Citation : 2010 Latest Caselaw 928 Del
Judgement Date : 17 February, 2010
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP No.154/2003
17th February, 2010
M/S. MOHAN LAL HARBANS LAL BHAYANA & CO.
...Petitioner
Through: Mr. R. Rajappan, Advocate.
VERSUS
UNION OF INDIA ....Respondents.
Through: Ms. Geeta Sharma, Advocate. CORAM: HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be allowed to see the judgment?
2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in the Digest?
% JUDGMENT (ORAL) VALMIKI J.MEHTA, J
1. In this objection petition under Section 34 of the Arbitration &
Conciliation Act, 1996, the counsel for the petitioner has very fairly pressed
only Claim No.4, Counter Claim No.2 and Counter Claim No.10 as awarded by
the Arbitrator. I will therefore deal with the arguments raised as regards each
one of them serially.
2. Claim No.4 was the claim of the petitioner for dewatering charges
done during an extended period of the contract. The counsel for the petitioner OMP 154/2003 Page 1 contended that since the claimant/petitioner was only to do the work of
dewatering for a limited period under the contract and since, the petitioner was
forced to do extra dewatering during the extended period, the petitioner was
entitled to this claim which has been rejected by the Arbitrator. I note that the
Arbitrator while deciding this claim has referred to an undertaking given by the
petitioner in his application dated 8.7.1999 that he has suffered no loss on
account of delay and that he shall not claim damages beyond what is already
paid for the dewatering upto 10.11.1998. If that be so that the petitioner himself
has given an undertaking that he will not claim any further amount except what
is already paid to him up to 10.11.1998. I therefore do not find any fault in the
finding of the Arbitrator while dismissing this claim.
3. Counter Claim No.2 was the claim made by the respondents herein
for the additional cost to the respondent on account of the rescission of the
contract. It is not disputed that the contract was formally rescinded by the
respondent on account of the breach of the petitioner. Once there is found to be
a valid rescission of the contract, any consequential higher cost upon the
respondents has to be to the account of the petitioner. What the Arbitrator has
done is that he has estimated a higher cost with respect to various materials
during the estimated time of performance by the new contractor and thereafter
by applying a percentage formula for escalation, has awarded a sum of
Rs.1,16,483/- (after allowing forfeiture of security deposit of Rs.50,000/- and
keeping the allowing of counter claim No.3) he found that the escalation would
OMP 154/2003 Page 2 in fact be of Rs.8,10,000/-. When damages are awarded, certain guess work is
inherent in the exercise for calculation of damages. The Arbitrator has on the
basis of materials before him arrived at a figure on the basis of honest
guesswork. Once there are materials and then the Arbitrator resorts to an honest
guesstimate, it is within his realm of jurisdiction to do so and no fault can be
found with the Award on this aspect.
4. Counter Claim No.10 was the claim made by the respondents for
the bill of electricity charges issued and which were payable by the petitioner
herein. The admitted fact is that the petitioner was the only consumer of
electricity at site. Though the petitioner was to take his own electricity
connection under the contract, but since the petitioner failed to do so, therefore
the respondent allowed the petitioner to use its electricity connection at site.
Surely, since the petitioner was the only user of the electricity from the
electricity connection all bills which are received with respect to that electricity
connection, have to be paid by the petitioner. The Arbitrator has done just that
and has awarded the charges payable under the bill to the respondent. Out of
the bill of Rs.6,35,522/-, since the respondent had already recovered
Rs.3,61,335/-, the Arbitrator awarded the balance amount of Rs.2,74,187/-. No
fault, therefore, can be found with the Award on this aspect also.
5. An Award can only be set aside, if the same is illegal or violative
of the contractual provisions or the findings are so perverse that the judicial
conscience of the Court is shocked. In the present case, there is no illegality nor
OMP 154/2003 Page 3 any perversity nor any violation of the contractual provisions for this Court to
interfere with the Award under Section 34. The objection petition is therefore
dismissed, however, leaving the parties to bear their own costs.
VALMIKI J.MEHTA, J
February 17, 2010
Ne
OMP 154/2003 Page 4
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!