Citation : 2010 Latest Caselaw 1249 Del
Judgement Date : 5 March, 2010
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ Arb. P. No.34/2010
5th March, 2010
M/S. GEO MILLER & CO. PVT. LTD. ...Petitioner
Through: Mr. S.D. Singh, Advocate with Mr.
Rahul Kumar Singh, Advocate.
VERSUS
INDIAN OIL CORPORATION LIMITED ....Respondent
Through: Mr. D. Moitra, Advocate. CORAM: HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be allowed to see the judgment?
2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in the Digest?
% JUDGMENT (ORAL) VALMIKI J.MEHTA, J
1. This is a petition under Sections 11, 14 & 15 of the Arbitration
& Conciliation Act, 1996 for the appointment of a new Arbitrator with
respect to the disputes which have arisen between the parties under the
Agreement dated 12.1.1997 as per which the petitioner was to construct a
Waste Water Treatment Plant for the respondent's Refinery Project at
Panipat. Earlier, a petition under Section 11 of the Act was filed and the
respondent had appointed one Mr. S.S. Mishra as the sole Arbitrator.
Subsequently, on an application, moved under Section 16 of the Arbitration Arb. P. No.34/2010 Page 1 & Conciliation Act, 1996, the Arbitrator terminated the arbitration
proceedings. On a petition by the petitioner herein being O.M.P. No.179/04
filed in this Court, the aforesaid order of the Arbitrator was set aside and this
Court directed the Ld. Arbitrator or his successor to conduct further
proceedings. It is stated that the appointed Arbitrator thereafter has not held
any further proceedings. The present petition is therefore filed for
appointment of a new Arbitrator after serving of a notice dated 7.9.07 and
also a letter dated 12.12.07.
2. By this petition, the prayer is that the existing Arbitrator Mr.
S.S. Mishra be removed and a new Arbitrator be appointed because Mr. S.S.
Mishra has failed to act with reasonable dispatch. It is stated that the said
Arbitrator cannot continue and would stand removed. In fact, Mr. Moitra,
on behalf of the respondent has given a list of three fresh names of
Arbitrators to the petitioner in the Court today pursuant to a note dated
2.3.2010 of the respondent. The names of these Arbitrators are Sh. B.S.
Giridhar, DGM (LPG)-DSO, Sh. D.K. Sharma, DGM (Consumer)-DSO and
Sh. Gopal Krishan, DGM (Finance)-DSO. The relief therefore for removal
of Mr. Mishra has become infrunctous.
3. The counsel for the petitioner has verified the aforesaid three
names, out of which one has to be appointed as an Arbitrator, however, the
counsel for the petitioner persists in his prayer on instrcutions that an
independent Arbitrator be appointed and the Arbitrator be not appointed in
Arb. P. No.34/2010 Page 2 terms of the Arbitration Clause. The Arbitration Clause in this case reads as
under:
"9.0.0.0 ARBITRATION
9.0.1.0 Subject to the provisions of Clause 6.7.1.0 and
6.7.2.0 hereof, any dispute or dispute or difference between the parties hereto arising out of any notified claim of the Contractor included in his Final Bill in accordance with the provision of Clause 6.6.3.0 hereof and/or arising out of any amount claim by the Owner (whether or not the amount claimed by the Owner or any part thereof shall have been deducted from the Final Bill of the Contractor or any amount paid by the Owner to the contractor in respect of the work) shall be referred to arbitration by the Sole Arbitration selected by the Contractor from a panel of three persons nominated by the general manager."
4. It is clear that arbitration, in terms of the subject arbitration
clause, has to be by an Arbitrator from a panel of three persons nominated
by the General Manager of the respondent. As already noted above, the
petitioner has been given the three names nominated by the General
Manager but the petitioner states that a sole and independent Arbitrator be
appointed by this Court. It is argued that the respondent has lost the right to
appoint the Arbitrator on its failure to comply with the notices sent by the
petitioner.
5. The counsel for the petitioner relies upon the judgment of the
Supreme Court reported as Northern Railway Administration, Ministry of
Railway, New Delhi Vs. Patel Engineering Company Limited (2008) 10
SCC 240 and para 14 thereof to contend that the Arbitrator must be an
independent and impartial person. I may at this stage refer to the decision of
Arb. P. No.34/2010 Page 3 the Supreme Court in the case of Yashwith Construction Private Limited
Vs. Simplex Concrete Piles India Limited 2006 (6) SCC 204 which lays
down that even after an existing Arbitrator is removed, the appointment of
the Arbitrator has to be in terms of the existing procedure prescribed in the
agreement. Therefore, even if Mr. S.S. Mishra is removed, the Arbitrator
will have to be in terms of the Clause 9.0.1.0 of the Agreement and as per
which the Arbitrator has to be one of the three persons nominated by the
General Manager of the respondent.
6. The Supreme Court recently in the judgment reported as Indian
Oil Corporation Ltd. & Ors. Vs. M/s Raja Transport (P) Ltd. JT 2009 (11)
SC 450 has held that merely because the appointing authority does not
appoint the Arbitrator within the period stated in the notice seeking
appointment of an Arbitrator, this would not mean that the Court has the
power to appoint the Arbitrator but the Arbitrator will have to be appointed
in terms of the agreed clause. The Supreme Court has made it abundantly
clear that the Arbitrator to be appointed has necessarily to be only in terms
of the agreed Arbitration Clause and not a person de hors the Agreement.
Para 21 of the aforesaid judgment, lays down the ratio, and the same reads
as under:
"In the light of the above discussion, the scope of Section 11 of the Act containing the scheme of appointment of arbitrators may be summarised thus:
(i) Where the agreement provides for arbitration with three arbitrators (each party to appoint one arbitrator and the two appointed arbitrators to appoint a third arbitrator), in the event of a party failing to appoint an arbitrator within 30 days
Arb. P. No.34/2010 Page 4 from the receipt of a request from the other party (or the two nominated arbitrators failing to agree on the third arbitrator within 30 days from the date of the appointment), the Chief Justice or his designate will exercise power under sub-section (4) of Section 11 of the Act.
(ii) Where the agreement provides for arbitration by a sole arbitrator and the parties have not agreed upon any appointment procedure, the Chief Justice or his designate will exercise power under sub-section (5) of Section 11, if the parties fail to agree on the arbitration within thirty days from the receipt of a request by a party from the other party.
(iii) Where the arbitration agreement specifies the appointment procedure, then irrespective of whether the arbitration is by a sole arbitrator or by a three-member Tribunal, the Chief Justice or his designate will exercise power under sub-section (6) of Section 11, if a party fails to act as required under the agreed procedure (or the parties or the two appointed arbitrators fail to reach an agreement expected of them under the agreed procedure or any person/institution fails to perform any function entrusted to him/it under that procedure).
(iv) While failure of the other party to act within 30 days will furnish a cause of action to the party seeking arbitration to approach the Chief Justice or his designate in cases falling under sub-sections (4) and (5), such a time-bound requirement is not found in sub-section (6) of Section 11. The failure to act as per the agreed procedure within the time-limit prescribed by the arbitration agreement, or in the absence of any prescribed time-limit, within a reasonable time, will enable the aggrieved party to file a petition under Section 11(6) of the Act.
(v) Where the appointment procedure has been agreed between the parties, but the cause of action for invoking the jurisdiction of the Chief Justice or his designate under clauses (a), (b) or (c) of sub-section (6) has not arisen, then the question of the Chief Justice or his designate exercising power under sub-section (6) does not arise. The condition precedent for approaching the Chief Justice or his designate for taking necessary measures under sub-section (6) is that
(i) a party failing to act as required under the agreed appointment procedure; or
(ii) the parties (or the two appointed arbitrators) failing to reach an agreement expected of them under the agreed appointment procedure; or
(iii) a person/institution who has been entrusted with any function under the agreed appointment procedure, failing to perform such function.
(vi) The Chief Justice or his designate while exercising power under sub-section (6) of Section 11 shall endeavour to give effect to the appointment procedure prescribed in the arbitration clause.
(vii) If circumstances exist, giving rise to justifiable doubts as to the independence and impartiality of the person nominated, or if other circumstances warrant appointment of an independent arbitrator by ignoring the procedure prescribed, the Chief Justice or his designate may, for reasons to be recorded ignore the designated arbitrator and appoint someone else."
Arb. P. No.34/2010 Page 5
7. Sub-para (vi) of the aforesaid para 21 of the judgment of the
Supreme Court in the case of Indian Oil Corporation's case (supra) makes
it crystal clear that the Courts should endeavour to give effect to the
appointment procedure prescribed in the arbitration clause, meaning thereby,
the Court should not appoint an independent Arbitrator.
8. In view of the judgment of the Supreme Court of Indian Oil
Corporation's case and in which judgment the earlier decisions have been
considered and explained including the judgment of Northern Railway's
case, I am unable to agree with the counsel for the petitioner that this Court
is empowered to appoint an independent Arbitrator against the terms of the
agreed Arbitration Clause. Even the Northern Railway's case requires the
Court to take into account the qualifications required by the agreement.
9. In view of the above discussion and the situation that a fresh
panel of three names of the arbitrators has been suggested by the respondent
to the petitioner, the present petition cannot be allowed for appointment of
an independent Arbitrator. Since the respondent itself has terminated the
appointment of Mr. S.S. Mishra, the petition for removal of Mr. S.S. Mishra
is infructuous to this extent. So far as the relief for appointment of an
independent Arbitrator, the petition stands dismissed and the respondent is
held entitled to act for appointment of the Arbitrator in terms of the agreed
Arbitration Clause. However, the petitioner is at liberty to select any one of
the three names suggested for being appointed as an Arbitrator within a
Arb. P. No.34/2010 Page 6 period of two weeks from today failing which the respondent may appoint
any one person out of the aforesaid three persons as an Arbitrator to
determine all the disputes/differences/claims/counter claims as arising out
between the parties and which are the subject matter of the present petition.
The prayer for appointment of an Arbitrator by the Court is rejected with
costs of Rs.50,000/- in terms of para 37 of the judgment of the Supreme
Court in the case of Salem Advocate Bar Association Vs. Union of India
(2005) 6 SCC 344.
10. With the aforesaid observations, the petition stands disposed of.
VALMIKI J.MEHTA, J
March 05, 2010
Ne
Arb. P. No.34/2010 Page 7
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!