Citation : 2010 Latest Caselaw 942 Del
Judgement Date : 18 February, 2010
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ W.P.(C) 5470/2008
% Date of decision : 18th February, 2010.
MUKESH MEHRA ..... Petitioner
Through Mr.Ravi D. Sharma, advocate.
versus
B.S.E.S YAMUNA POWER LTD ..... Respondent
Through Mr. Vikram Nandrajog, advocate.
CORAM:
HON'BLE MR. JUSTICE SANJIV KHANNA
ORDER
1. The impugned speaking order dated 9th/10th July, 2008
holds that the petitioner is guilty of dishonest abstraction of electricity
for the following reasons :-
"Establishment of facts of Cases:
The case has been analysed and observed as under:
In this case the date of inspection display was found hang. This fact has been mentioned on meter inspection Performa no.7374 as well as on seizure memo. This situation arises mostly in the cases where meter is tampered without any physical interference i.e. Electro Static Discharge (ESD) due to software disturbances as meter is not calibrated to face extreme high
WPC No.5470/2008 Page 1 voltage generated artificially.
As per CMRI data download and analysis of consumption pattern it has been observed that extra ordinary and extreme high MD (KW) as 41.4 KW has been recorded on 23/08/2007. This extra feature also appears when meter is subjected to high voltages generated artificially. As per CMRI data, meter RTC found faulty. This situation arises when meter is externally applying extra high voltage. This aspect also strengthens the fact in this case that meter has been applied with ESD.
As per CMRI, power factor found recorded very low. CT tamper events recorded for seven times and magnetic tamper events also recorded for four times. As per CMRI data, meter LCD and LED found not o.k. Hence the case again confirms that ESD has been used with the sole motives of Dishonest Abstraction of Energy. Thus, conclusive evidence of Dishonest Abstraction of Energy is deducted.
The average consumption as per module works out to 09.16% which is much less than the prescribed limit of DERC which is corroborative evidence of Dishonest Abstraction of Energy.
It is a case of Dishonest Abstraction of Energy wherein meter has been tampered without any physical interference. Thus the case is covered under clause 52(XII) as per SERC supply Code.
Final Proposal/Order:
In view of the evidence of tampering of seals, faulty of display and RTC, recording of low power factor, GT short tamper and magnetic tamper and extremely low recorded consumption pattern conclusive evidence of Dishonest Abstraction of Energy is substantiated against the consumer. Further consumer submission that he has not
WPC No.5470/2008 Page 2 tampered the meter does not absolve him from the case of Dishonest Abstraction of Energy. DAE is established under tariff schedule 2007 Regulation 52 & 53 of Metering & Billing Regulations of DERC and Section 135 & 138 of Electricity Act, 2003."
2. On the basis of the said Order, the respondent-discom has
raised the impugned bill of Rs.7,47,929/-.
3. Pursuant to complaint made by the petitioner on 14th
September, 2007 that the meter was not recording electric
consumption, the officers of the respondent-discom inspected the
meter on 19th September, 2007 and it was noticed that the meter
pulse and display was not working and therefore accuracy check was
not possible. It was also recorded that seals were removed for testing
and the meter terminal was found burnt. On 20th September, 2007 the
old meter was removed by the Enforcement Department and it was
recorded that the old terminal was found burnt.
4. Show cause notice dated 5th December, 2007 was issued to the
petitioner. The said show cause notice in addition to other
observations records that meter box seals, terminal seals and half
seals were found tampered. It further states that meter hologram
seals were found to be open. The impugned speaking order dated
9/10th July, 2008 records that there was evidence of tampering of
seals.
WPC No.5470/2008 Page 3
5. As noticed above, in the meter testing report dated 19th
September, 2007 there is no allegation of tampering of seals. In fact,
the meter testing report dated 19th September, 2007 specifically
states that seals were removed for testing. Thus, the officers of the
respondent-discom have themselves had removed the seals of the
meter for testing. The respondent-discom along with the counter
affidavit have filed inspection report dated 20th September, 2007. The
said inspection report records "no physical illegal evidence found
inside the meter by the joint team". It thereafter records that terminal
seals, ultrasonic welding and half seals were found tampered and
refixed. Obviously, this has reference to the removal of seals and
tests made by the meter testing team as recorded in their report
dated 19th September, 2007. This fact unfortunately has been
completely ignored and overlooked in the speaking order.
6. The speaking order further notes that CMRI data downloaded
on 23rd August, 2007 records extraordinary and high MDI as high as
41.4 KW. This may be correct but the officer passing the speaking
order should have addressed and examined the MDI (KW) for the
earlier period. MDI (KW) for the period between November 2006 to
August 2007 as per the details in the computer records of the
respondent-discom varies between 4.56 KW to 9.20 KW. It never
WPC No.5470/2008 Page 4 went into double figure. This factor has not been again accounted for
and is ignored. There are number of reasons why on a particular day
and time, the meter may record a high MDI like when a certain
special equipment is brought at site for repairs, etc. If high MDI (KW)
recorded on one day is an isolated incident, it may not be significant if
other data/MDI(KW) recordings over a period of time are satisfactory.
7. The speaking order records that Real Time Clock (RTC) was
found to be faulty. It is accepted that there can be number of reasons
why RTC may fail. The impugned order records one of the reasons
why the RTC can fail is when extreme high voltage current is applied.
However, it ignores that there can be other circumstances and
reasons why RTC can fail. The first paragraph of the reasons given in
the speaking order further records that the meter display was found to
be hanging and this mostly happens in cases where the meter is
tampered with. This again is a presumption or a possibility but not
certain or monolithic inference. The display can hang and malfunction
for various reasons. These may be a relevant factors, when there is
other material and evidence which justify and show tampering or
dishonest abstraction of electricity. RTC and display failure alone do
not indicate tampering or dishonest abstraction of electricity as a
universal affirmative rule and are not conclusive proofs. Probabilities
WPC No.5470/2008 Page 5 cannot take shape of proof itself and are not conclusions. The error
becomes apparent if we examine the reasons given by the laboratory
report when the meter was tested. The laboratory has opined that
the said failures may be due to heavy loads/imbalance load - due to
imbalance load condition. The reasons given in the laboratory test
report have not been considered and referred to in the speaking
order. They are completely ignored.
8. In view of the above, I find that the speaking order cannot be
sustained as it fails to take into consideration relevant and material
facts and is one sided. The same is accordingly quashed. The
impugned bill accordingly also fails and is set aside. No costs.
9. The amount deposited by the petitioner pursuant to the interim
order passed by this Court will be adjusted in the future bills of the
petitioner.
SANJIV KHANNA, J.
FEBRUARY 18, 2010
P/VKR/NA
WPC No.5470/2008 Page 6
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!