Citation : 2010 Latest Caselaw 1250 Del
Judgement Date : 5 March, 2010
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P. No.44/2010
5th March, 2010
UNION OF INDIA ...Petitioner
Through: Mr. Jagjit Singh, Advocate.
VERSUS
M/s. CHENAB CONSTRUCTION JOINT VENTURE ....Respondent
Through: Mr. Navin Chawla and Mr. Amit
Gupta, Advocates.
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be allowed to see the judgment?
2. To be referred to the Reporter or not? Yes
3. Whether the judgment should be reported in the Digest? Yes
% JUDGMENT (ORAL)
VALMIKI J.MEHTA, J
1. This petition under Section 34 of the Arbitration &
Conciliation Act, 1996 challenges the Award of the three member Arbitral
Tribunal comprising of the Chief Engineer of the Northern Railway, FA &
CAO (Traffic) Northern Railway and the Group General Manager of the
Delhi Metro Railway Corporation(Presiding Arbitrator), an officer who is
said to be on deputation from the Railways to the DMRC.
OMP 44/2010 Page 1
2. The counsel for the petitioner has only pressed his objections
with regard to Claim Nos.6, 9,10, 26 and 8, additional Claim No.1,
additional Claim No.6 and the award of interest as adjudicated in the Award.
3. The scope for hearing of a petition under Section 34 is now
well settled. A court would interfere with the Award only if the same is
illegal or violative of the contractual provisions or the findings are so
perverse that it shocks the judicial conscience. Keeping in view the
aforesaid parameters, I have examined the contentions as raised by the
counsel for the petitioner.
4. Claim No. 6 was the claim of the respondent/claimant for
expenses incurred for digging foundation below prescribed level as shown in
the tender document. The Arbitrators have found as a matter of fact that
there was a deviation of the work and the contractor has in fact executed
work beyond the specified quantities of the contract. The Arbitrators,
therefore, came to a finding that though 66 metres were measured and
recorded as the work done, payment was only made for part quantity of 30
metres. Claim No. 6 has accordingly been allowed by the Arbitrators for
payment for the work done up to 66 metres. The conclusions of the
Arbitrators are contained in the following paragraph and with which I agree.
"The Claimants referred page 4 of agreement and argued that there is provision in the contract that in case digging of foundation was less, recovery would accordingly be made and if it is more, additional quantity shall be paid at agreement rates. In the course of execution, foundation were got dug deeper than specified depth as such Respondents recorded measurements but have not paid full quantity of 66 meters as measured
OMP 44/2010 Page 2 and recorded by them. In running bill, Respondents released payment for part Quantity of 30 meters instead of 66 meters as actually executed by Claimants at site. On verification of records of Respondents, such as designs, measurements recorded by them and other relevant records, it was seen by Arbitration Tribunal that the Respondents had measured 52.136 meters in piers and 0.637 meters in abutment, and had released in running bill quantity of 28.876 meters in piers and 0.509 meters in abutments, hence payment for balance quantity of 52.136-28.976= 23.160 meters in piers and quantity of 0.637-0.509= balance 0.128 meters in abutment @ agreement rates i.e. Rs.60,000/- per m for piers and Rs.80,000/- per meter for abutment i.e.23.16x60000=Rs.13,89,600and 0.128 x 80000=Rs.10240=Rs.13,99,840/- is awarded to the Claimants."
5. Claim No. 9 was the claim of the respondent herein for
payment of compaction of earth filling carried out under Item No.8. The
Arbitrators have recorded a finding of fact that there was an agreed rate
between the parties of Rs.8.08 per m3. In spite of the Agreement, the
petitioner sought to unilaterally revise and reduce this rate to Rs.5.40 per m3
and which has therefore not been accepted by the Arbitrators. This finding
of the Arbitrators is therefore clearly justified because once there is an
agreed rate, there cannot be unilateral alteration of the same to the detriment
of the other party.
6. Claim No.10 was the claim of the respondent for expenses
incurred for providing/fixing and installing bridge bearings with complete
accessories. Under this claim, the Arbitrators have noted that though under
the tender document, either of the two bearings viz. Elastomeric Neoprene
Bearings or POT/PTFE bearings, could have been supplied by the
contractor. The contractor therefore submitted his tender with respect to
supply of Neoprene Bearings and accordingly priced his tender. The OMP 44/2010 Page 3 petitioner after accepting the tender unilaterally required, the respondent to
put, not Neoprene Bearings but POT/PTFE bearings. Since this would be an
amendment to the contract and since the POT/PTFE bearings were of a
higher cost instead of the tendered Neoprene bearings, the Arbitrators have
granted the claim for the higher cost of POT/PTEE bearings. No fault
therefore can also be found with respect to this finding and conclusion of the
Arbitration Tribunal.
7. Claim No. 26 and 8 have been dealt with by the Arbitral
Tribunal together because they pertained to the issue of price variation. The
Arbitrators have exhaustively and faithfully recorded the respective
submissions of the parties and after discussing the matter have given their
conclusions for awarding the amount. Since the Arbitration Tribunal has
with clarity recorded the submissions, findings and the conclusions, it would
be appropriate if I simply reproduce the same and which read as under:
" The Arbitration Tribunal has considered and examined various contentions, written submissions, record etc. as filed and relied upon by parties. The crux of Respondents arguments is that there was slow progress on part of Claimants, as such extension was granted upto 7.08.1999 with PVC, and thereafter extensions were sanctioned without levy of penalty/Liquidated Damages and without benefit of Price Variation Clause.
The averments of claimants such as non availability of land, which remained under occupation of security personal, non availability of land for casting yards, changes in GADS, changes in design of pier, delays in approval of design and drawing by Proof Consultants and the Department, delay in construction of catch water drains, delays due to diversion of National Highway, delays in power connections delays due to shortage in Departmental Supplies, delays in payments, wrong encashment of BGs, delays due to rains, strikes and Law and Order situation in J&K., non finalization of NS items etc. and Respondents replies to Claimants and instructions to increase progress etc. have been examined. The Arbitration Tribunal has carefully considered the merits and demerits including
OMP 44/2010 Page 4 conditions of contract, documents records etc. It is also seen that the work which was slated for completion on 07.02.1998 finally was completed on 31.07.2004 i.e. with additional period of 77 months, part of which was extended by Respondent with grant of escalation and rest of period without penalty, without escalation, though tenders for additional pier P1 were finally decided by Respondent on 25.04.2003, the Respondents could not throw light on the aspect of calling tenders in April, 2003 for this additional pier when in the meeting held on 19.8.1996 the respondents were aware that additional pier had to be provided and till it was completed claimants work of viaduct E-18, would have remained incomplete. The respondent, got additional Pier- I satisfactorily completed on 15.06.2004 which proves that Claimants contractual date for items to be completed after completion of additional pier had to be reasonably and proportionately extended. The balance items executed by Claimants after 15.06.2004 needed some time and Arbitration Tribunal finds that further time taken by claimants to finally complete work of viaduct E-18 by 31.07.2004, was not unreasonable. The Respondents admitted that no loss has been suffered by them and while extending completion date of additional Pier I upto 15.06.2004, no penalty/compensation was levied or recovered. It was also admitted by Respondents that line was opened after March, 2005. The respondents have also issued a certificate of satisfactory completion of work in favour of the Claimants.
The Arbitration Tribunal holds that Respondents were justified to make changes and/or revise scope of work as required and needed but in case of changing scope of work or adding certain items, reasonable extension of time has to be given to the contractor to complete balance items to treat the work complete so that payments is normal course such as security deposit, earnest money final bill etc. were released and paid, which remain blocked, unless work is certified to have been completed. The initial time of completion was very unrealistic and considerable period was consumed in making changes and approval of design. Due to various changes and unforeseen circumstances beyond reasonable control of Claimants the completion period was got extended. This upset the working cycle and rhythm of contractor and upset cash flows so very essential for expediting completion. The cash flows further get adversely affected if contractor is not compensated for escalating in prices and a vicious cycle begins.
The Arbitration Tribunal has gone into merits and demerits and is of the view that there was no undue delay on the part of the Claimants in completing remaining work by 31.07.2004. Even the Respondents have been granting extension to period of completion without any penalty and without any liquidated damages.
The Respondents have paid some escalation of amount to claimant up to 31-08-1998 and not up to 07.08.1999 and continued to pay escalation on the balance executed work on the last indices of 31.08.1998 till completion of work, withholding application of further price indices from 01.09.1998 till completion of work. The Arbitration Tribunal has also taken note of this fact that instead of 24 months work continued up to 101 months and extra period was regularized by Respondents without penalty.
OMP 44/2010 Page 5 The Respondents were asked to work out, amount of escalation till 31.07.2004 and the same has been worked out and have filed through their advocate before Arbitration Tribunal duly authenticated and signed by Dy.C.E/C/JAT having examined all aspects, worked out the escalation amount payable i.e. Rs.3,36,89,983.96. The RBI indices had to be treated as frozen till the date of completion i.e. 31st July 2004 as final for considering and calculating the CC-57 and FCC-58 figures have to be arrived at Rs.43,75,374.31 which when added to earlier PVC paid till CC- 56 i.e. Rs.2,85,91,951.27 coming to total amounting to Rs.3,29,67,325.58. The Respondents had paid in running bills Rs.1,31,52,606.01 on account of Price escalation till date of completion based on indices of 31.8.1998 and on star price items Rs.25,58,128,29 i.e. Rs.1,57,10,744.29 P to the Claimants. The Respondents paid the price escalation upto last bill on account of Price escalation on indices of 31.8.1998 and full escalation w.r.t. star price amounting to Rs.25,58,128.29 upto date of completion notwithstanding extensions granting without benefit of Price Variation Clause. No liquidated damages were charged and certificate of successful and satisfactory completion issued at end of work. An amount of Rs.1,31,52,606.01 on account of Price escalation has already been paid to the claimants as such Rs.32967325.58 -Rs.13152606.01= Rs.1,98,14,719.57 is awarded towards balance Price Variation Clause. The Arbitration Tribunal holds that the Claimants claim of escalation is justified and award to the claimants escalation amount of Rs.1,98,14,719.57."
The aforesaid conclusion clearly shows that the contract was extended
for an abnormal period of time. Not only was the contract extended for an
additional period of 77 months, the fact of the matter was also that because
of non-construction of an additional pier P1 which was not in the scope of
the work of the respondent, but which the petitioner had got constructed
through another contractor, the work in question got delayed. Further the
Arbitrators have noted that there was default on the part of the petitioner in
not only originally having an unrealistic time period but considerable time
was consumed in making changes and approval of design and there was
further delay due to various changes and unforeseen circumstances beyond
reasonable control of the claimant. It is further noted that the cash
OMP 44/2010 Page 6 flow got affected because the respondent was not compensated for the
escalation payment. Another finding of fact is that the extension which has
been granted to the respondent for completion of the contract was an
extension without levy of liquidated damages. Once there is no levy of
liquidated damages, it is quite clear that the extension is not on account of
any fault of the contractor. I, therefore, do not find any fault whatsoever
with the aforesaid awarding of the claim to the respondent by the Arbitration
Tribunal.
8. The counsel for the petitioner however contended that this
claim of price variation was an „excepted‟ matter. Firstly, I do not find that
this issue appears to have been argued before the Arbitration Tribunal. In an
Award which is detailed and exhaustive, containing faithfully the respective
submissions of the parties, I do not think that the Arbitrators would not have
decided this issue if it was argued before them. It is therefore, doubtful that
whether this issue, of this claim being an excepted matter, was at all argued
before the Arbitration Tribunal. Further, this issue of price variation claim
being an excepted matter, if it was so, was indeed an issue going to the root
of the matter and if, it was argued but not decided by the Arbitrators, then,
surely the petitioner would have approached the Arbitration Tribunal under
Section 33 of the Act and the Arbitration Tribunal would then have observed
whether this issue of price variation claim being an excepted matter was
argued or not argued. Since no such application has been filed under Section
OMP 44/2010 Page 7 33, and which the petitioner ought to have filed, if in its opinion such a basic
and vital matter was not addressed before the Arbitration Tribunal in the
Award, I feel that this issue in fact would not have been argued before the
Arbitration Tribunal.
In any case, this issue cannot be said to be an excepted matter
because a specific reference of this dispute was made to the Arbitration
Tribunal by the petitioner itself vide the letter of the referring authority
dated 5.12.2007, copy of which letter has been given by the counsel for the
respondent to this court. The counsel for the respondent has also pointed out
that subsequently on 31.07.2008, on an additional representation being made
by the respondent with regard to certain matters, the petitioner did not refer
those disputes to Arbitration because the competent authority of the
petitioner found the said matters to be excepted matters. It was therefore
urged, and in my opinion rightly, by the counsel for the respondent that if
the matter was an excepted matter, the same would not have been referred at
all to Arbitration. This reaffirms my above finding that this issue of the
price variation claim being an excepted matter would not have in fact been
argued before the Arbitrators.
9. Another argument with respect to the price variation claim was
that the price variation claims, if at all, the same were to be awarded ought
to have been restricted to an increase of 15% only by virtue of Clauses 32.3
and 32.4 of the Contract which read as under:-
OMP 44/2010 Page 8
"32.3 Total amount of reimbursement/recovery due to variation in
prices of the several components shall be limited to 15% (i.e. 20%-5% floor price) of the amount finally payable to the contractor excluding (a) cost of cement, steel and other items, supplied by the Railway to the contractor at a fixed price, and (b) specific consultancy charges as per accepted offer. 32.4 Price variation during extended period of contract.
The price adjustment as worked out above i.e. either increase or decrease will be applicable upto the stipulated date of completion and for all extensions of time granted to the stipulated date of completion of work except etension‟s) granted under 17(4) of N. Rly. General conditions of contract-1989. The aforesaid ceiling of 15% will however be applicable whatever may be the actual period of execution of the contract."
At the first blush, this argument may appear to be attractive, however,
there are three things which stand in the way of the petitioner. Firstly, a
reference to the response filed by the petitioner in the arbitration
proceedings show that except a general reference to Clause 32, no reference
has at all been made to the price variation aspect to be limited to 15% only.
Secondly, in fact, there appears to be a valid reason for the petitioner not to
have raised this issue of limit of price variation claims within 15% only,
because, the counsel for the respondent has drawn my attention to a Minutes
of Meeting dated 16.11.1999 in which, in para 2, it is clearly stated that the
respondent was not agreeable to work in the extended period of time unless
price variation claims were granted. In this Minutes of Meeting, it is clearly
recorded that this issue therefore, with respect to price variation claims, will
be reviewed by the Railways. The counsel for the respondent has in my
opinion rightly relied upon Asian Techs Ltd. Vs. Union of India and Others
2009 (10) SCC 354, paragraphs 17 and 21, as per which once a contractor
acts on a representation and does work, it is not permissible for the
OMP 44/2010 Page 9 owner/employer to refuse and deny the valid claims and entitlement of the
contractor. In the face of this understanding, I do not find any basis as to
why price variation claims should be restricted only to 15% and not the
actual price escalation as has been incurred by the contractor. Surely and
lastly, I must state that the contractual clauses which hold that petitioner,
even if found guilty of breach of contract in causing delays, yet it should not
pay actual damages of price variation, under either Section 55 or Section 73
of the Contract Act, 1872 are clearly illegal and void. In a recent judgment
in CS(OS) No.614-A/2002 titled as M/s. Simplex Concrete Piles (India)
Ltd. Vs. Union of India dated 23.2.2010, I have held that Clauses in a
contract which disentitle an aggrieved party from claiming actual damages
suffered by it, either under Section 55 or Section73, such contractual clauses
are void by virtue of Section 23 of the Contract Act.
Accordingly, for all the aforesaid reasons, I do not find any
valid basis to accept the arguments and contentions as raised by the counsel
for the petitioner that Claim Nos. 26 and 8 pertaining to price variation have
been wrongly allowed.
10. So far as additional Claim No.1 is concerned, this was a claim
made by the respondent seeking refund of recoveries made by the petitioner
for 20 ladders which were constructed by the respondent in terms of the
contract. It is a fact that the contract being a lump sum contract, did in fact
make a provision for providing of ladders. The respondent therefore
OMP 44/2010 Page 10 provided the ladders and claimed payment under the lump sum amount only
(and not any additional cost) for the 20 ladders. So far as the balance 19
ladders were concerned, since such ladders were not constructed, no
payment has been made to the respondent under the Contract. Therefore,
the Arbitrators have awarded this claim for installation of 20 ladders because
they were very much within the scope of the work for which respondent was
entitled to get payment. I do not find anything illegal in a person getting
payment for the work done within the scope of the Contract. There is
therefore no illegality or perversity with respect to this finding. The relevant
portion of the Award which deals with this aspect, and which I adopt, runs
as under:-
" The Respondents argued that inspection ladders inside piers were to be provided as per Clause 4.8.18 which were later on decided not to be provided as not required. Hence deduction for ladders has rightly been made from lump sum/value of contract, as amount for providing ladder was included in lump sum cost, whereas Claimants are claiming additional payment for providing 20 ladders and arranging materials etc. for remaining 19 ladders at site. The Respondents have recovered Rs.7,96,000/- from payment due to Claimants for not providing ladders though 20 ladders had been provided at site in different piers.
Clause 4.8.16 lays down that hollow piers after construction if provided shall be filled with concrete 1:4:8 up to H.F.L. The via-duct bridge was constructed not over an active river but it was local ground with depression & not subjected to floods, hence even technically filling with 1:4:8 concrete was not required. Ladders or other means are required to visually check and inspect constructed piers from time to time to carry out normal maintenance works. It was not disputed that even on date, the constructed piers could be easily and visually checked. Clause 4.8.18 lays down that ladders for inspection of galleries, inspection of platforms etc. shall be provided. The recovery as made by Respondents is not justified and it is refunded to Claimants. The claimants claim for arranging materials for remaining piers is rejected."
OMP 44/2010 Page 11
11. Additional Claim No.6 was the claim of reimbursement of risk
and cost pertaining to another contract entered into between the parties. The
Arbitrator notes that admittedly, the amount of Rs.23,08,599/- was payable
to the respondent under this contract, and therefore there could not be any
recovery of this amount by means of an order passed under this contract. It
is not the case of the petitioner that any order for withholding the amount
has been passed in another contract where in fact risk purchase action has
been taken. I therefore do not find any fault therefore with this finding of
the Arbitration Tribunal because it is always open to the petitioner to
withhold amounts by passing recovery and withholding order in the other
contract, which has not been so done. Objection to this claim is therefore
dismissed.
12. The last issue which was urged before this court was that the
Arbitrators have erred in awarding interest against the contractual
provisions. The counsel for the petitioner has for this purpose relied upon a
recent Supreme Court judgment reported as Sayeed Ahmed & Co.Vs. State
of U.P. & Ors. 2009 (3) Arb. LR. 29. The relevant clause of the contract
before the Supreme Court in Sayeed Ahmed's case reads as under:
"No claim for interest or damages will be entertained by the government with respect to any money or balance which may be lying with the government or may become due owing to any dispute, difference or misunderstanding between the Engineer-in-charge on the one hand and the contractor on the other hand or with respect to any delay on the part of the Engineer-in-charge in making periodical or final payment or any other respect whatsoever."
OMP 44/2010 Page 12 In the light of the aforesaid clause, which is a comprehensive clause
for all the claims under the contract, the Supreme Court held that the
contractor is not entitled to interest in the light of the contractual provisions.
The contractual Clause so far as the present case is concerned and
which has been relied upon by the counsel for the petitioner reads as under:
"16(2) Interest on amounts- No interest will be payable upon the earnest money or the security deposit or amounts payable to the Contractor under the contract, but Government Securities deposited in terms of sub- clause (1) of this clause will be repayable with interest accrued thereon."
On the basis of the aforesaid Clause 16(2) and the decision in Sayeed
Ahmed's case, the counsel for the petitioner has contended that interest
should not have been awarded.
13. In my opinion, this contention of the counsel for the petitioner
is not a valid contention. This is for the reason that the expression "amounts
payable to the contractor under the contract" as occurring in Clause 16(2) is
an expression which is necessarily to be read ejusdem generis with the
expression of "earnest money" and "security deposit" as found in this very
clause. That this expression should be read as ejusdem generis is clarified by
Clause 16(1) which is immediately above the Clause 16(2), and which reads
as under:
"16(1) Earnest money and security deposit:- The earnest money deposited by the Contractor with his tender will be retained by the Railway as part of security for the due and faithful fulfilment of the contract by the Contractor. The balance to make up this security deposit which will be 10 per cent of the total value of the contract, unless otherwise specified in the special conditions, if any, may be deposited by the contractor in cash or in
OMP 44/2010 Page 13 the form of Government Securities or may be recovered by percentage deduction from the Contractor‟s "on account" bills, provided also that in case of a defaulting contractor the Railway may retain any amount due for payment to the contractor on the spending „on account bills‟ so that the amount or amounts so retained may not exceed 10% of the total value of the contract."
A reading of Clause 16(1) shows that non payment of interest is
with respect to the amounts which are withheld either as earnest money or
security deposit. The subject Clause 16(1) is not for all amounts under the
contract. In the facts of this case, interest which has been awarded by the
Arbitrators has nothing to do with the amounts which have been withheld
towards the earnest money and security deposit. I therefore reject the
contention that no interest was payable on the amounts as awarded by the
Arbitrators as the interest awarded does not pertain to earnest money or
security deposit amounts.
14. The counsel for the petitioner in addition to the judgment of
Sayeed Ahmed's case has relied upon the decision of the Supreme Court in
the case of M.B.Patel and Company Vs. Oil and Natural Gas Commission
2008 (8) SCC 251. On a first reading, the clause in M.B. Patel's case
appears to be similar to the Clause 16(2) in question, however, the Clause in
the case of M.B. Patel is not similar because in the facts of the present case
there are two Clauses 16(1) and 16(2) and not only one clause similar to
Clause 16(2) as found in the facts of the M.B.Patel's case. In the case of
M.B.Patel, the relevant clause was an independent Clause 18 which reads as
under:
OMP 44/2010 Page 14 "18. Interest on amounts:- No interest will be payable on the security deposit or any other amount payable to the contractor under the contract."
In my opinion, the judgment in M.B.Patel's case also will not
apply to the facts of the present case. If there is a standalone clause like
Clause 18 and which would be equivalent to Clause 16 (2) in the facts of the
present case, then, the expression "any other amount payable to the
contractor" can be read as meaning all types of amounts payable but, as I
have already stated above, in the facts of the present case, the relevant clause
is only a sub-Clause 2 of the main Clause 16(1) and therefore, the
expression "any other amount payable to the contractor" has necessarily to
be read in the context of Clause 16(1) and also to be therefore read ejusdem
generis.
15. The counsel for the petitioner has further relied upon a Division
Bench judgment of Gauhati High Court in Arb. Appeal No. 4/2001 dated
19.6.2002 titled as Union of India Vs. Major V.P.Nijhawan. It is not clear
from the facts of the said judgment, that whether in that case, there were
same clauses as Clause 16(1) and Clause 16(2) as found in the facts of the
present case, in any case, with all due deference and humility I am not
bound by the aforesaid decision and in my opinion, the facts of the present
case are different. I do not therefore think that the judgment of Major
V.P.Nijhawan's case will in any manner assist the petitioner.
OMP 44/2010 Page 15 In this view of the matter, there is no bar to awarding of interest and
in fact statutorily under Section 31(7), an Arbitrator is fully entitled to grant
pendente lite and future interest unless the contract bars the same. I have
already held that the Clauses in the present contract do not bar the grant of
interest.
16. I may lastly note that the counsel for the petitioner sought to
urge that this issue of interest was not referred to arbitration however, I
agree with the counsel for the respondent that this issue need not
specifically be referred on account of Section 31(7) of the Arbitration and
Conciliation Act, 1996 which gives statutory jurisdiction for the awarding of
interest.
In view of the aforesaid observations, I do not find any merits
in this petition and the same is dismissed leaving the parties to bear their
own costs.
I.A. No. 1123/2010 in OMP No. 44/2010
17. Since the petition has been disposed of, no orders are required
to be passed in the application.
VALMIKI J.MEHTA, J
March 05, 2010
Ne/ib
OMP 44/2010 Page 16
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!