Citation : 2010 Latest Caselaw 348 Del
Judgement Date : 21 January, 2010
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP No. 314/2002
21th January, 2010
M/S. VISHAL ENGINEERS & BUILDERS ...Petitioner
Through: Mr. J.P.Gupta, Advocate with Mr. Sohan
Lal, Advocate.
VERSUS
M/S INDIAN OIL CORP. LTD. & ANOTHER
....Respondents
Through: Mr. Abhinav Vasisht, Advocate with Mr.
Raman Kumar, Advocate and Mr. Sumit
Singh, Advocate.
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be allowed to see the judgment?
2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in the Digest?
% JUDGMENT (ORAL) VALMIKI J.MEHTA, J
1. By this petition under Section 34 of the Arbitration and
Conciliation Act, 1996 the petitioner challenges the Award dated 29.6.2002
passed by the sole Arbitrator. The challenge is laid by the objector only to
Claim Nos.1 and 5 as dealt with by the Arbitrator.
2. The disputes which arose between the parties was with regard to a
contract which was awarded to the respondent no.1 (hereinafter referred to as
OMP 314/2002 Page 1 the respondent) for construction of internal roads, earth filling drains and pipe
culverts at L.P.G. Bottling plant, Farrukhabad, U.P.
3. Claim No.1 as awarded by the Arbitrator is with respect to an
indemnity given by the petitioner for any loss which the respondent may suffer
on account of any claim being laid against it by any employee of the petitioner.
An employee of the petitioner on account of an accident happening at site filed
a claim both against the petitioner and the respondent and as a result of which,
the respondent had retained with it an amount of Rs.25,000/- pending the
conclusion of the litigation. In fact, the Arbitrator has awarded that the amount
would be returned to the petitioner in case no liability is fastened on to the
respondent at the conclusion of the legal proceedings filed by the employee of
the petitioner. On a query by the Court to the counsel for the petitioner as to the
present stage of legal proceedings filed by the employee, the counsel for the
petitioner had no answer. The counsel for the respondent states that in case, in
the legal proceedings as filed by the employee of the petitioner no liability is
fastened on to the respondent, it shall return the amount withheld to the
petitioner. The Award also says this. No fault can be found with this part of the
Award and objection to this claim is therefore rejected. At this stage, I may
take on record the statement of the counsel for the respondent that respondent
shall put an amount of Rs.25,000/- in a fixed deposit within a period of one
week from today and if the amount has to be returned to the petitioner the same
OMP 314/2002 Page 2 will be returned alongwith interest which is earned thereon from the fixed
deposit.
4. The second claim, is Claim No.5 pertaining to the issue of
liquidated damages. The respondent had recovered an amount of Rs.4,59,873/-
from the bills of the petitioner towards liquidated damages in terms of the
clause of liquidated damages under the contract. The facts as found while
dealing with Claim No.5 by the Arbitrator are that there has been a delay of 37
weeks in execution of the work. As per the clause of liquidated damages,
damages are payable at the rate of 1% per week delay subject to the maximum
of 10% of the contract value. Meaning thereby, once if 10 weeks are reached
the maximum penalty of liquidated damages can be imposed. In this case, delay
is of 37 weeks. The arbitrator therefore awarded damages for delays caused by
the petitioner. Counsel for the petitioner sought to urge that the finding in this
behalf is faulty and needs to be set aside by this Court. I may note that the
jurisdiction of this Court while hearing objections under Section 34 is indeed
limited. An Arbitrator is entitled to weigh the evidence filed by both the parties
for coming to a conclusion. The Arbitrator has after weighing the respective
evidence of the parties arrived at a conclusion with regard to the delay being
caused by the petitioner. In any case, even a delay of 10 weeks was good
enough for imposing damages which in this case is of 37 weeks and, the
Arbitrator has given findings of fact that the petitioner was guilty of delay in
OMP 314/2002 Page 3 performance of the work, which findings are not shown to this Court to be in
any manner perverse.
5. Mr.J.P. Gupta, counsel for the objector has endeavoured to take me
through various documents to show that the petitioner is not guilty of delay in
performance of the work. Reference in this behalf was made more particularly
to an internal note dated 8.3.1996 of the respondent and the decision given
thereon dated 25.3.97 that penalty should not be levied. Firstly, I am not
entitled to look into those documents which are the internal records of the
respondents and which have not been communicated to the present petitioner.
This has been the consistent view of the Supreme Court right from the case of
Bachhittar Singh Vs. State of Punjab AIR 1963 SC 395 and followed
recently in Sethi Auto Services Vs. DDA 2009(1) SCC 180. Admittedly, this
note has not been communicated to the petitioner, and nor is it so the case of the
petitioner. On the contrary, the learned counsel for the respondent has drawn
my attention to the fact that the counsel for the petitioner is only stating half
facts because ultimately this very note, when it was put up before the final
authority ,the same note and the recommendation of extension of time was
rejected. This rejection of recommendation as made in the note dated 25.3.1997
appears at running page 648 of the Arbitration record.
In my opinion, firstly the internal documents cannot be looked
into, and in any case if it is looked into, shows that there is no recommendation
for extension of time period without levy of liquidated damages.
OMP 314/2002 Page 4
6. Once again, I reiterate that this Court does not sit as an Appellate
Court over the findings of the Arbitrator. Merely, because two views are
possible, this Court cannot interfere with the findings in the Award merely
because it is of another view, and the Arbitrator has held another plausible view.
As already stated, Arbitrator has held one plausible view from reading of the
various documents filed before him of the petitioner being guilty of delay in
execution of the works. This aspect as I have already stated is further
strengthened because the maximum liquidated damages becomes payable after
10 weeks of delay and here the delay is admittedly of 37 weeks.
7. Mr. Gupta also sought to contend that the damages under Section
74 of the Contract Act, 1872 i.e. the liquidated damages imposed could not
have been levied before issuing any notice to the petitioner i.e. the requirement
of Article 14 of compliance of principles of natural justice. Firstly, I do not find
in the arbitration record that any such objection was taken. Even assuming, if
such objection is taken, this objection is misconceived because parties are
governed in their affairs by the Contract Act and the elements of public law
field cannot be brought in the disputes of a private contractual nature. This has
been held by the Supreme Court in the judgment of Assistant Excise
Commissioner Vs. Issac Peters (1994)4 SCC 104 and which has been recently
followed by the Supreme Court in S.K. Jain Vs. State of Haryana (2009)4 SCC
357. This contention of Mr. Gupta is therefore rejected because public law
elements cannot be brought into private law field.
OMP 314/2002 Page 5
8. It was lastly contended by Mr. Gupta that the note dated 25.3.1997
and preceded by the note dated 8.3.1996 say that no loss has been caused to the
respondent. I have already dealt with the issue that these are internal notes of
the respondents and which were not communicated to the petitioner and hence
cannot be relied upon by the petitioner. Additionally, as already noted above,
recommendation in the note was ultimately rejected. In any case, in my
opinion, the issue is covered by the recent decision of the Supreme Court in
ONGC Vs. Saw Pipes (2003) 5 SCC 705 that in certain contracts loss actually
need not to be proved because loss is not capable of being proved. The
Supreme Court in the case of Saw Pipes's (supra) in paragraphs 46, 66 and 67
has held that in certain contracts such as construction of road or making of an
refinery, actual losses can never be calculated. Accordingly, the Supreme Court
has said that the liquidated damages automatically become payable. If that be
so, in a case of this type which is for construction of the nature already
mentioned, in my opinion, it is not necessary that actually losses have to be
proved by the respondents before enforcing the clause of liquidated damages.
9. In view of the above, the objections are dismissed with costs of
Rs.25,000/-.
VALMIKI J.MEHTA, J
January 21, 2010
Ne
OMP 314/2002 Page 6
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!