Citation : 2010 Latest Caselaw 254 Del
Judgement Date : 19 January, 2010
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP No. 127/2002
19th January, 2010
SHRI DHEERAJ SINGH ...Petitioner
Through: Mr. Rajiv Kapoor, Advocate
VERSUS
GOVT. OF NCT OF DELHI ....Respondent
Through: Mr. V.K.Tandon, Advocate CORAM: HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be allowed to see the judgment?
2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in the Digest?
% JUDGMENT (ORAL) VALMIKI J.MEHTA, J
1. By this petition the petitioner is challenging the impugned Award dated
16.01.2002 passed by the sole Arbitrator.
2. In my opinion the Award is liable to be set aside inter alia, for the
following reasons:-
(i) There are contradictory findings and conclusions in the Award.
OMP 127/2002 Page 1 (ii) The Award fails to give germane reasons, which reasons in law, are a sine
qua non, under Section 31of the Arbitration and Conciliation Act 1996 for a
valid Award. (See Jai Singh Vs. DDA, 2008(9) AD(Delhi 453).
(iii) The Award is illegal.
(iv) The perversity in the Award is such that the judicial conscience of this
court requires the setting aside of the Award.
3. The Award was passed on account of disputes which arose between the
parties whereby the petitioner was awarded the work of construction of bridge
across N.G.Drain from crossing water mains at RD-79600 m & RD-20673
respectively. There were delays in the performance of the contract and
ultimately the contract was rescinded by the respondent. Claims and Counter-
Claims, were filed by the parties before the Arbitrator. The claims of the
petitioner pertained to the work done, escalation, refund of the security deposit
and illegality of rescission of the contract etc. The counter-claims of the
respondent pertained to, inter alia, cost of awarding of risk purchase tender,
forfeiture of the security deposit and levy of compensation.
4. The counsel for the petitioner has pressed his objections with regard to
setting aside of the entire Award and all the claims/counter-claims decided.
5. So far as Claim No.1 is concerned, since the Award shows the admitted
position that an amount of Rs. 47,216/- is payable, the objections in this regard
are not sustainable and thus this part of the Award is not liable to be set aside.
OMP 127/2002 Page 2
6. Claim No.2 was the claim for refund of the security deposit. This claim
can be dealt with along with the Counter-Claim no.1 which is with respect to
forfeiture of the same security deposit. The Arbitrator has allowed the
respondent to forfeit the security deposit on account of the counter-claim of the
respondent on the same subject matter, by holding that the respondent was
justified in rescinding the contract.
Since the decision on the issue of forfeiture of the security deposit is also
related to Claim no.5 with regard to the entitlement to rescission of the contract
by the respondent, I am also taking up the said claim along with this
claim/counter-claim of forfeiture of the security deposit.
7. On the aspect whether the respondent was entitled to rescind the contract,
I note that this was a case where time of performance was not the essence of the
contract and nor was it so treated in view of the extensions granted by the
respondents. In terms of the decision of the Supreme Court reported as Hind
Construction Contractors Vs. State of Maharashtra AIR 1979 SC 720, once
the time of performance is not the essence, it was necessary for the respondent
first to make time, the essence of the contract before rescinding the contract.
There is no discussion on this aspect, in this part of the Award. The issue with
regard to the rescission of contract and the related issue of forfeiture of the
security deposit therefore is remanded back to the Arbitrator for a fresh decision
to be made after considering all the relevant aspects.
OMP 127/2002 Page 3
8. Claim No.3 was with regard to the entitlement of the contractor for
escalation under Clause 10CC. I find that the Arbitrator has awarded a sum of
Rs.5173/-, but, I find that this is only a conclusion and how is this figure arrived
at instead of the figure as claimed by the petitioner are not very clear. It is
therefore, desirable that this claim be also remanded back to the Arbitrator to
give appropriate reasons and findings for arriving at the figure of Rs.5173/-
which has been awarded and whether this figure ought to be awarded or any
other figure on a fresh consideration of the matter by the Arbitrator.
9. So far as challenge to Claim No.4 is concerned, I do not find any
substance in the challenge because the Arbitrator has examined the factual
position with respect to the making of the „bandi‟ and has held that the amount
already paid to the petitioner of Rs.42,000/- will serve the purpose. Before
giving this conclusion, the Arbitrator has given the following findings and
which cannot be faulted with:-
"I have carefully gone through the submission of both parties & documents submitted and find that the respondents reasoning is correct. There is not much change in slope or depth of drain from RD 30673 to RD 30775 and such extra bundi construction, its restoration and pumping of water was not required. As there is not much flow, normally water is diverted to other side by digging a drain, no pumping is required and cofferdam is made by earthwork. The calculation submitted by claimants are contradictory to size, length and also pumping out water from pound size 95 mx75mx17m, restoration of 192 m length and new cofferdam construction of 74 m only. Contractor himself has agreed in letter dated 21.10.1993 exhibit C-4 of original claims that rains has damaged bundi and as per special condition 12 of agreement at page 121 of agreement, nothing extra is payable for damage/extra work because of rain."
OMP 127/2002 Page 4
10. Counter-Claim Nos .2,5 and one counter claim titled as "another counter-
claim" (last page of the Award) can all be dealt with together. These counter-
claims have been dismissed by the Arbitrator by holding that the same are not
arbitrable and also holding that no actual expenditure and loss has been proved
by the respondent.
I note from the dealing of these counter-claims, that what is the reason ,
why the claims have been held to be non arbitrable, is not clear. The Award
must contain not only the conclusion but also the findings and reasons, on the
basis of which the conclusion is arrived at. While dealing with Counter-Claim
no.2, the Arbitrator records that the new bridge which has to be constructed is
on a different alignment at a different site, however, what would be the
consequential effect thereof, has not been discussed. What is most perplexing
in the Award is the dealing in the Award with respect to the counter-claim titled
as "another counter claim". This part of the Award, in my opinion, is totally
bereft of any logic. To understand this complete lack of logic, it would be
necessary for me to reproduce how this counter-claim has been dealt with. This
relevant portion of the Award reads as under:-
"Another counter claim It arises during proceeding was that the respondents should be permitted to adjust the recoveries dues on accounts of compensation levied under clause-2 of agreement and recoveries of risk & cost of Rs.1108846/26 (Which was non-arbitrable) against the amount of award if any due to contractor. Respondents submitted that as per normal practice in the ordinary dealing, they will adjust the recoveries & release the balance amount.
OMP 127/2002 Page 5
Award Claimants submitted that the no recoveries can be
adjusted against the awarded amount. That is needed to be released in full. If any claims are recoverable from claimants, respondents need to file a separate suit for that under law of land. No recoveries should be adjusted against the amount of award.
Our careful consideration of submission of both sides during hearing and reading of clause-29 (1) & 29 (A) of contract, undersigned finds that this point also needed to be settled by Arbitrator.
Hence, I award, that the claims for recoveries of Rs.209580/- (Towards compensation levied under clause-2 of contractor) and Rs.1108846/26 including Rs.1 lacs security deposit forfeited by the respondents is (Towards recoveries for balance work done under clause-3 of contract) may be adjusted from the award so given."
From the aforesaid discussion in the Award, certain things which
become clear are that, after dismissal of the counter-claims of the risk purchase
cost and other related claims, still the Arbitrator has, without any reasoning,
awarded a sum of Rs.11,08,846.26p. to the respondent. The effect of this is that
after dismissing effectively the counter-claims, the same is in fact surprisingly
allowed for this amount of Rs.11,08,846.26 and the awarding of such counter-
claim is without any discussion whatsoever of the entitlement, basis and reasons
which justify the grant of an Award for the said sum. What is further
inexplicable is that how has the Arbitrator arrived at a figure of Rs.2,09,580/-
which has been finally awarded to the present petitioner. Still further, it is
totally inexplicable as to how the Arbitrator has finally awarded the respondent
a sum of Rs.52,389/-, I am totally confused in fact as to how at all these
separate figures namely Rs.11,08,846.26/-, Rs. 2,09,580/- and Rs.52,389/-
OMP 127/2002 Page 6 can be reconciled. It is therefore best that this Award is remanded back to the
Arbitrator to again pass a fresh Award by giving proper findings and
appropriate reasons to support the conclusions as regards Counter-Claim Nos. 2
& 5, as also the Counter-Claim titled as "another counter-claim".
11. So far as the rate of interest is concerned, I find that the Arbitrator has
awarded the same at 12% per annum while dealing with Claim No.6. In my
opinion even the rate of interest awarded is higher than what ought to have been
at 9% per annum simple. In view of the recent pronouncements of the Supreme
Court in the judgments reported as Rajendra Construction Co. Vs.
Maharashtra Housing & Area Development Authority & ors.2005 (6) 678,
McDermott International Inc. Vs. Burn Standard Co. Ltd.& ors 2006 (11)
SCC 181, Rajasthan State Road Transport Corpn. Vs. Indag Rubber Ltd.
(2006) 7 SCC 700 and Krishna Bhagya Jala Nigam Ltd. Vs. G.Harischandra,
2007 (2) SCC 720 and State of Rajasthan vs. Ferro Concrete Construction
Pvt. Ltd (2009) 3 Arb. LR 140(SC). The award of interest @ 12% is set aside. I
am not directing the Arbitrator to award a particular interest but, I am setting
aside this claim and directing the Arbitrator to award interest lesser than 12%
and in accordance with the aforesaid judgments of the Supreme Court.
Accordingly, except so far as Claim Nos. 1 and 4 which are sustained, the rest
of the Award is set aside and is remanded back to the Arbitrator for
reconsideration of the other claims and counter-claims and passing a fresh
Award in accordance with law with regard thereto.
OMP 127/2002 Page 7
12. I may note that in view of the apparent shortcomings and illegalities in
the Award, its lack of reasons and findings, the counsel for the respondent after
making the endeavour to argue realised the futility, and in all fairness
thereafter, has not very vehemently objected to the issue of remission.
13. The Award is therefore sustained so far as Claim Nos.1 and 4 are
concerned. The Award is set aside qua the Claim Nos.2,3, issue of rescission,
counter-claim Nos.2,4 and 5 and the one titled as "another counter claim" and
the matter is remitted back to the Arbitrator qua these claims and counter-
claims. The Arbitration record in this court be returned back to the counsel for
the respondent for being returned to the Arbitrator so that a fresh Award, in
accordance with law, can be passed in terms of the present judgment. Parties
are left to bear their own costs.
VALMIKI J.MEHTA, J
January 19, 2010
ib
OMP 127/2002 Page 8
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!