Citation : 2010 Latest Caselaw 3061 Del
Judgement Date : 2 July, 2010
*IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of decision: 2nd July, 2010.
+ CS(OS)2666-A/1996
%
JEEVAN ENGINEERING WORKS ..... Petitioner
Through: Mr. Shiv Khorana, Advocate.
Versus
UNION OF INDIA ..... Respondent
Through: Mr. R.V. Sinha with Mr. A.S. Singh,
Advocates.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may No
be allowed to see the judgment?
2. To be referred to the reporter or not? No
3. Whether the judgment should be reported No
in the Digest?
RAJIV SAHAI ENDLAW, J.
1. The objections filed by the petitioner vide I.A. No.4766/1997
under Sections 30 and 33 of the Arbitration Act, 1940, upon service of
notice of filing of the award, are for consideration. Disputes arose
between the parties out of a contract placed by the respondent on the
petitioner for supply of six diesel dumpers. It was inter alia a term of
the said contract that if the respondent was not satisfied, after trial of the
two dumpers to be supplied initially, it could foreclose the order for the
remaining four dumpers without any financial liability. The respondent,
prior to the expiry of the period of trial of the first two dumpers supplied,
called upon the petitioner to rectify certain defects found therein.
However, simultaneously the petitioner was also called upon to supply
the remaining four dumpers. It is the case of the respondent that the
petitioner failed to rectify the defects in the first two dumpers and also
failed to supply the remaining four dumpers within the stipulated time.
The petitioner though had dispatched the remaining four dumpers;
according to the respondent though it was not inclined to accept the
delivery of the remaining four dumpers for the reason of the delivery
having been offered after the stipulated period therefor but there being
no procedure of the railways for returning the consignment the delivery
of remaining four dumpers was accepted and the same were rebooked
with the railways to the petitioner. The petitioner however failed to take
the delivery of such four dumpers and the same were ultimately
reconsigned back to the respondent. It is not in dispute that thereafter
the four dumpers remained with the respondent.
2. The petitioner before the arbitrator made a claim of Rs.8043/-
towards the balance 5% price of the first two dumpers and of
Rs.3,21,705/- being the price of the remaining four dumpers, besides for
interest and costs of arbitration. The respondent made a counter claim of
Rs.1,59,625/- for expenses towards repair/rectification of the first two
dumpers which the petitioner had failed to carry out and of
Rs.1,13,406.35p towards the infructuous expenditure incurred in
consignment / re-consignment and freight charges incurred with respect
to the remaining four dumpers, besides for interest and costs.
3. The arbitrator appointed by the respondent has vide award
impugned in this proceeding, though held the petitioner entitled to
Rs.8043/- towards balance 5% price of two dumpers, allowed the same
to be adjusted out of the amount of Rs.1,59,625/- towards expenses on
repairs of the said two dumpers allowed to the respondent. The claim of
the petitioner for price of the remaining four dumpers has been
disallowed for the reason of the petitioner having tendered the delivery
thereof after the expiry of the period stipulated therefor and for the
reason of the petitioner having otherwise failed to perform its duties with
respect to the first two dumpers. The claim of the petitioner for interest
on Rs.8043/- has also been declined. The arbitrator has allowed both the
counter claims of the respondent subject to adjustment of Rs.8043/- as
aforesaid but has rejected the claim of the respondent for interest.
4. The objections to the award have also remained pending before
this Court for long. The usual issues were framed and evidence by
affidavit was ordered to be led thereon, even though the arbitrator's
record has been requisitioned. The counsels for the parties have been
heard.
5. The petitioner has in the objections also pleaded lack of
opportunity of being heard before the arbitrator. However, no arguments
were addressed on that aspect. The counsel for the petitioner during
hearing before this Court has contended that even though it is not in
dispute that the remaining four dumpers were also with the respondent,
the arbitrator has still denied the price thereof to the petitioner. It is also
contended that there was no evidence whatsoever before the arbitrator of
the respondent having incurred expense of Rs.1,59,625/- for repair /
rectification of first two dumpers or of Rs.1,13,406.35p in payment of
freight /consignment/re-consignment of the remaining four dumpers.
The award is also challenged on the ground of being without reasons
though required to be speaking. It is also contended that there was no
delay in delivery of the remaining four dumpers inasmuch as the same
were offered for inspection within the stipulated time. Holes are also
poked in the claim of Rs.1,13,406.35p by contending that for the same
distance, different freights are being claimed. It is also pointed out that
while in the communication dated 12th February, 1992 C-24 in the
arbitrator's record, the respondent has claimed only Rs.17,518/- towards
repairs of the first two dumpers but in the claim before the arbitrator the
amount was inflated to Rs.1,59,625/-. It is also urged that there was no
reason for the arbitrator to decline interest on 5% balance price of the
first two dumpers admittedly found due to the petitioner. It was argued
that the award is without any application of mind and liable to be set
aside.
6. The counsel for the respondent per contra contended that the
respondent is not liable for the price of the remaining four dumpers,
having already rejected the same and there is no error inviting
interference in the award.
7. Though the counsel for the petitioner has along with the written
arguments handed over, annexed a number of judgments but need is not
felt to deal with the same inasmuch as considering the long time which
has elapsed and the amounts involved and for the reasons stated
hereinbelow, and to hopefully put a quietus to the matter it is deemed
expedient to modify the award:
a. The award of Rs.1,59,625/- for repair/rectification of the
first two dumpers i.e. equal to the cost thereof is not found to be in
accordance with law. It defies logic that the price of repair/rectification
would be the same as the cost of the product. If that were to be so, the
respondent, instead of having the goods repaired/rectified ought to have
gone for new goods. It is unbelievable that the respondent would go
ahead with the work of repair/rectification without obtaining estimates
therefor. There is no commercial sense which is expected even from
government in spending the same amount as the cost / price of the goods
on repair/rectification.
b. It being not a dispute that notwithstanding rejection and to
and fro movement of the remaining four dumpers, before the
commencement of arbitration the possession thereof was with the
respondent only. The award does not record and it is not the case of the
respondent that before the arbitrator the respondent offered delivery of
the remaining four dumpers. The remaining four dumpers having
remained in the possession of the respondent and the arbitrator having
not made any award for return thereof to the petitioner, could not have
deprived the petitioner of the price of the said four dumpers.
8. For the aforesaid reasons it is deemed expedient to modify the
award as under:
a. The claim of the respondent of Rs.1,59,625/- for
repair/rectification of the first two dumpers is modified to that of
Rs.17,518/- claimed by the respondent in its communication
dated 12th February, 1992 C-24 in the arbitrator's record. There
being no other evidence before the arbitrator save for the claim
simplicitor, of the respondent of having incurred the remaining
amount, the claim of the respondent for remaining amount over
and above Rs.17,518/- is disallowed. Out of the said sum of
Rs.17,518/-, payable by the petitioner to the respondent, the
petitioner shall adjust Rs.8043/- being the 5% balance price of the
first two dumpers, due from respondent to petitioner.
b. Though the petitioner is found entitled to price of the remaining
four dumpers of Rs.3,21,705/- but subject to adjustment
therefrom of Rs.1,13,406.35p allowed in the award to the
respondent towards freight and cost of consignment/re-
consignment of the remaining four dumpers. In the entirety of
the facts and circumstances, no case for interference with the
award for the sum of Rs.1,13,406.35p in favour of the respondent
is made out. A perusal of the arbitration record does show that the
dispute between the parties with respect to the delivery of the
remaining four dumpers, acceptance of delivery/rejection was a
highly contentious one involving interpretation of
correspondence and the view taken by the arbitrator is not found
to be such which could not be a possible view from the entire
record. The view taken by the arbitrator being a possible view,
interference in exercise of power under Sections 30 and 33 of the
1940 Act is impermissible. The award for the said amount
cannot be said to be perverse or such which is de hors the record.
c. Thus, the respondent is liable to pay a total sum of
Rs.1,98,823.65p to the petitioner as under:
i) Towards cost / price of four dumpers. : Rs.3,21,705/-
ii) Towards 5% balance price / cost of
two dumpers. : Rs.8,043/-
A. Total : Rs. 3,29,748/-
iii) Less repair / rectification cost of two
dumpers. : Rs.17,518/-
iv) Less freight / consignment / reconsignment
cost of four dumpers. : Rs.1,13,406.35p
B. Total : Rs.1,30,924.35p
Balance i.e. A-B : Rs.1,98,823.65p
d. I have also considered the question of interest. The award does
not grant any interest to either party. Considering the nature of
controversy it is not deemed appropriate to grant any interest
while modifying the award, also not in exercise of powers under
Section 29 of the 1940 Act.
9. The award, subject matter of the proceedings, is thus modified as
aforesaid with the direction to the respondent to pay to the petitioner the
sum of Rs.1,98,823.65p within eight weeks herefrom failing which the
same shall incur simple interest at 9% per annum. A decree in terms of
the modified award is also passed. However, the parties are left to bear
their own costs.
RAJIV SAHAI ENDLAW (JUDGE) 2nd July, 2010 M
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!