increased the demand/
consumption of Gas, and consequently, the consumption went up from 4000
CUM per day to 28,000 CUM with the result that the transportation charges
also slab wise increased from Rs.26,650/- per month to Rs.2,03,837/- per
month. By the 5th agreement, the consumption of Gas was however
decreased from 28,000 CUM per day to 21,000 CUM per day and the
transportation charges were also accordingly brought down to Rs.49,896/-
per month i.e., the same charges as payable vide Agreement dated 24.5.1994
when it was agreed to supply 21,000 CUM per day. Here it may be noted
that higher transportation charges are required for greater quantities because
in such case there is higher cost to petitioner for maintaining higher pressure
for transportation at different points in the pipeline.
3. The respondent however, resorted to over drawl of Gas, than as fixed
under the Agreement dated 10.2.1999. This fact is an undisputed and
admitted in the arbitration proceedings. The issue which therefore arose was
whether the respondent is liable to pay transportation charges for over
drawing in excess of 25,000 CUM per day or is it merely liable to pay
OMP 280/2003 Page 2 transportation charges at the contractual rate of Rs.49,896/- per month for
only at the contractual quantity of 21,000 CUM per day.
4. The Arbitrator by the impugned Award has allowed additional
transportation charges from 1st March, 1999 to 31st December, 1999 i.e. a
period of 10 months totalling to Rs. 5,08,330.20. This would come to only
Rs.58,330/- per month, although the contractual rate for 28000 M3 per day
was Rs.2,03,837/- per month.
5. In my opinion, the Award is absolutely illegal and perverse. Once
there is a breach of contract by the respondent in over drawing Gas, the
respondent was bound to compensate the petitioner in proportion to the cost
of transportation of higher quantities of Gas. In any case, under Section 70
of the Contract Act, 1872 a person who receives the benefit of a non-
gratuitous act has also to compensate the person on from whom the benefit
has been received. Transportation charges therefore have to be paid by the
respondent to the petitioner in terms of the actual drawl of Gas in excess of
25000 M3 and not the transportation charges for the lesser contracted
quantity of 21,000 M3. The transportation charges cannot be for the
contracted quantity because the contracted quantity is 21,000 CUM per day
whereas the actual drawl is admittedly in excess of 25,000 CUM per day.
No doubt, the Arbitrator is not bound by the strict rules of the Evidence Act,
1872 as per Section 19 of Arbitration and Conciliation Act, however, it is
not permissible for the Arbitrator to act wholly irrationally and
OMP 280/2003 Page 3 unreasonably. As already stated if we divide the figure of Rs.5,08,033/- by
a figure of 10, inasmuch as the aforesaid payment of 5,08,033/- has been
awarded for 10 months, the monthly charges will come to only Rs.50,833/-
per month. The evidence to determine the amount payable for transportation
of Gas in the slab of 21000 M3 to 28000 M3 was however available to the
Arbitrator and the Arbitrator is not permitted to ignore the admitted facts so
as to arrive at a totally arbitrary figure. The evidence is the Agreement
dated 11.6.1996, which shows that when the supply of Gas was 28,000
CUM per day, then transportation charges were fixed at Rs.2,03,837/- per
month. A reference to the earlier Agreements also show that the payment
for transportation for Gas is slab wise and there is a geometrical progression
of increase of transportation charges and it is not an arithmetical
progression. The slab of supply for transportation is the same between
21,000 M3 to 28,000 M3 per day. We therefore have to take the figure of
Rs.2,03,837 (payable under Agreement dated 11.6.1996) because charges
for supply of 25,000 CUM per day would come to the figure of charges
payable for the slab of supply of gas between 21,000 CUM per day to
28,000 CUM per day. Since the admitted evidence in the form of the
Supplementary Agreement dated 11.6.1996 was before the Arbitrator, the
transportation charges should have been atleast Rs.2,03,837 per month
considering that those were the charges in 1996 and the disputed period in
the present case is from March, 1999 to December 1999 and which evidence
OMP 280/2003 Page 4 has been illegally ignored by the Arbitrator making the Award perverse
which shocks the judicial conscience. Accordingly, I hold that instead of
Rs.50,08,33/- per month as awarded by the Arbitrator, the petitioner was
entitled to charges of Rs.2,03,837/- per month.
6. The counsel for the petitioner had also sought to contend that the
Arbitrator and the Directors of the respondent were common directors in a
company known as Asian Hotels Ltd., however, in view of my findings
above, I need not go into this aspect because nothing will turn upon the
same.
7. Under Section 34 of the Arbitration and Conciliation Act, 1996, once
the Award is perverse and against the provisions of the law of the land, a
court is entitled to, and in fact duty bound to interfere with the Award. In
this regard the following judgments are relevant which are as under:-
In ONGC Vs. Garware Shipping Corporation Ltd., 2007 (13) SCC
434 the Supreme Court has laid down in paragraph 30 of the judgment that
there is no such provision that Courts have to be slow in interfering with the
Arbitrator's Award even if the conclusions are perverse and the very basis of
the Award is wrong. In Security Printing & Minting Corporation of India
Ltd. and Anr. Vs. Gandhi Industrial Corporation, 2007 (13) SCC 236 in
paragraph 16 it has been held by the Supreme Court that even though the
courts are slow in interfering with the Award it does not mean that if the
Award is perverse the Courts are powerless to interfere in the matter.
OMP 280/2003 Page 5 In the present case, the Award is wholly violative of the provisions of
Sections 70 and 73 of the Contract Act, 1872 because it ignores the admitted
breach. The Award is wholly perverse which shocks the judicial conscience
because the Arbitrator has ignored the evidence in the form of the admitted
Supplementary Agreement showing a slab for payment from 21,000 to
28,000 CUM per day at Rs.2,03,837 per month. The present is therefore a
fit case for interfering and setting aside the Award.
8. Accordingly, objections to the impugned Award dated 17.2.2003 are
accepted and it is held that the petitioner herein is entitled to the
transportation charges from 1.3.1999 to 31.12.1999 at the rate of
Rs.2,03,837/- per month. With the aforesaid observations, the objection
petition is allowed to the extent as stated above. Since the respondent has
not appeared, the petition is disposed of leaving the parties to bear their own
costs.
VALMIKI J.MEHTA, J
March 10, 2010
ib
OMP 280/2003 Page 6
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!