Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Budhiraja Electricals vs Rites
2010 Latest Caselaw 3062 Del

Citation : 2010 Latest Caselaw 3062 Del
Judgement Date : 2 July, 2010

Delhi High Court
M/S Budhiraja Electricals vs Rites on 2 July, 2010
Author: Rajiv Sahai Endlaw
            *IN THE HIGH COURT OF DELHI AT NEW DELHI

+                          CS(OS) 571A/1999

%                                            Date of decision: 2nd July, 2010

M/S BUDHIRAJA ELECTRICALS                ..... Petitioner
                 Through: Ms. Anusuya Salwan, Advocate.

                                    Versus

RITES                                                    .... Respondent
                           Through:      Mr. Ravi Sikri & Mr. Ayushya,
                                         Advocates.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1.      Whether reporters of Local papers may
        be allowed to see the judgment?                      NO

2.      To be referred to the reporter or not?               NO

3.      Whether the judgment should be reported              NO
        in the Digest?

RAJIV SAHAI ENDLAW, J.

1. The objections under Sections 30 & 33 of the Arbitration Act, 1940

by way of I.A. No.6198/1999 preferred by the petitioner M/S Budhiraja

Electricals, on being served with notice of filing in this Court of the award

dated 10th February, 1999 of Sri B.K. Makhija, General Manager of the

respondent Rites, acting as the sole Arbitrator are for consideration. The

Arbitrator was appointed pursuant to the order dated 26th November, 1997 of

this Court in a petition under Section 20 of the 1940 Act preferred by the

petitioner and registered as Suit No.2312A/1995 of this Court. Accordingly,

even though the Arbitrator entered upon reference after coming into force of

the 1996 Act but the arbitration was one under the 1940 Act.

2. It was one of the pleas of the respondent Rites in Suit No.2312A/1995

that the petitioner having prior thereto furnished a no claim certificate and

accepted refund of the security deposit thereunder was disentitled from

seeking arbitration. This Court in order dated 26th November, 1997 in Suit

No.2312A/1995 left the said question also open for arbitration. The

Arbitrator in the award filed in this Court has held that the petitioner was

forced to give the no claim certificate and/or furnishing of the same did not

prevent the petitioner from seeking arbitration of disputes raised earlier.

3. The petitioner before the Arbitrator raised six claims. The objections

have been preferred to the findings of the Arbitrator on Claim Nos.1, 2 & 4.

However, the counsel for the petitioner at the time of hearing fairly stated

that she was not pressing the objections insofar as the award on Claim No.1

and confined her arguments to the objections to the findings of the Arbitrator

on claim nos.2 & 4 only.

4. The Claim No.2 of the petitioner of Rs.13,49,017/-was for non

payment of escalation specially agreed to between the parties. It was the case

of the petitioner that the respondent Rites had agreed to pay escalation in

terms of the letter dated 2nd March, 1990 of the petitioner to the respondent

Rites and in addition to the escalation provided under Clause 10CC of the

contract; that while the petitioner had been paid for escalation in accordance

with Clause 10CC, it had not been paid the escalation in terms of the letter

dated 2nd March, 1990.

5. The respondent Rites contested that the letter dated 2nd March, 1990

whereunder Claim No.2 of Rs.13,49,017/- for escalation was made, was a

part of the contract. The Arbitrator negated the said contention of the

respondent Rites and held the letter dated 2nd March, 1990 to be a part of the

contract.

6. However, the Arbitrator has rejected the Claim No.2 for the reason of

the petitioner having failed to submit any documentary proof of entitlement

to escalation in accordance with the letter dated 2nd March, 1990.

7. The respondent Rites on 4th August, 1989 had invited tenders for the

electrical installation works at Exhibition Centre of Trade Fair Authority of

India (TFAI) at New Delhi. The respondent Rites having been unable to take

a decision on the Tender of the petitioner within the period of its validity,

sought extension and the petitioner vide its letter dated 2nd March, 1990

(supra) agreed to such extension with the clarification that "difference in

costs due to any statutory increase in prices by the Government or in the

market by the manufacturers since the date of opening of the Tender shall be

payable" by the respondent Rites to the petitioner. The Tender of the

petitioner was accepted and a Letter of Intent dated 18/19th April, 1990

issued by the respondent Rites to the petitioner.

8. It was further the case of the petitioner that as per the Tender the work

had to be completed within a tight time schedule and owing whereto the

petitioner had kept its resources in a state of readiness; however the

execution of the work was delayed for reasons not attributable to the

petitioner. Hence, the claim of the petitioner for escalation.

9. The petitioner had claimed total escalation of Rs.28,63,158.11p. The

respondent Rites allowed escalation of Rs.15,14,121/-. Accordingly, the

balance amount of Rs.13,49,017/- was the subject matter of Claim No.2

before the Arbitrator. It was the petitioner's case that the escalation paid to it

of Rs.15,14,121/- was under Clause 10CC of the contract and escalation

claimed of Rs.13,49,017/- was in terms of the letter dated 2nd March, 1990.

10. The Arbitrator has held that the letter dated 2nd March, 1990 had been

made part of the contract; that there was delay not attributable to the

petitioner entitling the petitioner to escalation. However, the Arbitrator has

held that "the best and only right proof to establish the then prevailing rates

would have been the actual supplier bills/purchase vouchers which the

claimant did not produce either during the currency of the contract or later

during the arbitration proceedings". Such hesitancy on the part of the

petitioner to produce best evidence was held to disentitle the petitioner from

the claim. The Arbitrator further found that the petitioner had not submitted

any price lists to demonstrate statutory increase or increase by the

manufacturers, as it was required to in terms of the letter dated 2 nd March,

1990 (supra). Yet another reason given was that even before the Arbitrator,

the price lists were not submitted alongwith the letters under cover of which

they were alleged to have been submitted to the respondent Rites and were

submitted almost one year thereafter. Such non-filing of the relevant price

lists alongwith the letters before the Arbitrator was held to support the

version of the respondent Rites of the price list having not been submitted

under cover of the letters for which they were alleged to have been

submitted. The Arbitrator also held that the price lists were filed before him

only after directions in that regard.

11. The petitioner has objected to the award on the basis of its letter dated

5th June, 1992 to the respondent Rites proved as Ext. C-3 before the

Arbitrator. The petitioner vide the said letter purported to intimate revised

rates for the items and sought approval of the same. The said letter as

"Enclosure" thereto mentioned "two sets of analysis of rates". The

petitioner also places heavy reliance on the letter dated 4th August, 1993 of

the respondent Rites to India Trade Promotion Organization (being the

changed name of TFAI). The respondent Rites vide the said letter supported

the case of the petitioner. It is the case of the petitioner that the said two

letters clearly show that the revised price lists were submitted by the

petitioner as claimed and the finding of the Arbitrator of the petitioner

having not submitted the revised price lists to the respondent Rites is

contrary to the documents on record. Reliance in this regard is placed on:-

(i) K.P. Poulose Vs. State of Kerala (1975) 2 SCC 236 holding

inconsistent findings and decision in ignorance of material documents

to be a misconduct within the meaning of Section 30 of the 1940 Act.

(ii) Food Corporation of India Vs. Chandu Construction (2007) 4

SCC 697 holding that the Arbitrator has to operate within the four

corners of the agreement and if he ignores the specific terms of the

contract, he commits a jurisdictional error on the face of the award

falling within the ambit of legal misconduct which could be corrected

by the Court.

(iii) Sathyanarayana Brothers (P) Ltd. Vs. T.N. Water Supply &

Drainage Board (2004) 5 SCC 314 relying on K.P. Poulose (supra).

12. However, in the present case, it is not as if the Arbitrator has ignored

or disregarded the documents aforesaid forming the basis of the objections

of the petitioner before this Court. The Arbitrator has in para 4.2.7 (ii & iii)

of the award dealt with the said documents. It has been held that the

reference therein is not to escalation in terms of the letter dated 2 nd March,

1990. It has further been held that the said documents do not contain any

admission by the respondent Rites of any price lists having been submitted

by the petitioner.

13. Thus the judgments cited do not apply to the facts of the present case.

The controversy in the present case rather falls within the domain of

appreciation of evidence and construction of documents and which fall

outside the domain of interference in an award. If the courts while

adjudicating objections to the awards start interfering in appreciation of the

evidence by the Arbitrator or in construction of documents by the Arbitrator,

the scope of jurisdiction of interference in awards would be no different

from the scope of jurisdiction in appeals from orders of the Courts of

original jurisdiction.

14. The counsel for the respondent Rites in this regard has relied on:-

(i) U.P. State Electricity Board Vs. Searsole Chemicals Ltd.

(2001) 3 SCC 397 laying down when the Arbitrator has applied his

mind to the pleadings, the evidence adduced and the terms of the

contract, it is beyond the jurisdiction of the Court to reappraise the

matter as in an appeal--where two views are possible, the view taken

by the Arbitrator would prevail.

(ii) Prem Chand Sharma & Company Vs. DDA 127 (2006) DLT

696 laying down that interpretation of a contract is a matter for the

Arbitrator and on which the Court cannot substitute its own decision.

15. There is yet another reason for me to refrain from interfering in the

award on Claim No.2. The letter dated 2nd March, 1990 (supra) forming the

basis of the said claim was written by the petitioner while extending the

validity of its Tender. The condition imposed by the petitioner for such

extension being statutory increase in price or increase in price by the

manufacturers would only have reference to the increase, if any, between the

date, till when the tender was valid and the date till when the validity thereof

had been extended. However, the perusal of the letters claiming increase

proved before the Arbitrator and filed as annexures to the objections show

that the increase claimed was between the date of original validity of the

tender and the "current rate". According to this Court, the petitioner on the

basis of the letter dated 2nd March, 1990 is not entitled to the current rates

and the claim for increase/escalation between the date of acceptance of the

tender and the date of execution of the contract could only be on the basis of

the term in the contract i.e. Clause 10CC, escalation whereunder has already

been received by the petitioner. Though the said reason does not appear to

have been the defence of the respondent Rites or to have been considered by

the Arbitrator but in the opinion of this Court, if for such reason the

petitioner is not entitled to Claim No.2, the award on the said claim even if

for erroneous reasons, cannot be interfered with.

16. Thus I do not find any case of interference with the award on Claim

No.2 to have been made out and the objections to Claim No.2 are dismissed.

17. Claim No.4 of the petitioner for Rs.6,60,000/- was towards

infructuous expenditure and damages sustained in maintaining establishment

and T&P for period of 33 months at the rate of Rs.20,000/- per month. The

sum of Rs.20,000/- was worked out on the basis of salary of Site Engineer,

two Munshis, four Wiremen, 3 Chowkidars, costs of accommodation, T&P

Charges etc. It was further pleaded that as per CPWD procedure, the loss on

account of overheads worked out to be Rs.8,60,454/- and the petitioner was

claiming Rs.6,60,000/- only.

18. The Arbitrator negated the said claim for the reason of the petitioner

having not produced any documentary evidence to prove that the staff and

T&P mentioned in the calculation was in fact deployed at the site and for the

reason that the petitioner had not produced any documentary proof that this

issue was raised during the extended period of work. In the circumstances, it

was also held that the extensions were accepted by the petitioner without any

claim.

19. The petitioner contends that once the Arbitrator concluded that the

delay was attributable to the respondent Rites, the Arbitrator was not

empowered to totally reject the claim and was bound to assess the damages

caused to the petitioner.

20. The counsel for the petitioner also contended that the contract in the

present case does not contain any provision for loss on that account and that

the respondent Rites had not disputed that the petitioner was on the site of

work for the period of the delay. It is contended that no further proof was

required of breach and on which breach damages should have followed.

Reliance in this regard is place on Union of India Vs. V. Pundarikakshudu

& Sons 2003 (3) Arb. LR 168 (SC) to the effect that the Arbitrator cannot

act arbitrarily, irrationally, capriciously and independently of the contract

and on McDermott International Inc. Vs. Burn Standard Co. Ltd. 2006 (2)

Arb. LR 498 (SC) laying down that a claim for overhead costs resulting in

decrease in profit or additional management costs is a claim for damages and

that no invoice was required to be drawn for the same and the amount

therefor not required to be quantified and quantification is a matter of proof.

21. Per contra the counsel for the respondent Rites in this regard also

relies on McDermott International Inc. (supra) to contend that different

formulas can be applied in different circumstances and the question as to

whether damages should be computed by taking recourse to one or the other

formula having regard to the facts and circumstances of a particular case

would eminently fall within the domain of the Arbitrator and that the

Arbitrator may insist on some proof of actual damages and may not allow

the parties to take recourse to one formula or the other.

22. The counsel for the petitioner in rejoinder has contended that the

Arbitrator in the present case having admitted delay on the part of the

petitioner could have adopted either formula and given damages to the

petitioner as per that formula for the admitted delays/breach on the part of

the respondent Rites.

23. The Arbitrator in the present case has declined the Claim No.4 for the

reason of the petitioner having failed to prove that it was deploying man

power and the infrastructure at the site during the period of delay. A mere

breach of contract does not entitle the other party to damage. The breach has

to be accompanied by a loss to the other party and to compensate which

damages are awarded. If the breach is not accompanied by a loss to the other

party, the question of awarding damages or of applying one formula or the

other does not arise. The formulas for computation of damages have evolved

in cases where loss was not in dispute. Where loss owing to breach is in

dispute and/or is controverted and has not been established, the question by

the Court or the Arbitrator awarding any damages does not arise. The

petitioner neither in the objection nor during the hearing has cited any

evidence whatsoever of loss owing to the breach. In the absence of loss,

there can be no damages and there can be no interference with the award.

The petitioner having not established any loss and which is a finding of fact

and interference wherewith, even otherwise in exercise of jurisdiction under

Section 30 & 33 of the Arbitration Act, is very limited.

24. Accordingly, the objections to the award under Claim No.4 are also

rejected.

25. Axiomatically I.A. No.6198/1999 is dismissed. The award is made

Rule of the Court and the decree in terms therewith is passed and be drawn

up. The amounts as per the award having already been paid, need is not felt

to award any interest under Section 29 of the 1940 Act.

No order as to costs.

RAJIV SAHAI ENDLAW (JUDGE) 2nd July, 2010 bs

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter