Citation : 2010 Latest Caselaw 172 Del
Judgement Date : 14 January, 2010
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP No. 138/2006
14th January, 2010
M/S NATIONAL HIGHWAY AUTHORITY OF INDIA ...Petitioner
Through: Mr. Sandeep Sethi, Sr. Advocate with
Ms. Padma Priya, Advocate.
VERSUS
ITALIAN THAI DEVELOPMENT PUBLIC COMPANY LTD. ....Respondent
Through: Mr. V.A.Mohta, Sr. Advocate, Mr. S.B.
Upadhayay, Sr. Advocate, Mr. Arvind Minocha & Mr. Neelkanth Mohta, Advocates.
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be allowed to see the judgment?
2. To be referred to the Reporter or not? yes
3. Whether the judgment should be reported in the Digest? yes
% JUDGMENT (ORAL)
VALMIKI J.MEHTA, J
1. This is a petition under Section 34 of the Arbitration and Conciliation
Act, 1996 which challenges the Award with respect to Claim Nos. 1 and 2 as
dealt with in the Award. Under these claims, certain amounts have been
awarded to the respondent herein.
2. So far as Claim No.2 is concerned, in my opinion, and for the reasons
stated hereinafter, there cannot be any challenge successfully laid to the findings OMP 138/2006 Page 1 and conclusions of the Arbitrators. The issue so far as Claim No.2 is concerned,
the same was, with respect to an item of work being a particular type of
drainage layer, which work is admittedly not provided under the Contract. The
Agreement in question vide Clause 52.1 requires that if the item of work done,
is not provided for under the contract, then, in such a case, if there is a similar
item in the contract, then, endeavour shall be made to make the payment for the
extra item of work done on the basis of the rate provided for the similar item in
the contract.
3. In the present case, in the Bill of Quantities (BOQ) of the subject
contract, qua the head Bill No.3, there is provided the following two entries:-
Bill of Quantities (Package-IIA)
Item Description Unit Quantity Unit Rate (Rs.) Amount (in Rs.) In words in figures In words In figures
Bill No.3 - SHOULDER, SUB-BASE & BASE COURSE 3.01 Providing and Cu.m. 140005 Five Hundred 590.00 Eighty-Two 82,602,950.00 Constructing granular and Ninety Million, and sub-base complete as per Rupees Six Hundred Technical Specification and Two Clause No.401, grading- Thousand, and 1 of Table 400-1 Nine Hundred and Fifty Rupees 3.03 Constructing drainage Cu.m. 212510 One Thousand, 1,60,00 Two Hundred 246,511,600.00 layer (granular sub base and One and Forty-Six course) below rigid Hundred and Million, and pavement as per drawing Sixty Rupees Five Hundred and technical and Eleven specification clause 401 Thousand, and Six Hundred Rupees
OMP 138/2006 Page 2
4. The Arbitral Tribunal has found that the item of work in question
executed by the respondent is similar to item 3.03, as stated above, and has
awarded the rate for such work at Rs.1160 per cubic meter and which is the rate
provided for work done under item 3.03. Before so doing, the Arbitral Tribunal
has considered various factors which increased and also decreased the cost of
execution of the work to the contractor, when executing this item. Some
relevant paragraphs of the Award in this regard are as under:-
"3.2.4 The AT has further observed that as per Analysis of Rate (A/R) submitted by the Claimants vide letter dated 18.3.2002 (Exh.C-23) they have claimed the rate of the varied item as Rs.1400 per cum which is higher than the rate for BOQ item 3.03, due to higher density involving additional transportation and compaction cost. However, the AT is of the view that since the aggregate size covers a broader range varying from 75 mm downwards, against the earlier size of 20mm downwards, there are some savings in the cost of procurement and as such the rate should be restricted to that of BOQ item 3.03, as initially decided by the Engineer's Representative under the power delegated to him and accepted by the Claimants.
3.2.5. The subsequent A/R for Rs.891per cum, derived by the Engineer from PWD Schedule of Rates has also been examined by the AT carefully and after considering the comments of both parties, the AT is of the view that due to increased density of modified drainage layer with changed grading, the rate works out to Rs.1170.36 per cum., as per A/R attached at Annexure 1, which is based on the A/R prepared by the Engineer."
5. It is not in issue that the item of work in the present case is with respect
to making of a drainage layer below the rigid pavement. Item 3.03 of the Bill of
Quantities reproduced above, in my opinion has rightly been relied upon by the
Tribunal because the language of the said Clause shows that it is surely similar
to the new work executed by the contractor instead of the work falling under
Clause 3.01, and therefore, the rate provided for the item 3.03 has to be adopted
by virtue of Clause 52.1 of the Contract. Mr. Sandeep Sethi, Sr. Advocate , for
OMP 138/2006 Page 3 the petitioner ,sought to urge that item 3.01 of the Bill of Quantities applies and
not item 3.03. This was so urged on the basis that there is commonality of the
ingredient of " granular sub-base" in both the items 3.01 and 3.03. I do not
agree with this contention because it is not the content of the item which is
material but the head of the item and its similarity with the head of the item
which is executed by the contractor, which is relevant, because there are many
items which may have common material for doing the works.
Even assuming that there are two views possible, as to whether item 3.01
applies or item 3.03 applies, it is settled law that until and unless, the course of
action and interpretation adopted by the Arbitrator, is wholly perverse, or so
unreasonable that only an unreasonable man could have taken such a view, this
Court while hearing objections under Section 34 will not interfere with the
plausible interpretation as given by the Arbitrators. Since, although in my
opinion, a reading of Clause 52.1 necessarily shows that the conclusion of the
Arbitrator is correct, in the alternative I feel that, since two views are possible,
assuming the view as canvassed by the petitioner, is one of the possible view,
then also, I refuse to exercise discretion in allowing the objection as regards
awarding of this claim.
6. The second claim which has been awarded by the Arbitral Tribunal, and
which has been challenged before this Court, is as regards Claim No.1. Before I
discuss the conclusions in the Award, as regards this claim, it would be
OMP 138/2006 Page 4 necessary to reproduce certain relevant clauses of the contract. The relevant
clauses of the contract in this regard are as under;-
"Section 200 CLEARING AND GRUBBING
Clause 201.1 Scope
Replace with following para
This work shall consist of cutting removing and disposing of all materials such as trees of girth up to 300 mm, bushes, shrubs, stumps, roots, weeds etc. and top soil 150mm minimum thickness, rubbish etc, which in the opinion of Engineer is unsuitable for incorporation in the work including draining out stagnant water if any from the area of road land, drain, cross drainage structure and other area as specified in the drawing by Engineer. It shall include necessary excavation by harrow discs or any other suitable equipment, back filling of the pits, by suitable soil, resulting from uprooting of trees & stumps and making the surface in proper grade by suitable equipment and compacted by power roller to required compaction as per Clause 300. The work also includes handling salvaging and disposing of cleared material. Clearing and grubbing shall be performed in advance of earthwork operation and in accordance with requirement of these specification. (Emphasis supplied)
"Clause 201.6.1 The contract unit rates for the various items of clearing and grubbing shall be payment in full for carrying out the required operations including full compensation for all labour, materials, tools equipment and incidentals necessary to complete the work. These will also include removal of stumps of trees less than 300 mm in girth as well as stumps left over after cutting of trees carried out by another agency, excavation and back-filling of required density, where necessary, had handling, salvaging, piling and disposing of the cleared materials with all lifts and upto a lead of 1000m."
"Clause 201.6.1 Delete "as well as stumps left over after cutting of trees carried out by another agency" from the second sentence. Add the following paragraph:
"The removal from site and disposal of all materials obtained from clearing and grubbing operations, which, in the opinion of the Engineer, cannot be used or auctioned, shall be included in the Contract unit rate."
7. The issue in the Arbitration proceedings, as regards this claim was of the
payment for the work of earth filling for levelling or back filling of the pits
OMP 138/2006 Page 5 which is required as a result of the work done of clearing and grubbing in terms
of Clause 201.1 and 201.6.1 A conjoint reading of relevant clauses brings out
the following salient ingredients contained therein:-
(i) In the job of clearing and grubbing, the contractor has to cut and remove
such materials and vegetation growth (including trees). The contractor has also
to remove top soil of 150mm thickness, if so directed by the Engineer when the
Engineer finds that such removal was necessary as surface was not of proper
grade.
(ii) The work as stated in point (i) above with respect to clearing of the top
soil is only required to be done for making the surface in proper grade, meaning
thereby, if the surface is otherwise in a proper grade, there is no requirement of
removing of 150mm of top soil and in which circumstance no directions are
issued by the Engineer to remove the top soil.
(iii) If as a result of removal of the trees, shrubs etc., there are caused pits, the
cost of work of back filling of the pits, is to the account of the contractor.
(iv) To the extent of removal of the top soil of 150mm, when so required in
terms of the requirement of Clause 201.1 , it is open to the contractor to use
such material for back filling of the pits, and in fact is bound to do so.
(v) It is nowhere provided in the contract that if earth is removed up to
150mm, the same cannot be used for back filling of the pits caused by removal
of the stumps of the trees or other vegetation. This becomes further clear from
the paragraph added to Clause 201.1 because it is only such material which
OMP 138/2006 Page 6 cannot otherwise be used has to be removed from the site but the rest has to be
incorporated in the work at site and which material when used will fall within
the unit rate of that subject item under the contract of clearing and grubbing.
8. Not much dispute with regard to these ingredients of the aforesaid clauses
could be raised by the counsel for the parties inasmuch as the aforesaid
interpretation of the clauses, in the opinion of this Court, is a correct
interpretation on the conjoint reading of the relevant clauses. The disputes
however in this case was more factual in nature than as regards the
interpretation of the clauses. The dispute was that, whether the contractor had
unnecessarily scraped the soil up to 150mm even if it was not required and
directed and if scraping and clearing up to 150 mm depth was required,
whether the contractor, in fact, in the work area went to depth in fact even
below 150 mm. On the one hand the stand of the present petitioner, respondent
in the Arbitration, was that unnecessary scraping or going to a greater depth
than 150 mm was in fact done by the respondent/contractor, however, the
respondent has very empathically denied such a charge and has stated that the
back filling of the pits caused on account of uprooting of the trees stumps etc.
was not on account of use of such soil from the work area which it could not
have validly done in terms of aforesaid provisions of the contract.
9. On reading the relevant portion of the Award, which is contained at
internal pages 14 to 17 of the Award, I find that there is no specific discussion
as to whether the soil which is used for back filling of the pits and levelling is in
OMP 138/2006 Page 7 fact the soil below the depth of 150 mm or even if up to the depth of 150 mm if
such soil was not such soil which was required to be cleared as per directions of
the Engineer while performing the obligations by the contractor under Clause
201.1. I find that the Arbitration Tribunal has, while awarding this claim to the
respondent, proceeded on the basis that the soil used for back filling of the pits
is in fact the soil which was validly available to the respondent while
performing his obligations under Clause 201.1. In my opinion, there cannot be
any assumptions or an accepted hypothesis in a case like this which requires in
fact a factual foundation and finding by the Arbitrators with regard to the fact
that whether or not the soil which has been used by the respondent for back
filling of the pits was the soil which was otherwise validly available, i.e. "extra
soil" while otherwise performing the obligations under Clause 201.1 of the
Contractor.
10. In view of the aforesaid position emerging from the interpretation of the
clauses, and the conclusions/findings in the Award which are clearly inadequate
for deciding this issue, the counsel for both the parties have agreed that only so
far as this Claim No.1 is concerned, the same be remanded back to the
Arbitrator to pass a fresh Award keeping in view the interpretation of the
Clauses as already given by me above and more importantly, firstly for arriving
at a factual finding as to whether the soil used for back filling of the pits was
extra soil available to the respondent from the work area was or was in fact such
OMP 138/2006 Page 8 soil which it could not have used and also as per the observations in para 8
above.
11. Accordingly, this matter is remanded back to the Arbitration Tribunal for
deciding afresh, in accordance with law, the Claim no.1. So far as Claim No.2
is concerned, objections thereto are dismissed with costs of Rs.50,000/-.
VALMIKI J.MEHTA, J
January 14, 2010
ib
OMP 138/2006 Page 9
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!