Citation : 2010 Latest Caselaw 3269 Del
Judgement Date : 15 July, 2010
*IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of decision: 15th July, 2010.
+ W.P.(C) No.618/2008 & CM No.1212/2008 (for interim relief)
%
SMT. USHA GOEL ..... Petitioner
Through: Ms. Neha Gupta, Advocate
Versus
BSES YAMUNA POWER LIMITED ..... Respondent
Through: Mr. Vikram Nandrajog & Mr. Sushil
Jaswal, Advocates.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? No
2. To be referred to the reporter or not? No
3. Whether the judgment should be reported No
in the Digest?
RAJIV SAHAI ENDLAW, J.
1. The petitioner by this writ petition seeks quashing of the order
dated 20th November, 2007 of the respondent holding the petitioner
guilty of dishonest abstraction of energy and quashing of the
bill/demand of Rs.23,23,608/- on the petitioner in pursuance thereto.
This Court vide order dated 25th January, 2008 which continues to be in
force while issuing notice of the writ petition stayed the said demand.
The parties were referred to Lok Adalat where the respondent gave a
proposal for settlement on payment of 70% of the impugned demand.
The same was not acceptable to the petitioner. The respondent has filed
the counter affidavit to which rejoinder affidavit has been filed by the
petitioner. The counsels have been heard.
2. The electric connection in question is in the name of M/s V.D.
Industries of which petitioner is the Proprietor and is for industrial
purposes. It is the case of the petitioner that on 22nd November, 1999 the
respondent replaced the manual meter with a mechanical CT meter; that
on 14th September, 2006 the mechanical CT meter was replaced with an
electronic meter; that however neither the box of the meter nor CT was
changed and the box and the CT are the same as installed in 1999; that
on 11th January, 2007 the petitioner complained of the meter not
showing the reading; the officials of the respondent visited the premises
of the petitioner on 12th January, 2007 and endorsed that the reading was
not visible; that on 6th April, 2007 the officials of the respondent again
visited the premises of the petitioner and again made an endorsement
"no download, no display show by meter"; that on 23rd April, 2007 a
new CT meter was installed along with box with new CT and the old
meter disconnected but retained at site; that on 27 th April, 2007 the
disconnected meter was again inspected though in the absence of the
petitioner; that in the assessment during the said inspection, without
getting the disconnected meter tested in lab, endorsement was made of
the petitioner indulging in DAE and "CT connection found short
deliberately" and the meter being found burnt. It is further the case of
the petitioner that the disconnected meter was taken away finally on 27th
April, 2007 after breaking the seal thereof and without resealing the
same.
3. The respondent in the speaking order impugned in this writ
petition has held that during the inspection on 27 th April, 2007,
connected load of 64.198 KW was found as against the sanctioned load
of 33.00 KW; the CT box and meter box seals were found tampered and
reaffixed; Y phase CT connection was found deliberately short and
meter disconnected; that the supply was restored through a new meter;
that the lab to which the petitioner's disconnected meter was sent has in
its report concluded that the LCD & LED of the disconnected meter was
"found not ok, accuracy of the meter could not be checked because of
the same being dead and CMRI data could not be retrieved". Though the
speaking order deals with the contentions of the petitioner in the reply to
the show cause notice, one of the reasons given is that on analysis of
consumption pattern a sudden increase in the recorded consumption after
replacement of the tampered meter was found. It has thus been held that
the same was clearly indicative of dishonest abstraction of energy.
4. The counsel for the petitioner has contended that the show
cause notice ought to have been issued within 30 days but was issued
thereafter; that the meter was sent to/received by the lab with the seal
broken and thus no reliance could be placed on the record of the lab.
Reliance is placed on Jagdish Narayan Vs. North Delhi Power Limited
140 (2007) DLT 307 laying down that mens rea or intention of
consumer to dishonestly abstract electricity must be proved conclusively
to bring home charge of DAE. It was further held that interference of
DAE should not be permitted to be drawn on mere fact that the meter
had been found with broken seals. Reliance is also placed on Udham
Singh Vs. BSES Rajdhani Power Ltd. 136 (2007) DLT 500 laying
down that inspection should precede assessment that consumer indulged
in DAE and mere irregularity in meter seals, or breakage of glass, do not
authorise issuance of show cause notice.
5. The counsel for the petitioner has further contended that the
meter in question was inspected earlier thrice on 12th January, 2007, 6th
April, 2007 and 23rd April, 2007 and no allegation as made on 27th April,
2007 of any such tampering was made. It is thus contended that the
inspection of 27th April, 2007 suddenly alleging tampering is bad.
6. The counsel for the respondent states that neither the data was
downloaded from the disconnected meter nor was the meter inspected
prior to 27th April, 2007. It is contended that the visits on 12 th January,
2007, 6th April, 2007 and 23rd April, 2007 were merely checks and
cannot be classified as inspection. It is further averred that it was quite
evident during the inspection on 27th April, 2007 as also borne out from
the photographs that the petitioner had tampered with the meter. It is
further urged that the petitioner has failed to explain the sudden surge in
consumption immediately after replacement of the meter.
7. The counsel for the respondent has also urged that the
disputed questions of fact raised cannot be adjudicated in the writ
petition and the appropriate remedy for the petitioner is to approach the
Special Courts constituted under Section 153 of the Electricity Act, 2003
as laid down by the Division Bench of this Court in B.L. Kantroo Vs.
BSES Rajdhani Power Ltd. 154 (2008) DLT 56.
8. The counsel for the petitioner in rejoinder has sought to
explain the sudden surge in consumption immediately on replacement of
the meter by contending that a new motor has been installed. The
counsel for the respondent however points out that the said explanation
was given after the speaking order was made and the respondent thus
had no occasion to deal with the same.
9. I am perturbed by the admitted sudden surge in consumption
immediately on replacement of the allegedly defective meter. The same
is prima facie indicative of DAE. It is too much of a co-incidence that a
new motor leading to increased consumption was installed at about the
same time as the removal of the allegedly defective meter and its
replacement with a new one. Leave apart the other contentions, this
alone is a factual dispute and if the petitioner is unable to satisfy that a
new motor in fact was installed, sudden increase in consumption without
any other parameter can only lead to one conclusion which is against the
petitioner. This Court in the exercise of writ jurisdiction would not come
to the assistance of such a consumer of electricity. There is nothing to
indicate that the petitioner before or immediately after installing the new
motor, if any, informed the respondent of the same or sought any
additional load for the same. In the circumstances, the said explanation
prima facie appears to be an afterthought.
10. The writ petition is therefore dismissed. The petitioner shall
however have the remedies available to her in law before the fora which
can go into such disputed questions. It is further clarified that nothing
contained herein shall be deemed to be an expression of view on the
merits of the case and which observations have been made purely for the
purposes of determining whether the writ jurisdiction should be
exercised or not. The petition is accordingly dismissed and the interim
order vacated. However, notwithstanding the same, the respondent shall
not disconnect the electric supply to the petitioner owing to non-
payment of the demand, subject matter of this writ petition, for a period
of four weeks from today. The said time is given to allow the petitioner
to approach the alternative forum and to apply for interim relief therein.
However, unless there is stay of disconnection from any other
forum/Court after four weeks herefrom and further if the petitioner fails
to pay the demanded amount, the respondent shall be free to disconnect
the electric supply to the petitioner.
The petition is disposed of.
No order as to costs.
RAJIV SAHAI ENDLAW (JUDGE) 15th July, 2010 bs (Corrected and released on 26th July, 2010.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!