Citation : 2010 Latest Caselaw 13 Del
Judgement Date : 6 January, 2010
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP No. 389/2001
6th January, 2010
M/S AUTOMOBILE CORPORATION OF GOA LTD. ...Petitioner
Through: Ms. Surekha Raman, Advocate
VERSUS
M/S DELHI TRANSPORT CORPORATION ....Respondent
Through:
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be allowed to see the judgment?
2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in the Digest?
% JUDGMENT (ORAL) VALMIKI J.MEHTA, J
1. This is a petition under Section 34 of the Arbitration and Conciliation
Act, 1996, whereby the petitioner, who had agreed to supply and fix bus bodies
to the respondent, on the chassis supplied by the latter, is challenging the
Award dated 11.8.2001 of the sole Arbitrator.
2. I would take up the arguments qua each claim which has been very ably
urged by the counsel for the petitioner.
OMP 389/2001 Page 1
3. At the outset, the counsel for the petitioner has urged that the Award
decides issues which are beyond the scope of reference. I note that no such
objection was taken by the present petitioner before the Arbitrator that disputes
are beyond the scope of reference and hence cannot be arbitrated upon. In the
case titled as M/s Deconar Services Pvt. Ltd. Vs. National Thermal Power
Corporation being OMP No. 262/2000 decided on 16.12.2009, I have had an
occasion to consider two aspects which squarely applies to this case. The first
aspect is that an issue which has not been raised before the Arbitrator cannot be
raised for the first time before the Court. The second aspect, I have dealt with is
that as per the judgment of the Supreme Court reported as Inder Sain Mittal Vs.
Housing Board Haryana (2002)3SCC 175 once a person appears in the
arbitration proceedings and takes a chance of Award going in his favour, then,
he cannot turn around and raise an objection as to the jurisdiction of the
Arbitrator, once the Award is passed against him. Accordingly, on both these
counts I am unable to agree with the objection raised by the counsel for the
petitioner that the Award is beyond the scope of reference.
4. The first issue which has been urged pertains to Claim No.8. The issue
before the Arbitrator and the claim accordingly filed was that the
claimant/respondent was not entitled to the loose items of the bus chassis, and
which chassis was provided by the respondent to the petitioner after fitment
thereon of the bus bodies. Clause 14 of the contract dated 4.6.1998 in this
regard is relevant and the same reads as under:-
OMP 389/2001 Page 2 "The Contractor will have to return back the loose items/fitment supplied/provided on the chassis but not used in the fabrication of bus bodies to the Corporation alongwith the completed vehicles."
In view of Clause 14, it is therefore beyond any cavil that the loose items
of the chassis in fact belonged to the respondent and not to the petitioner. It is
not an issue that such loose items or chassis were not returned by the petitioner
to the respondent. These parts are of a huge amount of Rs.67,33,881/-. I see no
reason to interfere with the Award of the Arbitrator by which he has awarded
such an amount in case the petitioner does not return the necessary items within
15 days of the date of the issue of the Award. It is also not disputed that these
items have not been returned to the respondent within 15 days after passing of
the Award. The counsel for the petitioner has very strenuously urged that after
the contract dated 4.6.1998 was entered into between the parties, and which was
signed by both the parties, and pursuant to which the present petitioner acted in
terms thereof, the petitioner appears to have written certain letters whereby the
petitioner claimed that this Clause 14 was not found in the earlier contract dated
6.4.1998 and therefore, the petitioner should not be bound by the Clause 14.
This argument is, merely stated to be rejected, because once a contract, which is
a bilateral act, is entered into, then, no party, by an unilateral act can seek to,
alter the agreed terms and conditions of the contract. The only way in which a
bilateral contract can be altered is by an agreed novation of the same, and, I do
not find that there is any agreed novation, and nor is that the case of the counsel
OMP 389/2001 Page 3 for the petitioner, and which merely is, as stated above, that by writing letters,
the aforesaid Clause 14 would not apply. If I accept the contention of the
counsel for the petitioner, then, sanctity and solemnity of the final contractual
document can be whittled down by an unilateral act of writing of letters by a
party and surely which is not the legal position. Accordingly, I do not find any
merit with respect to the challenge to Claim No.8.
5. The next objection which has been taken up was with respect to grant of
liquidated damages under Claim No.1 to the respondent by the Arbitrator. The
liquidated damages have been granted at Rs.400 per bus per day. The counsel
for the petitioner canvassed that as per para 11 (ii) of the terms and conditions
of the tender, it is the date of inspection which is a date of delivery and since
inspections have been done before the scheduled/prescribed dates under the
contract therefore it should be held that there is no delay in the supply by the
petitioner to the respondent. The said clause relied upon by the counsel for the
petitioner reads as under:-
"ii) For the purpose of this clause delivery of the completed bus shall be treated as having been effected on the date on which the inspection is carried out. The mere fact that the buses may be made ready for inspection shall not be considered as completion of delivery unless delay in arranging inspection is caused by the Corporation."
Once again a reference to the written statement filed by the
petitioner before the Arbitrator does not show that such an objection in this
manner has been taken before the Arbitrator that merely on inspection, the
OMP 389/2001 Page 4 delivery stands completed. Even assuming this to be so, this argument has no
legs to stand upon because this clause is with reference to the subject matter that
if the respondent delayed inspection, then, delay in delivery should not be
attributable to the petitioner. This is clear from a reading of the complete
paragraph in question. In any case, it is not the stand of the petitioner that
actual deliveries were made to the respondent before the prescribed/scheduled
dates as per para iii (running page 10) of the contract by which the buses were
to be delivered in lots every 30 days and the last lot in the fortnight after the
penultimate delivery. I may state that though the counsel for the petitioner
obviously did not refer to Clause 11, this clause of the contract is indeed
relevant because it prescribes that both delivery and inspection have to be at
Delhi and not at Goa as was sought to be contended by the counsel for the
petitioner. The aforesaid para 11 of the Contract dated 4.6.1998 reads as
under:-
"11. The final inspection of the completed bus body/bodies be done at Delhi before effecting delivery of the completed vehicle at Central Workshop-1, of the Corporation at B.B.Marg, Delhi-9. In case, any defects/deficiencies/discrepancies are observed after the receipt of vehicle at DTC Delhi, the same shall be removed by DTC at your cost without giving any notice."
In any case, the Arbitrator is the final fact finding authority and I
do not find any perversity whatsoever in the approach of the Arbitrator for this
court to interfere within the parameters of the law under Section 34. Though,
only the view as taken by the Arbitrator is correct that the deliveries were not
OMP 389/2001 Page 5 done by the prescribed dates and hence liquidated damages were payable, even
assuming for the sake of argument, if I accept the contention of the counsel for
the petitioner, yet the objections have to fail, because, the Arbitrator can take
one plausible view, and which if done, the court is not entitled to interfere
with the Award merely because an alternate view can also be canvassed.
Therefore objection with respect to Claim no.1 is also accordingly rejected.
6. Claim Nos. 2 and 3 awarded by the Arbitrator are basically towards
defects and deficiencies in the bus bodies supplied by the petitioner. The
Arbitrator has arrived at a finding of fact that there were defects and
deficiencies. This finding of fact has been arrived at by the Arbitrator by
noticing that the defects and deficiencies were observed at the time of final
inspection carried out in the presence of the representatives of the present
petitioner. The Arbitrator has also referred to relevant reports which have been
countersigned by the representatives of the present petitioner and which show
the agreed defects observed by the inspecting team. Further, the Arbitrator has
referred to the various test reports of a Government Lab.Test House and the
bills for payment with respect to getting the material tested and also for the
replacement of the substandard material used in the bus bodies fabricated by the
present petitioner. The Arbitrator has therefore, allowed 50/70% of the amount
as claimed by the respondent.
I may note that the Arbitrator has for no apparent reason reduced the total
claim by 30/50%, which logic is not understood, however, since there are no
OMP 389/2001 Page 6 objections filed by the respondent, the Award in this regard has to stand. While
so observing, I may also note that even with respect to Claim No.1 where
liquidated damages have been awarded by the Arbitrator, he has only awarded
50% of the liquidated damages without giving any reasoning. Once again since
there are no objections by the respondent to the Award, this Court can do
nothing except sustaining the Award with respect to 50% of the amount
awarded.
Accordingly, there cannot be any valid basis for challenge to Claim Nos.
2 and 3 as awarded for the defects and deficiencies in the bus bodies as supplied
by the petitioner to the respondent.
7. The next Claim No.4 is with respect to the warranty period defects. The
counsel for the petitioner argued that when delivery of the buses was taken, no
such defects were pointed out. I have completely failed to understand this
argument. A warranty clause is with respect to warranty against defects if the
goods are used and not when the goods are taken in a brand new condition from
a supplier. Not only this, the Arbitrator has referred to, in this regard the four
letters written by the respondent to the petitioner whereby the petitioner was
asked to come and rectify the defects but the petitioner failed to do so. Once
again while awarding this claim, I may note that the Arbitrator has awarded
only 50% amount claimed by the DTC, though once again without any rationale
whatsoever, but since as stated above, there are no objections of the DTC
OMP 389/2001 Page 7 nothing can be done except sustaining 50% of the amount awarded under this
claim.
8. In view of the above, I do not find any merit whatsoever in this petition
which is dismissed, leaving the parties to bear their own costs. Let a copy of this
judgment be sent to the Chairman of the DTC, to bring to his notice the
negligent lack of representation on behalf of the respondent during the hearings
of the objections.
VALMIKI J.MEHTA, J
January 06, 2010
ib
OMP 389/2001 Page 8
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!