Citation : 2010 Latest Caselaw 3142 Del
Judgement Date : 7 July, 2010
R-20
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P. NO.181/2004
Date of Decision: 07th July, 2010
M/S BELLARY STEELS & ALLOYS LTD. ..... Petitioner
Through: Mr. C. Mohan Rao, Advocate
versus
M/S OJSC POWER MACHINES - ZLT, LMZ ..... Respondent
Through: Mr. Amar Gupta, Mr. Mayank
Mishra & Mr. Chetan Chopra,
Advocates
CORAM:
HON'BLE MR. JUSTICE VIPIN SANGHI
1. Whether the Reporters of local papers may
be allowed to see the judgment? No
2. To be referred to Reporter or not? No
3. Whether the judgment should be reported
in the Digest? No
% JUDGMENT (Oral)
VIPIN SANGHI, J.
1. In challenge in these proceedings under Section 34 of the
Arbitration and Conciliation Act is the award dated 11.12.2003 made
by an arbitral tribunal consisting of three learned arbitrators. The
respondent herein was the claimant before the arbitral tribunal. The
petitioner had also raised certain counter claims. The arbitral tribunal
substantially awarded the claims of the respondent.
2. The parties had entered into an agreement whereunder the
respondent agreed to supply one complete 12 MW Turbo generation
set with auxiliaries for a total consideration of US$ 1,600,000.00 (One
Million Six Hundred Thousand US Dollars only). The equipment under
the agreement was to be delivered at the Madras port. The same was,
however, delivered at Bombay port. Under the terms of the agreement
a sum of US$ 1,440,000.00 (One Million Four Hundred Forty Thousand
US Dollars only) stands paid to the respondent. The last instalment of
10% of the value, amounting to US$ 160,000 (One Hundred and Sixty
Thousand US Dollars Only) was, however, not paid. Under the
contract, the payment was made through the mechanism of a letter of
credit.
3. It appears that the last instalment of US$ 160,000.00 could
not be paid due to delay in the shipment of the equipment, caused as
a result of the change of port from Madras to Bombay and the expiry of
the validity of the letter of credit in the meantime.
4. As the petitioner failed to make payment of the balance
consideration of US$ 160,000.00, the respondent invoked the
arbitration clause contained in the agreement between the parties.
The matter was referred to the arbitral tribunal consisting Mr. Justice
Attamjit Singh Nehra, Presiding Arbitrator, Mr. Justice J.K. Mehra,
Arbitrator and Mr. Justice N.C. Kochhar, Arbitrator. The arbitral tribunal
rendered a unanimous award in favour of the respondent.
5. The respondent raised three claims in the arbitration
proceedings. The first claim was towards the payment of the balance
amount of US$ 160,000.00 towards the cost of the turbo generator set
and accessories. The second claim was for US$ 65,000 towards
expenses stated to have been incurred in maintaining the performance
bank guarantee provided by the respondent to the petitioner. The
third claim was for interest @ 3.1% per annum amounting to US$
17,773/- till the date of filing of the statement of claim, besides the
claim for pendente lite and future interest. The respondent, apart from
denying the liability towards payment of the amount claimed by the
respondent also raised its counter claim in the sum of Rs.75,22,000/-,
the details whereof are as follows:
1. Value of missing generator parts 6 lakhs 2. Custom duty and penalty paid on Engineering 13.72 lacs
drawings for non-assessment/ improper assessment
3. Demurrage charges 4 lacs
4. Legal expenses & other litigation charges, additional 1.5 lacs freight, L/C amendment charges etc.
5. Loss suffered by the respondent in completing the 50 lacs project due to breaches committed by the Complainant
6. Before the arbitral tribunal the parties relied on documents
filed by them along with their pleadings and admitted the documents
filed by the opposite party and did not lead any evidence. The tribunal
heard the counsels for the parties and on the basis of the record and
the written arguments submitted before it, proceeded to pass the
award. The arbitral tribunal allowed the claim of the respondent for
US$ 160,000 with interest @ 3.1% per annum w.e.f. 03.06.2003 i.e. the
date of filing of the statement of claim, till realisation. It also allowed
the claim towards legal expenses incurred by the claimant/respondent
herein amounting to Rs.2,94,300/-. The tribunal, however, disallowed
the counter claim preferred by the petitioner herein in its entirety. For
disallowing the counter claim preferred by the petitioner, the tribunal
adopted the reason that no such claim had ever been asserted by the
petitioner and, consequently, it could not be said that a dispute had
been raised by the petitioner in respect of its claims which had been
repudiated by the respondent. It was held that no dispute arose which
could be arbitrated, so far as the counter claim was concerned. The
tribunal found that the counter claims had been raised for the first time
in the reply/counter statement filed before the arbitral tribunal.
7. Mr. Rao, learned counsel for the petitioner/objector, does not
challenge the rejection of the counter claim by the tribunal as not
being maintainable. His submission, however, is that while allowing
the claim of the respondent the tribunal has not considered the
defence of the petitioner that the amount claimed was not payable to
the respondent.
8. Before proceeding to examine the award on this aspect, it
would be useful to refer to some of the contractual terms. Article 3 of
the contract provided that the delivery of the equipment under the
contract shall take place within 10 months of the opening of the letter
of credit. The date of bill of lading was to be considered as the date of
delivery. Article 4 provided the terms of payment. The payment was
to be made through an irrevocable confirmed letter of credit which was
to be opened by the petitioner within 10 days of the signing of the
contract for the total contract value. The payment was to be made in
four instalments, the last being 10% of the contract value i.e. US$
1,60,000 within 7 days of the presentation of the following documents:
(i) invoice in three copies, (ii) copy of guarantee of the respondent in
favour of the petitioner for the equivalent amount for the guarantee
period. The bank guarantee was to be issued by the respondent in
favour of the petitioner in the prescribed proforma.
9. The letter of credit opened at the instance of the petitioner
provided the destination of the shipment as Madras port. A perusal of
the award shows that the claimant/respondent herein had written to
the petitioner herein that though the generators were ready, but since
no vessel was going to Madras port in the near future, it was not
possible to send the same to Madras port and the same could be
transported to Mumbai port, for which the vessel was available. The
petitioner vide letters dated 18.02.1998 & 03.03.1998 requested the
respondent to send the generator sets to Mumbai port. Consequently,
the destination port was changed to Mumbai port from Madras port at
the instance of the petitioner vide amendment of the letter of credit
dated 26.02.1998. The generator was accordingly sent to Mumbai port
where delivery was taken by the petitioner herein.
10. Reference may also be made to Article 8A which dealt with
claims on quality and quantity. The claims on quality and quantity of
the delivered goods was to be sent by the petitioner directly to the
respondent. Clause 8.2 provided that the claims on quality and
quantity of the goods could be made within two months from the date
of receipt of equipment at site, but not later than three months from
the date of delivery. Clause 8.3 further provided that claims of
shortage of goods, if responsibility of the carrier is excluded, could be
made within two months from the date of receipt of equipment at site,
but not later than three months from the date of delivery. The claims
both on quality and quantity of goods were required to contain the
description of the goods, the contract number, the nature of the
petitioner's claim and demands. The same was to be forwarded by
registered post along with the necessary documents.
11. The submission of learned counsel for the petitioner is that in
its reply and counter claim preferred before the arbitral tribunal, the
petitioner had raised various defences to deny the claim of the
respondent. The petitioner had asserted that there was delay on the
part of the respondent in the shipment of the equipment which led to
the expiry of the letter of credit. According to the petitioner the
change of port from Madras to Bombay led to the petitioner incurring
additional charges and damages. The petitioner further asserted that
it incurred demurrage charges, penalty and litigation charges since the
equipment was sent to the Bombay port. It was further asserted that
the respondent had failed to supply the engineering drawings with
proper declaration the shipped equipment. This also led to delay in the
release of the equipment and led to the petitioner incurring additional
customs duty, demurrage, additional transportation etc. As aforesaid,
the submission of learned counsel for the petitioner is that none of
these defences have been considered by the arbitral tribunal while
allowing the claim of the respondent.
12. On the other hand, learned counsel for the respondent has
supported the award in its entirety. He submits that the petitioner
never raised any of the disputes which form the basis of the counter
claim and also did not, at any stage, raise any of the defences as were
sought to be raised for the first time in the reply and counter
statement before the arbitral tribunal. He submits that, on the
contrary, the petitioner repeatedly promised that the balance of US$
160,000 would be released to the respondent shortly and the reason
for the delay in release of the said amount was stated to be the
financial stringency of the petitioner.
13. Having heard learned counsels for the parties and perused
the impugned award, I am of the view that there is absolutely no merit
in the objections raised by the petitioner and the same deserve to be
dismissed. The award passed by the arbitral tribunal is well reasoned
and does not call for any interference. There is no merit in the
submission of learned counsel for the petitioner that its defences have
not been considered by the arbitral tribunal. Mr. Rao has not been
able to point out any material whatsoever from the record to suggest
that in support of the petitioners aforesaid defences even a shred of
paper had been produced as evidence before the tribunal to
substantiate the petitioners plea that there was any delay or default on
the part of the respondent in their performance of the agreement. Not
an iota of evidence appears to have been led, and no document was
produced to substantiate the plea that the petitioner has incurred
additional costs due to any act or omission of the respondent. So far
as the change of port of destination is concerned, from the award itself
it is evident that the same had been changed as there was no vessel
available to take the equipment to Madras port, whereas a vessel was
available which could deliver the shipment at Bombay port. On this
being informed, the petitioner itself had instructed the respondent
supplier to ship the equipment to Bombay port. The consent of the
petitioner to the change of the port is also evidenced from the
amendment in the letter of credit as aforesaid. Obviously, the
additional expenses, if any, incurred by the petitioner on account of
the change of port could not have been claimed from the respondent in
these circumstances. The decision to change the port of the dispatch
was that of the petitioner. In any event, the petitioner, it appears,
produced no material whatsoever to substantiate its claim towards
demurrage, higher duty, transportation charges etc. on account of
change of port from Madras to Bombay.
14. Learned counsel for the petitioner has also not been able to
show that the petitioner produced any material before the tribunal in
support of the submission that the respondent had failed to supply the
correct engineering drawings and thereby breached the contractual
obligations. No correspondence appears to have been brought on
record to show the raising of any grievance in this regard by the
petitioner. No particulars of the damages claimed to have been
suffered were stated before the tribunal.
15. I have already referred to the contractual terms, which
required the petitioner to raise its claims regarding the quality and
quantity of the goods being deficient within two months, and certainly
not later than three months from the date of delivery. There is nothing
to show that any such grievance or claim was ever raised by the
petitioner. In this background, obviously the tribunal could not have
been expected to deal with the wholly unsubstantiated defence of the
petitioner.
16. Learned counsel for the respondent has submitted that the
respondent had placed before the arbitral tribunal correspondence to
show that the principal claim of the respondent stood unconditionally
admitted. He has referred to the letters sent by the petitioner on
31.01.2000, 06.04.2000, 15.05.2001, 16.06.2001 etc. and lastly on
06.03.2002 wherein the petitioner repeatedly expressed its regret for
not being able to release the last instalment of 10% of the equipment
cost and assured the respondent that the same would be released very
soon.
17. For all the aforesaid reasons, I find no merit in this petition.
The same is, accordingly, dismissed.
VIPIN SANGHI, J.
JULY 07, 2010 rsk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!