Citation : 2010 Latest Caselaw 3178 Del
Judgement Date : 9 July, 2010
11
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ Date of Decision: 09.07.2010
% O.M.P. 345/2010
M/S BHAGWANA RAM CHOUDHARY & CO ..... Petitioner
Through: Mr. Pankaj Chaudhry, Advocate
versus
THE EXECUTIVE ENGINEER BFD-V,CPWD
BARMER (RAJASTHAN) ..... Respondent
Through:
CORAM:
HON'BLE MR. JUSTICE VIPIN SANGHI
1. Whether the Reporters of local papers may No
be allowed to see the judgment?
2. To be referred to Reporter or not? No
3. Whether the judgment should be reported No
in the Digest?
VIPIN SANGHI, J. (Oral)
IA 7981/2010 (Exemption) Allowed, subject to all just exceptions.
O.M.P. 345/2010
1. The petitioner has filed the present petition under Section 34 of
the Arbitration and Conciliation Act ("the Act") to seek for setting aside
of the award dated 03.02.2010 made by Sh. Divakar Garg, the sole
arbitrator in Case No.ARB/DG/389.
2. The learned Arbitrator has rejected all the claims made by the
petitioner/contractor and has upheld the action of the respondent in
rescinding the contract and in forfeiting the Earnest Money Deposit
(EMD) and in encashing the performance bank guarantee furnished by
the petitioner, by holding that the petitioner had failed to perform the
works under the contract.
3. The petitioner/contractor was awarded the contract involving the
work of maintenance of roads, embankment and culverts on Indo-Pak
Border from BP 921 to BP 951 in Gujarat Sector (Sub Head: Repair to
damaged road) vide agreement No.01/EE/BFD-V/BMR/2007-08. The
tendered amount was Rs.94,91,242/- as against the estimated cost of
Rs.54,13,319/-. The date of start of work was 13.04.2007 and the
stipulated date of completion was Rs.12.08.2007. However, the work
was prematurely rescinded by the respondent on 25.06.2007. This led
to disputes arising between the parties, which were referred to
arbitration of the learned Arbitrator.
4. The petitioner/claimant's claim No.1 was for Rs.18 lakhs towards
work already done but which remained unpaid. The petitioner also
claimed refund of the forfeited EMD of Rs.1,10,000/- (Claim No.2); the
refund of forfeited security deposit of Rs.4,75,000/- (Claim No.3); and,
the refund of forfeited performance guarantee of Rs.4,75,000/- (Claim
No.4). Loss of profit of Rs.7,50,000/- was claimed under Claim No.5.
Interest was claimed under Claim No.6 and arbitration/litigation
charges of Rs.50,000/- was claimed under Claim No.7. The
petitioner/claimant, however, gave up claim no.3 as, in fact, neither
any security deposit had been deposited by the petitioner nor the
same was forfeited by the respondent.
5. It appears that after the date of start of the work, i.e.
13.04.2007, on account of failure of the petitioner to start the work,
the respondent initially sent a communication dated 28.04.2007
complaining about the delay in start of work. The petitioner did not
submit the progress chart for each milestone and did not get it
approved from the department as envisaged in clauses (5.1) and 10 of
the agreement. The petitioner also did not obtain a valid labour
license under clause 19 of the contract, nor submitted any labour
report as envisaged under clause 19-D of the contract. All this showed
that the petitioner was not ready for the performance of the contract.
6. A further notice was issued to the petitioner by the respondent
on 22.05.2007 under clauses 3(a), 3(b) and 3(c) and he was called
upon to show cause as to why action be not taken against him for
breach of contract. There was no response to this notice by the
petitioner.
7. Another show cause notice dated 08.06.2007 was issued to the
petitioner. He responded to this show cause notice vide letter dated
13.06.2007, wherein he cited hindrances like rains on few days. The
petitioner informed that they had started collection of GSB material
and stone aggregate and had also asked for stoppage of traffic on the
road to start the laying and compacting of stone aggregate for road
work. The claimant vide communication dated 16.06.2007 stated that
it was aware that the road in question is an important border road and
that it could not be closed for any time. The petitioner also assured
that they would complete the work by 12.08.2007, i.e. the stipulated
date of completion.
8. The respondent, after considering the ground reality that even
after lapse of 50% of the time (two months) upto 13.06.2007, the work
had not even started, rescinded the contract vide communication
dated 25.06.2007. Thereafter, joint measurements of the material
brought by the claimant was fixed for 18.07.2007 and the material
brought by the petitioner at site was recorded. Respondent found out
that the materials brought by the claimant were not as per CPWD
specifications. This was communicated to the claimant vide letters
dated 20.08.2007 & 31.08.2007 and he was also requested to remove
the rejected material from the site immediately.
9. Before the learned Arbitrator, the petitioner/claimant pleaded
that he had mobilized the required labour and material at site, but the
progress of work was slow on account of obstruction by BSF authorities
at site, non availability of space for stacking the material, heavy and
frequent traffic on the narrow road at the site, continuous rain in the
area, non availability of approval from BSF for stoppage of traffic on
the road, non payment of work already done and non availability of AE
due to frequent transfer.
10. On the other hand, the respondent relied on the contractual
terms. The petitioner was required to acquaint himself with the site
conditions before tendering. The petitioner was also advised that some
restriction may be imposed by the BSF, and under special condition
no.3 the claimant was advised that vehicular traffic cannot be stopped
and if required, such traffic may be diverted on the diversion road to
be provided by the petitioner at his own costs.
11. The learned Arbitrator relied on the communication of the
petitioner dated 13.06.2007 and two communications dated
15.06.2007 and 16.06.2007 (C-3 & C-4), which showed that the
petitioner started collecting materials as late as around 13.06.2007.
He also gave importance to the fact that the hindrances were pointed
out by the petitioner only after the receipt of the show cause notice
dated 08.06.2007. The stand taken by the petitioner in its
communication dated 13.06.2007 and 15.06.2007 (C-3) that the work
could not be done without stopping the vehicular traffic was held to be
contrary to the contractual terms, as the petitioner was informed that
the traffic could not be stopped on the said road, and it was the
obligation of the petitioner to provide for a diversion road to carry out
the contractual work.
12. The non submission of the time and progress chart and also the
failure of the petitioner to examine the tender conditions was also
considered by the learned Arbitrator to be a reason enough to reject
his claims. As per Schedule F of the tender document, the petitioner
was supposed to complete upto 1/8th work within 1/8th of the total time
and upto 3/8th of work within 1/2 of the total time allowed. However,
since no work had begun despite half of the period having expired, the
learned Arbitrator held that the rescission of the contract could not be
said to be arbitrary or illegal. Consequently, he held that the
respondent was entitled to forfeit the EMD and the performance
guarantee under the contract. He, therefore, rejected the claim nos.2
and 4. As aforesaid, claim no.3 had already been withdrawn by the
petitioner.
13. So far as claim no.1 was concerned, the learned Arbitrator
referred to the joint measurements taken on 18.07.2007, which
showed that only some substandard materials like stone aggregate
and GSB (which was not even contracted for) were collected by the
petitioner at the site. The respondent had directed the petitioner to
remove such materials from the work site vide letter dated
31.08.2007. Since the petitioner failed to establish that it had
executed any part of the contracted work, the learned Arbitrator
rejected claim no.1. Claim no.5 towards loss of profit was rejected, as
the learned Arbitrator held that the determination of the contract was
legal and contractually valid. Consequently, claim no.6 towards
interest and claim no.7 towards litigation/arbitration expenses were
also rejected.
14. The submission of the learned counsel for the petitioner is that
the contract could not have been rescinded merely on account of the
late start of the work. In support of his submission, he relies on M/s
Hind Construction Contractors by its sole proprietor
Bhikamchand Mulchand Jain (Dead) by LR's v. State of
Maharashtra, AIR 1979 SC 720 to submit that the contract could
not have been rescinded as time was not of the essence of the
contract. In my view, this decision is not applicable in the facts of the
present case. It appears that the petitioner did not even raise the
issue as to whether the time was of the essence of the contract or not
before the learned Arbitrator. This issue cannot be raised at this stage
of the proceedings. The petitioner has not even referred to the terms
of the contract to substantiate his contention that time was not of the
essence of the contract.
15. The facts of this case do suggest that, in fact, time was of the
essence of the contract. A perusal of the award shows that the period
during which the work was to be completed was only four months.
Moreover, the petitioner was required to give the timetable of
milestones as per Schedule F of the tender document, which provided,
inter alia, that upto 1/8th work had to be completed within 1/8th of the
total time and upto 3/8th of the work had to be completed within 1/2 of
total time allowed. The parties were, therefore, conscious of the fact
that strict punctuality had to be maintained by the petitioner with
regard to the execution of the work and it was not open to the
petitioner to claim that they could complete the work in the remaining
half tenure, when, in the first half of the contract term, the petitioner
had not done any work at all.
16. The next submission of the learned counsel for the petitioner is
that the respondent was not entitled to forfeit the EMD or encash the
performance guarantee furnished by the petitioner, as no loss had
been caused to the respondent. In support of his submission, the
petitioner relies on a Supreme Court decision in Union of India v.
Rampur Distillery & Chemical Co. Ltd., AIR 1973 SC 1098. In my
view, this decision is of no avail to the petitioner. In the facts of that
case, the Supreme Court had observed that the contractor had
supplied the stipulated quantity of rum at the contractual rate, though
belatedly. In this light, the Supreme Court held that no loss has been
caused to the appellant, Union of India and no attempt had been made
by Union of India to establish that they had suffered any loss or
damage on account of the breach committed by the
respondent/contractor.
17. In the facts of this case, the contract having been rescinded,
there was no question of the petitioner performing the work at all. On
account of the failure of the petitioner to perform the contract under
the contractual terms, the respondent was entitled to encash the
performance guarantee and forfeit the EMD.
18. The last submission of the learned counsel for the petitioner is
that the petitioner has been wrongfully denied the claim towards loss
of profit. He places reliance on the Supreme Court decision in M/s
A.T. Brij Paul Singh & Ors. v. State of Gujarat, AIR 1984 SC
1703. This decision is of no avail to the petitioner. Herein the breach
of the contract was committed by petitioner himself, as held by the
learned Arbitrator. The arbitrator held that a party who is in breach
cannot certainly claim damages towards loss of profit, the petitioner
cannot be given any relief.
19. The petitioner has made no other submission. The award
appears to be well reasoned and no part of the same appears to be in
conflict with the public policy of India. None of the findings of the
learned arbitrator can be said to be founded on an erroneous
understanding of the law. For the aforesaid reasons, I find no merit in
this petition and the same is accordingly dismissed.
VIPIN SANGHI, J.
JULY 09, 2010 sr
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!