Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Sachdeva Industries vs Union Of India & Anr.
2010 Latest Caselaw 960 Del

Citation : 2010 Latest Caselaw 960 Del
Judgement Date : 19 February, 2010

Delhi High Court
M/S Sachdeva Industries vs Union Of India & Anr. on 19 February, 2010
Author: Mukta Gupta
*     IN THE HIGH COURT OF DELHI AT NEW DELHI

+     FAO(OS) 116/2009

                                       Reserved on: January 28th, 2010

                                       Decided on:     February 19th , 2010

M/S SACHDEVA INDUSTRIES
Through its Partner,
Sh. Om Prakash Sachdev,
S/o late Sh. M.R. Sachdev,
Having its office at
401, Arunachal Building,
19th Barakhamba Road,
New Delhi-110 001.                                     ..... Appellant
                         Through:   Mr. Digvijay Rai, Advocate.

                  versus

1.    UNION OF INDIA
      Through the Secretary,
      Ministry of Communications,
      Department of Telecommunications,
      Government of India, Sanchal Bhawan,
      1, Ashoka Road, New Delhi-110 001.

2.  SH. T.K. SIL,
    Ex-Director Computer & Sole Arbitrator,
    Calcutta Telephones,
    Office of the General Manager (HQ),
    Dept. of Telecom,
    P-10, New CIT Road,
    Calcutta-700 073.                              ..... Respondents
                       Through: Ms. Preeti Dalal and Ms. Manisha Dhir,
                                   Advocates.
Coram:

HON'BLE THE ACTING CHIEF JUSTICE
HON'BLE MS. JUSTICE MUKTA GUPTA

FAO (OS) No.116/2009                                               Page 1 of 7
 1. Whether the Reporters of local papers may
   be allowed to see the judgment?                            Yes

2. To be referred to Reporter or not?                         Yes

3. Whether the judgment should be reported
   in the Digest?                                             Yes

%

MUKTA GUPTA, J.

1. The Appellant on 3rd June, 1988 was awarded a tender by Respondent

No. 1 for supply of PV-Drop-Wire-0.91 mm. Vide letter dated 2nd September,

1988 the Appellant expressed his willingness to commence supply of 20,000

KMs Drop Wire within a week after the receipt of the confirmed and complete

order. On 11th January, 1989 the purchase order No. C-89/D. Wire/6073/2

was placed on the Appellant. Clause 16 of the said purchase order is relevant

and reproduced as under:

"16. Special instruction

1) Supply is to commence @ 3,000 Kms. per month after 2 months from the date of issue of this P.O. and be completed by 10.12.89.

2) TAC. No. TDBG/18/2/4191 dt. 22.5.86 valid upto 21.5.89."

2. The Appellant expressed his willingness to deliver the goods on 11th

January, 1989 itself. To this, the Respondent No. 1 vide its letter dated 12th

January, 1989 duly informed the Appellant that he was permitted to go ahead

with the production of drop wire in proportion to the monthly capacity

mentioned in the tender offer even during the lead period, however, no supply

and test call to QA would be accepted before 27th January, 1989. Thus, in

clear terms the Appellant was informed not to supply before 27th January,

1989, though the Appellant through senior officers of the Respondent also

tried to persuade that the supplies be taken earlier.

3. Pursuant to the supplies, the Appellant raised a bill applying the price

variation formula as per the price of the raw material prevailing thirty days

before 11th January, 1989 and the interest thereon in terms of clause 14.4, as

according to the Appellant he offered the same on the said date. Clause 14.4

stipulates:

"14.4 For applying price variation formula indicated in Annexure „B‟ the price of the raw material prevailing as on 30 days before date of offer of stores to the Inspecting Authority will be taken into account. Necessary documentary evidence from the concerned authority has to be produced along with the bills preferred for payment in support of claim."

4. On this, a dispute arose and besides other claims these two claims with

regard to the date of applicability of the price variation formula and the

interest thereon were also referred. The Arbitrator decided the above said

claims No. 1 and 2 against the Appellant and held that the price on the basis of

rate prevailing thirty days prior to 27th January, 1989 has to be calculated.

5. The Appellant filed objections against the arbitral award dated 4 th June,

1996 of the Respondent No.2 under the Arbitration Act, 1940. The learned

Single Judge of this Court after hearing the parties, vide its order dated 5th

November, 2008 dismissed the objections of the Appellant and the award was

made rule of the Court. This judgment dated 5th November, 2008 is impugned

before us in the present appeal.

6. The short issue for determination is whether by granting the price

variation thirty days prior to 27th January, 1989 and the interest thereon,

instead of thirty days prior to 11th January, 1989, and the interest thereon

whether the Arbitrator has misconducted in any manner or there is an error on

the face of the Award or that the same is contrary to the law or public policy.

7. Learned counsel for the Appellant in support of his contention relies on

the repeated communications addressed by the Additional Secretary of the

Respondent No. 1 to the General Manager, Telecom Stores on the

representations made by the Appellant, advising him that no embargo of

supplies before 27th January, 1989 could be placed.

8. In Steel Authority of India v. Gupta Brother Steel Tubes, 2009 (12)

Scale 393 the Hon‟ble Supreme Court summarized the legal position as under:

"26. It is not necessary to multiply the references. Suffice it to say that the legal position that emerges from the decisions of this Court can be summarised thus:

(i) In a case where an arbitrator travels beyond the contract, the award would be without jurisdiction and would amount to legal misconduct and because of which the award would become amenable for being set aside by a Court.

(ii) An error relatable to interpretation of the contract by an arbitrator is an error within his jurisdiction and such error is not amenable to correction by Courts as such error is not an error on the face of the award.

(iii) If a specific question of law is submitted to the arbitrator and he answers it, the fact that the answer involves an erroneous decision in point of law does not make the award bad on its face.

(iv) An award contrary to substantive provision of law or against the terms of contract would be patently illegal.

(v) Where the parties have deliberately specified the amount of compensation in express terms, the party who has suffered by such breach can only claim the sum specified in the contract and not in excess thereof. In other words, no award of compensation in case of breach of contract, if named or specified in the contract, could be awarded in excess thereof.

(vi) If the conclusion of the arbitrator is based on a possible view of the matter, the court should not interfere with the award.

(vii) It is not permissible to a court to examine the correctness of the findings of the arbitrator, as if it were sitting in appeal over his findings.

Propositions (ii), (vi) and (vii) are relevant for the decision in the

present case. The Appellant‟s contention at best, being an error relatable to

the interpretation of the contract by the Arbitrator, is an error within his

jurisdiction and thus such an error is not amenable to correction by Courts as

the same is not an error on the face of the Award. Moreover, if two possible

views of interpreting the terms of the contract are plausible, it is not

permissible for the Court to interfere with the Award nor sit in appeal over its

findings.

9. On facts also we find that there is no error in the award of the Arbitrator

in applying the price variation thirty days prior to 27th January, 1989 and the

interest thereon, instead of the price variation thirty days prior to 11th January

and the interest thereon. Undoubtedly, the lead period of two months is given

to the supplier to ensure the supplies to be ready with the consignment and

ensure the supplies at the right time. However, this time is also given to the

concerned consignees to be able to accept the order and utilize it/store it

effectively. Merely because the Appellant was ready with the supplies on 11th

January, 1989 he could not force the Respondent No. 1 to have accepted it on

the same date and the Respondents were entitled to receive it at the right time

as fixed. On his offer for delivery of goods on 11th January, 1989 itself he

was clearly informed that the delivery will not be accepted before 27th

January, 1989. The Appellant could not have unilaterally fixed the date as per

his choice.

10. This being the only issue urged before us, we find no infirmity either in

the Arbitration Award or the order of the learned Single Judge.

11. The appeal is dismissed. No order as to costs.

(MUKTA GUPTA) JUDGE

(MADAN B. LOKUR) ACTING CHIEF JUSTICE FEBRUARY 19, 2010 vn

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter