Citation : 2010 Latest Caselaw 472 Del
Judgement Date : 28 January, 2010
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ FAO(OS) No.459/2008
Siri Ram Syal & Sons (P) Ltd. .....Appellant through
Mr.M.G. Ramachandran &
Mr. Pulkit Aggarwal, Advs.
versus
Ircon International Ltd. & Anr. .....Respondent through
Mr. K.R. Gupta, Ms. Kiran
Dharam & Ms. Shilpa
Bansal, Advs.
% Date of Hearing: January 13, 2010
Date of Decision: January 28, 2010
CORAM:
* HON'BLE MR. JUSTICE VIKRAMAJIT SEN
HON'BLE MR. JUSTICE MANMOHAN SINGH
1. Whether reporters of local papers may be
allowed to see the Judgment? No
2. To be referred to the Reporter or not? Yes
3. Whether the Judgment should be reported
in the Digest? Yes
VIKRAMAJIT SEN, J.
1. This Appeal impugns the Judgment dated 20.8.2008 of the
learned Single Judge, whereby the Arbitral Award in respect of
two of the claims of the Appellant was set aside and the
remaining Award was made the Rule of Court.
2. The brief facts of the dispute are that Respondent No.1,
IRCON International Limited, bagged two contracts for
improvement of roads from Road & Highway Department,
Dhaka („RHD‟ for short). This work was sub-contracted by
IRCON to the Appellant/Siri Ram Syal & Sons (P) Ltd.[SRS] for
part of the total work. After the work was completed,
differences with respect to Claims made under the contract
arose between IRCON and SRS which necessitated resolution
through Arbitration. A Sole Arbitrator was appointed before
whom all the Claims and Counter-Claims were laid and the
learned Arbitrator, after hearing the parties, passed a common
Award in favour of the Appellant on 27.11.1997 under
Arbitration Act, 1940 („The Act‟ for short). Respondent had filed
his Objections under Sections 30 and 33 of the Act essentially
on the ground that the Arbitrator had ignored the method of
assessing claims agreed by the parties and had evolved his own
formula to calculate the Award for escalation in costs items of
contract. As per the Respondent, this method of assessment of
escalation cost was contrary to the mandate of Agreement
between the parties and this warrants intervention of the court
under Sections 30 and 33 of the Act.
3. Vide Order dated 20.8.2008, the learned Single Judge has
set aside the compensation awarded on two Claims of the
Appellant - firstly, the compensation for Claim No.3- viz.
„Payment of Balance Escalation‟ and secondly, the compensation
awarded for Claim No.2 titled - „Work done but not paid‟ under
the Item „Construction of traffic diversions‟.
4. It is the contention of the Appellant that the learned
Single Judge erred in setting aside its Claims awarded by the
Learned Arbitrator in his Award dated 27.11.97 on the ground
that the Learned Arbitrator transgressed his limits by writing a
new contract between the parties. It has been urged by the
learned counsel for the Appellant that the Learned Arbitrator
has not gone against the agreement between the parties and in
fact to do justice and balance the equities a formula to calculate
the escalation was devised by the Arbitrator and the same is not
a transgression of terms of agreement between the parties.
5. As is admitted by both the parties, IRCON had an
escalation clause in its agreement with RHD and as per the
agreement between SRS and IRCON, IRCON was expected to
pay SRS the escalation amount obtained from RHD on back-to-
back basis, after deducting IRCON‟s overheads and profits.
Therefore, the agreement between the adversaries before us did
not have a formula stipulated in the agreement between them
for the calculation of the escalation cost but had agreed that
the same would be mutatis mutandis governed by the formula
by which RHD has paid escalation to IRCON.
6. The essential components in the formula devised in the
agreement between RHD & IRCON are :-
1. A rise or fall in the indexed cost of labour, contractual plans, material and other inputs till a fluctuation of 10% shall not be considered. Thereby meaning that an escalation of price will be considered only when the same goes above 10% of the estimated cost.
2. The price adjustment factor is to be determined by a formula of general type by keeping a fixed coefficient „x‟ representing a non adjustable position in contractual payment. There are other coefficients a,b,c etc. representing estimated proportion of each cost element.
3. Formula of general type is as under:- P= x + a. EL/ELo + b.LL/LLo + c. PL/PLo + d. FU/FUo + e.BI/BIo + f.CE/CEo + g.RS.RSo + h.ST/STo + i.BR/BRo + j.MI/MIo In this EL, LL, PL etc. are current cost indexes and these are to be divided by ELo, LLo, PLo etc, which are bare cost indexes or price corresponding to various elements at a time prior to submission of bids.
7. It is admitted that IRCON received a sum of BDT
519,427,622.54 as escalation, out of which SRS has been paid
BDT 4,10,47,989. In the reasoned Award, the learned Arbitrator,
while dealing with the claims of the two sides, has recorded that
the procedure suggested for calculation of the compensation for
the escalation payable to SRS by both sides was not acceptable.
Thus, preserving the basic essentials of the agreement between
SRS and IRCON, viz. firstly, escalation payment to SRS
should be on back-to-back basis and secondly, escalation should
be on the basis only on inputs of SRS and IRCON are not to be
considered; the learned Arbitrator proceeded on his own
method of calculation of the compensation for escalation.
8. The salient features of the method/formula adopted by the
learned Arbitrator are-
1. The burden of fixed coefficient of 10% to be shared by both parties in proportionate basis.
2. Escalation has been worked out on the basic amount actually paid to SRS by IRCON. This automatically excluded the overheads and profits of IRCON.
3. Payment to SRS to be made in BDT as well as USD in the proportion in which IRCON has received from RDH keeping in view that the payments are to be made back to back to the SRS.
4. No escalation has been permitted where the same is less than 10 percent.
9. The defects pointed out by Arbitrator in procedure
suggested by IRCON, which according to them was in closest
proximity to the formula in the main contract, are that-
1. Burden of the fixed coefficient [(0.1) in all categories of work] has been thrown entirely on SRS.
2. Input weightage of items applicable only to IRCON has also been included as an additional fixed coefficient applicable to SRS.
3. The said manner of calculation is not logical and it deprives the escalation amount.
4. Escalation induces in respect of some categories of work need to be worked out correctly.
10. There is no gainsaying that the Arbitration Tribunal
appointed by the parties is bound by the Agreement between
the parties and an Arbitrator is not permitted to travel beyond
the hedges placed by the clauses of the Agreement. Any
transgression of these boundaries would certainly land an
Arbitral Award in the nebulous territory of unsustainability.
Hon‟ble Supreme Court in the case of Rajasthan State Mines &
Minerals Ltd. -vs- Eastern Engg. Ent., (1999) 9 SCC 283 has laid
perspicuous norms to be followed by Court while dealing with
the objections against an Arbitral Award being beyond the scope
of agreement referring dispute to Arbitration:-
23. It is settled law that the arbitrator is the creature of the contract between the parties and hence if he ignores the specific terms of the contract, it would be a question of jurisdictional error which could be corrected by the court and for that limited purpose agreement is required to be considered. For deciding whether the arbitrator has exceeded his jurisdiction reference to the terms of the contract is a must. It is true that arbitration clause 74 is very widely worded, therefore, the dispute was required to be referred to the arbitrator. Hence, the
award passed by the arbitrator cannot be said to be without jurisdiction but, at the same time, it is apparent that he has exceeded his jurisdiction by ignoring the specific stipulations in the agreement which prohibit entertaining of the claims made by the contractor. In the letter dated 5-2-1985 appointing the sole arbitrator, it has been specifically mentioned that agreement dated 14-5-1981 was executed by and between the parties and that the contractor has raised the claims as mentioned in the letter dated 7-9-1983 which was denied by the Company and at the request of the contractor, the sole arbitrator was appointed to adjudicate the claims made by the contractor vide his letter dated 7-9-1983. This reference to the arbitrator also clearly provides that reference was with regard to the dispute arising between the parties on the basis of the agreement dated 14-5-1981. It nowhere indicates that the arbitrator was empowered to adjudicate any other claims beyond the agreement between the parties. No such issue was referred for adjudication. Even the arbitrator in his interim award has specifically stated that he was appointed to adjudicate the disputes between the parties arising out of the agreement dated 14-5-1981. ...
44. From the resume of the aforesaid decisions, it can be stated that:
(a) It is not open to the court to speculate, where no reasons are given by the arbitrator, as to what impelled the arbitrator to arrive at his conclusion.
(b) It is not open to the court to admit to probe the mental process by which the arbitrator has reached his conclusion where it is not disclosed by the terms of the award.
(c) If the arbitrator has committed a mere error of fact or law in reaching his conclusion on the disputed question submitted for his adjudication then the court cannot interfere.
(d) If no specific question of law is referred, the decision of the arbitrator on that question is not final, however much it may be within his jurisdiction and indeed essential for him to decide the question incidentally. In a case where a specific question of law touching upon the jurisdiction of the arbitrator was referred for the decision of the arbitrator by the parties, then the finding of the arbitrator on the said question between the parties may be binding.
e) In a case of a non-speaking award, the jurisdiction of the court is limited. The award can be set aside if the arbitrator acts beyond his jurisdiction.
(f) To find out whether the arbitrator has travelled beyond his jurisdiction, it would be necessary to consider the agreement between the parties containing the arbitration clause. The arbitrator acting beyond his jurisdiction is a different ground from the error apparent on the face of the award.
(g) In order to determine whether the arbitrator has acted in excess of his jurisdiction what has to be seen is whether the claimant could raise a particular claim before the arbitrator. If there is a specific term in the contract or the law which does not
permit or give the arbitrator the power to decide the dispute raised by the claimant or there is a specific bar in the contract to the raising of the particular claim then the award passed by the arbitrator in respect thereof would be in excess of jurisdiction.
(h) The award made by the arbitrator disregarding the terms of the reference or the arbitration agreement or the terms of the contract would be a jurisdictional error which requires ultimately to be decided by the court. He cannot award an amount which is ruled out or prohibited by the terms of the agreement. Because of a specific bar stipulated by the parties in the agreement, that claim could not be raised. Even if it is raised and referred to arbitration because of a wider arbitration clause such claim amount cannot be awarded as the agreement is binding between the parties and the arbitrator has to adjudicate as per the agreement. This aspect is absolutely made clear in Continental Construction Co. Ltd. (1988) 3 SCC 82 : (1988) 3 SCR 103, by relying upon the following passage from Alopi Parshad v. Union of India AIR 1960 SC 588: (1960) 2 SCR 793 which is to the following effect: "There it was observed that a contract is not frustrated merely because the circumstances in which the contract was made, altered. The Contract Act does not enable a party to a contract to ignore the express covenants thereof, and to claim payment of consideration for performance of the contract at rates different from the stipulated rates, on some vague plea of equity. The parties to an executory
contract are often faced, in the course of carrying it out, with a turn of events which they did not at all anticipate, a wholly abnormal rise or fall in prices, a sudden depreciation of currency, an unexpected obstacle to execution, or the like. There is no general liberty reserved to the courts to absolve a party from liability to perform his part of the contract merely because on account of an uncontemplated turn of events, the performance of the contract may become onerous."
(i) The arbitrator could not act arbitrarily, irrationally, capriciously or independently of the contract. A deliberate departure or conscious disregard of the contract not only manifests the disregard of his authority or misconduct on his part but it may tantamount to mala fide action.
(j) The arbitrator is not a conciliator and cannot ignore the law or misapply it in order to do what he thinks just and reasonable; the arbitrator is a tribunal selected by the parties to decide the disputes according to law.
11. Therefore, as a prerequisite to set aside the claim for
escalation granted in the Arbitration, the learned Single Judge
had to be satisfied that :-
(a) There was a concluded agreement between the parties on the method of calculation of compensation for escalation and,
(b) That the Arbitrator while granting the said compensation has made a departure or manifestly disregarded the method that was agreed upon by the parties.
12. The learned Single Judge, while setting aside the Award,
has returned the findings that the parties had agreed upon a
specific formula for payment of escalation and that application
of any other formula by the Arbitration would defeat the
contract itself. It has been further held that the Arbitrator has
not disclosed his mind regarding the calculation of escalation,
and by applying a formula independent of those suggested by
the parties, had transgressed his limits. With respect, in our
considered opinion, the findings returned by the learned Single
Judge are erroneous. The Clause regarding escalation payment
is admittedly contained in paragraph 9 of the letter of the
Appellant dated 21.12.1988 and the same reads as under:-
"Claims for extra items and escalation payment etc., shall be passed on to us on back to back basis after taking IRCON‟s Overhead & Profit."
13. This Clause does not provide for any formula or method
for calculation of the escalation to be granted to SRS nor does it
stipulate that the escalation has to be calculated only in
accordance with the formula agreed upon between IRCON and
RHD. As already observed earlier, the two stipulations which
conspicuously find mention in the said Clause is that firstly, the
payment by IRCON has to be made on back to back basis and
secondly, that the IRCON‟s expenditure and profits have to be
excluded while granting the same.
14. From the reasoning given by the learned Arbitrator in his
speaking Award, it is manifestly evident that these two
stipulations have been clearly adhered to. The shortcomings of
the formula suggested by both the parties have also been clearly
set-out and the same are plausible. The methodology adopted by
the Arbitrator and the reasons for the same are also clearly
spelt-out in the Award. The division of burden of fixed
coefficient is sound and reasonable; escalation has been
calculated on the amount that was actually paid to SRS by
IRCON as the working coefficient for each element and finding
its ratio in terms of the contribution by SRS was reasonably
considered to be cumbersome and could have led to an
erroneous result. The payment being made in BDT and USD has
been awarded, keeping the „back-to-back‟ rule in mind.
15. Thus, in our view, there is no capricious divergence from
the Agreement which could have led to a manifest illegality in
Award which would be unsustainable by Courts.
16. As regards the Second Claim that was rejected by the
learned Single Judge, we concur with the findings of the learned
Single Judge that the same was on "Excepted matter‟ and
moreso because the Agreement stipulated that SDS could only
raise claims for which IRCON has received payments from RHD
on back-to-back basis. As no claims had been raised on
payments received by IRCON for making diversions of road, the
Arbitration Tribunal erred in granting the same to the
Appellant.
17. The Appeal is partly allowed. The impugned Order in
respect of claim for escalation cost is set aside and the same is
made rule of the Court along with rest of the Award accordingly.
Parties to bear their own costs.
( VIKRAMAJIT SEN )
JUDGE
( MANMOHAN SINGH )
January 28, 2010 JUDGE
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!