Citation : 2010 Latest Caselaw 1094 Del
Judgement Date : 24 February, 2010
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS(OS) No. 2139A/2000
24th February, 2010
DELHI GOVERNMENT OFFICERS CO-OPERATIVE GROUP HOUSING
SOCIETY LTD.
...Petitioner.
Through: Mr. Sandeep Sharma and Ms. Kanika
Singh, Advocates
M/S MANCHANDA & MANCHANDA BUILDERS PVT. LTD.
....Respondent.
Through: Mr. Milanka Chaudhary and Mr.
Sarojanand, Advocates
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be allowed to see the judgment?
2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in the Digest?
% JUDGMENT (ORAL) VALMIKI J.MEHTA, J I.A.No. 3645/2001 in CS(OS) No. 2139A/2000
1. These objections under Sections 30 and 33 of the Arbitration Act, 1940
have been preferred by the contractor/petitioner/objector to the Award dated
7.7.2000 passed by the sole Arbitrator Justice Satpal (Retd.) Hon'ble Judge of
this court. The dispute which arose between the parties was on account of the
CS(OS) 2139A/2000 Page 1 contract awarded to the objector for construction of about 76 dwelling units at
the respondent's site at Patparganj, Delhi. The claims therefore pertained to
various items of construction work.
2. The counsel for the objector has only pressed the objections with respect
to Claim No.1 sub items 3, 4 and 5, Claim No.2 sub items 5 and 7 and Counter-
claim awarded to the non-objector for defective work. As regards the last
objection with regard to Counter-claim for defective work, during the course of
hearing, it transpired that no such objection has been raised in the objection
petition and therefore in the absence of any objection, no argument can be
addressed as regards the Award pertaining to the Counter-claim for defective
work and which issue was therefore not pressed. As regards the other claims, I
will take up the same serially.
3. Claim No.1, sub item-3 pertains to the claim made by the objector for
extra steel consumption. The Arbitrator has recorded the inconsistency in
different running account bills as submitted by the objector and has therefore
dis-believed the claim for extra steel consumption. This finding is a finding of
fact. There is nothing perverse in this finding for this court to hold that the
Arbitrator has mis-conducted himself or the proceedings. Objection to this
claim is therefore rejected.
4. Claim No.1 sub-items 4 and 5 pertained to the escalation claims of labour
and material. The Arbitrator while dealing with these aspects, has arrived at a
factual finding that whatever was the entitlement with respect to the labour and
CS(OS) 2139A/2000 Page 2 material escalation, the same was duly paid for as per the amounts assessed by
the Architect. Again this finding is a finding of fact that the entitlement of
escalation stands duly paid. In my opinion therefore, such finding of fact
cannot be challenged under Sections 30 and 33 of the Arbitration Act, 1940 as
no perversity has been pointed to this court.
5. Claim No.2 sub item 7 was the only other claim which was challenged.
Under this claim, the objector claimed charges for providing terrazo grit finish
instead of rough sand cast plaster finish. The arbitrator has referred to the
relevant clauses of the contract namely Clause 3 of Section XII and sub Clause
( n ) of this clause. The arbitrator has held that the work done of the terrazo grit
finish falls within the scope of the work as per the aforesaid sub-Clause and
therefore no extra amount is payable. A reading of the relevant clause also
shows that the item of work is for grit finishing plaster and it is not limited to
rough sand cast cement plaster. Therefore, the Arbitrator was entitled to hold
that all types of grit finishing including terrazzo grit finishing falls within the
scope of the work under this clause. At best, as per the contention of the
counsel for the objector, two views are possible. Once two views are possible
and the view adopted by the Arbitrator is one plausible view, this court will not
interfere with the view taken by the Arbitrator merely because another view is
possible. No valid objection therefore can be raised to this part of the Award.
No other claim or issue was pressed. The objection to the Award are
accordingly dismissed.
CS(OS) 2139A/2000 Page 3 I.A. No. 2932/01in CS(OS) No.2139A/2000
6. These are objections filed by the petitioner's society. Only one objection
has been pressed by the counsel for the petitioner with respect to the claim of
unadjusted mobilisation advance of Rs.2,10,450/-. The Arbitrator has given a
finding of fact as regards this aspect in the Award that the Society has not given
any details as to how the amounts only of Rs.8,80,027/- and Rs.59,523/- stand
adjusted leaving a balance of Rs.2,10,450/- out of the total of Rs.11,50,000/-.
Even before this Court, in the objection petition, I do not find any detailed
calculations in terms of the 24 running bills which are stated to be showing that
the total of the adjustment towards mobilisation advance in each of the 24 bills
leaves the unadjusted amount of Rs.2,10,450/-. In the absence of any detailed
averments in an affidavit by way of evidence, a finding of fact has been arrived
at by the Arbitrator that the society failed to prove that an amount of
Rs.2,10,450/- is still lying unadjusted. Once the society fails to discharge its
onus to prove before the Arbitrator by giving appropriate details, the Arbitrator
committed no misconduct in dismissing this claim. Even in the objection
petition filed in this Court no details have been mentioned except a general
averment that this claim has been wrongly allowed and there was unadjusted
advance of Rs.2,10,450/-. In the facts and circumstances of the case, I do not
find that the Arbitrator has in any manner misconducted himself and the
proceedings.
CS(OS) 2139A/2000 Page 4
7. No other issue was pressed. The objection petition of the society is
therefore also dismissed. In view of the dismissal of both the objection petition,
the Award dated 7.7.2000 is made rule of the Court. Let a decree be drawn in
terms thereof. Parties are left to bear their own costs.
VALMIKI J.MEHTA, J
February 24, 2010
ib
CS(OS) 2139A/2000 Page 5
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!