Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Emaar Mgf Construction Pvt Ltd vs Delhi Development Authority & Ors
2010 Latest Caselaw 5749 Del

Citation : 2010 Latest Caselaw 5749 Del
Judgement Date : 20 December, 2010

Delhi High Court
Emaar Mgf Construction Pvt Ltd vs Delhi Development Authority & Ors on 20 December, 2010
Author: Vipin Sanghi
*     IN THE HIGH COURT OF DELHI AT NEW DELHI

                  Judgment reserved on: 29.11.2010

%                 Judgment delivered on: 20.12.2010

+            O.M.P. 633/2010 & IA 14210 and 15795/2010


      EMAAR MGF CONSTRUCTION PVT LTD                 ..... Petitioner
                    Through: Mr. P.V. Kapur, Sr. Adv.
                             (S.G. Solicitors)- Mr. Sunil Goel,
                             Dheeraj Singh, Sushil Bhartiya,
                             Aman Anand and Pranav Sapra,
                             Advocates

                    versus


    DELHI DEVELOPMENT AUTHORITY & ORS           ..... Respondent
                  Through: Ms. Indira Jaisingh, ASG with Mr.
                           Ajay Verma and Ms. Sonam Anand,
                           Advocates
                           Mr. U.C. Mittal and Mr. Ankur Mittal
                           for R-3
CORAM:

HON'BLE MR. JUSTICE VIPIN SANGHI

1.    Whether the Reporters of local papers may
      be allowed to see the judgment?               :     Yes

2.    To be referred to Reporter or not?            :     Yes

3.    Whether the judgment should be reported
      in the Digest?                                :     Yes

                             JUDGMENT

VIPIN SANGHI, J.

1. The petitioner has preferred the present petition under

Section 9 of the Arbitration and Conciliation Act, 1996 to seek an

interim order of injunction against the respondent no.1, DDA to stay

the effect and operation of the notice dated 16.10.2010 issued by it;

to restrain the respondent no.1 from giving effect to the demand as

raised in the said notice; to restrain the respondent no.1 from taking

any steps pursuant to the notice dated 16.10.2010, and; to restrain

the respondent No.1/DDA from invoking the three bank guarantees

aggregating to ` 183.00 crores , as furnished by respondent No.2 State

Bank of Patiala (who have furnished their guarantee for ` 33 crores

being BG No. 5079408BG0000654) and respondent no.3, i.e. State

Bank of India (who have furnished their Guarantee for ` 150 crores

being BG No. 0480308BG0010173), to any extent whatsoever.

2. Corresponding injunction is sought against respondent nos.2

and 3 banks from encashing the aforesaid bank guarantees furnished

by them at the behest of the petitioner in favour of respondent no.1,

DDA.

3. The petitioner company is a real estate developer and claims

to have undertaken various real estate development projects all over

the country. The petitioner states that sometime in 2006, the

respondent DDA invited bids for development and construction of

Commonwealth Games Village on a parcel of land comprising 11

hectares adjacent to Akshardham Temple in NOIDA. The petitioner

was shortlisted along with other 11 bidders, and eventually selected as

the successful bidder. The construction of residential towers of the

Commonwealth Games Village was to be undertaken on Public-Private

Participation (PPP) basis.

4. The parties entered into a Project Development Agreement

(PDA) on 14.09.2007. This agreement contains an arbitration

agreement in clause 17. The petitioner has filed the present petition

under Section 9 of the Act by relying upon the said arbitration clause

contained in the Project Development Agreement.

5. The petitioner claims to have made payment of earnest

money of ` 80.25 crores and also an amount of ` 120.375 crores

towards upfront fee. The petitioner also states that it appointed various

consultants and architects to execute the project.

6. Under the terms of the agreement, "Project Completion Date"

was defined to mean the date when all residential facility are

completely developed in all respects (including landscaping),

technically fit to be occupied and ready to use/livable, with no pending

construction, unfinished work, construction equipments, debris,

construction material etc. on the project site and certified in writing by

the Monitory Committee. (Clause 1.1.20).

7. The petitioner, who acted as a project developer, was obliged

to completely develop the project by 01.04.2010 (Clause 3.11). The

date of completion of the Project is deemed to be the date when all

Residential Apartments are completely developed and are technically

fit to be occupied, including all other associated facilities and amenities

and a completion / occupancy certificate in this regard has been

obtained from NDMC/MCD and DDA.

8. Under clause 3.1, the Project Developer was, inter alia,

obliged to develop the residential facility at the project site within the

time frames as set out in greater detail in Schedule III to the

Agreement. Clause 3.1 reads as follows:

"3.1 The Project Developer shall undertake to develop the Project Site and construct such capacity of residential accommodation and meeting such specifications and requirements as are specified in greater detail in Schedule II to this Agreement. The Project Developer shall develop the Residential Facility at the Project Site within the time frames as set out in greater detail in Schedule III to this Agreement."

9. Annex III/Schedule III contains the project milestones which

the petitioner was obliged to attain. The same reads as follows:

Annex 3 PROJECT MILESTONE

A. Following are the Project Milestone to ensure timely completion of the Project.

Milestone Milestone                                Time from the date of
No.                                                signing   of   Project
                                                   Development
                                                   Agreement i.e. D- Day
                                                   (estimated at July 15,
                                                   2007) including all
                                                   holidays/Sundays

1            Foundation Work (including Plinth D+120   days    i.e.

Level) upto Plinth Level for 50% November 12, 2007 Blocks and Mock Unit completion

2 Structure work upto G+4 level, with D+240 days i.e. associated electrical works + November 12, 2007 Foundation work including Plinth Level for rest of the books

3 Structure Work upto terrace level, D+420 days i.e. with associated electrical works September 7, 2008 and B.W. upto G+4 level

4 Completion of brick work upto D+600 days i.e March terrace level and internal plaster, 6, 2009 flooring, etc. for 5 levels, with associated electrical works

5 Completion of flooring and D+780 days i.e. finishing, with associated electrical September 2, 2009 works of all blocks all levels upto terrace level

6 External finish of all blocks and all D+840 days i.e. levels November 1, 2009

7 Completion of all electric work D+870 days i.e. including lifts, E.S.S etc and December 1, 2009 completion of U.G.R./ Pump Rooms/ Lifts/ Pump Sets etc.

8 Completion of all development D+900 days i.e. work including landscaping December 31, 2009

9 Project Completion Date April 1, 2010

Note: No exclusions, including time taken by DDA in giving approvals/ notifications, will be allowed to be considered in the calculation of time taken for the achievement of Project Milestone.

B. The liquidated damages amount to be paid by the Project Developer to DDA in case of non-achievement of each of the aforesaid Project Milestone shall be calculated as follows:

a. Rs.15,00,000 (Rupees Fifteen Lakhs Only) a day for each day of delay for the first fifteen (15) days of delay;

b. Rs.25,00,000 (Rupees Twenty Five Lakhs Only) a day for each day of delay for the next fifteen (15) days of delay;

c. Rs.50,00,000 (Rupees Fifty Lakhs Only) a day for each day of delay thereafter till the date of achievement of that Project Milestone or Termination Date, whichever is earlier.

I am also informed that the figure of ` 25 lacs set out in para

B(b) as liquidated damages, stands reduced to ` 20 lacs, by agreement

of parties.

10. Under clause 6 of the agreement, the petitioner was required

to submit performance security for ` 400 crores in the form of

unconditional bank guarantee(s) in accordance with the format

specified in Schedule VI, from scheduled commercial bank acceptable

to the respondent, DDA. Clause 6.2 of the agreement, inter alia,

provides as follows:

"6.2 DDA shall have the rights to invoke the Performance Security as recourse in the Project Developer Event of Default including but not limited to on account of an event of non-compliance to the milestones or persistent delays by the Project Developer in implementing the Project, in accordance with the terms of the Performance Security.

Without prejudice to the aforesaid, DDA shall have the right to invoke the Performance Security under the following events:

i. In case the Project Developer is unable to deposit the liquidated damages for delay in achieving any Milestone the said Performance Security shall be forfeited for an amount as computed under Schedule III.

ii. In case of default by the Project Developer in meeting the defects liability obligations mentioned under Clause 7 below, to the extent of Rs.5,00,00,000/-

(Rupees Five crores only) in case of water-proofing defects and Rs.5,00,00,000/- (Rupees Five crores only) in case of other defects.

iii. In case of default by the Project Developer in meeting the deficiency charges obligations mentioned under Clause 8.12.3 to the extent of Rs.5,00,00,000/- (Rupees Five crores only).

iv. In case of default by the Project Developer in meeting its obligations mentioned under Clause 8.14.2 below, to the extent of Rs.2,00,00,000/- (Rupees Two crores only).

In the event DDA invokes the Performance Security, the Project Developer shall have to furnish a fresh Performance Security for the invoked amount from a scheduled commercial bank, failing which, the DDA shall be entitled to terminate this Agreement.

The performance security shall be returned in the following manner: ... ... ..."

11. The admitted position is that in terms of clause 6.2, the

respondent/DDA, from time to time, partially returned the bank

guarantees furnished as performance security and continued to retain

the performance security of ` 183 crores. These performance bank

guarantees are valid till 31.12.2010. Performance security of Rs.17

crores, apart from the aforesaid amount of Rs.183 crores, was also

retained, to be returned in terms of clauses (d), (e) and (f) of clause 6.2

12. The petitioner states that there is no dispute between the

parties that the petitioner achieved milestone nos.1 to 7 on time.

Accordingly, the bank guarantees to the extent of ` 200 crores were

returned by the respondent to the petitioner.

13. The petitioner further states that at the Commonwealth

Games Village, construction/development activity was being carried

out by other agencies/corporations/contractors besides the petitioner,

which included respondent no.1 DDA as well. The scope of work of the

petitioner under the Project Development Agreement did not include

all the construction/development work of the Commonwealth Games

Village. Once the milestone no.7 had been achieved by the petitioner,

the only thing that remained to be completed, on the part of the

petitioner, was external landscaping and connection of intermediaries

from the water/sewage lines and electrical connection after the main

lines had been laid and completed by the respective agencies including

the DDA, DJB, ECIL and BSES.

14. Insofar as the external landscaping work is concerned, the

same included hard scape-consisting of road and pathways, and soft

scape consisting of trees, shrubs, grass etc. The petitioner states that

the external landscaping work could not be completed unless and until

all the work of every agency including DJB, BSES, DDA etc. were

completed.

15. It is claimed that these agencies were not working in tandem

with each other. The petitioner states that under Schedule III, there

was a period of only 30 days provided for achieving milestone no.8,

after milestone no.7 had been achieved. The same could be achieved

only if the other agencies had also completed their respective works.

The petitioner also states that it could not have carried out the

landscaping work before the laying of the underground cable,

water/sewage lines etc. by third party agencies had been done, as

these agencies would otherwise have dug up the work done by the

petitioner.

16. The petitioner states that it complied with all its obligations,

which it could, for achieving the milestone no.8 by 01.03.2010 and

made an application in the prescribed format on 29.03.2010 to the

DDA for issuance of the completion certificate. It is stated that the

respondent, DDA was also called upon to take over possession of the

towers. However, the respondent no.1 failed to take over possession.

17. It is averred that respondent no.1 neither issued the

completion certificate to the petitioner, nor refused the same within

the specified period of 7 days as provided in the Project Development

Agreement. On 03.09.2010, the respondent DDA requested the

petitioner to provide certain documents to enable them to process the

request of the petitioner for issuance of occupancy certificate. On the

same day, without waiting for any further documents from the

petitioner, the respondent no.1 issued a temporary occupancy

certificate, and on the same day, it also issued the occupancy

certificate in relation to the Commonwealth Games Village to the

Organising Committee, wherein it was stated that the said occupancy

certificate was being issued on the basis of statutory clearances. The

petitioner states that the factum of issuance of the occupancy

certificate establishes that the project was completed and fit to be

occupied.

18. The respondent no.1, by its letter dated 20.05.2010, alleged

that the milestones had not been met by the petitioner within the time

granted under the agreement, and threatened to levy liquidated

damages on the petitioner on account of the said alleged default. By

letter dated 09.06.2010, the DDA demanded liquidated damages of `

13.45 crores from the petitioner alleging that there were defects and

delays. The petitioner disputed the allegations of delays and defects.

19. The petitioner states that the respondent took over the

possession of the towers constructed by the petitioner much after the

date when they were completed. It is also stated that the respondent

coerced the petitioner for extending the validity of the bank

guarantees/performance securities. The petitioner claims that there

was a lot of negative publicity for the Commonwealth Games Village in

the media. However, after the intervention of Prime Minister's Office,

the other agencies completed their respective obligations. The

petitioner submits that the Commonwealth Games were held

successfully, and the Commonwealth Village was occupied by

thousands of athletes and officials without any complaints. The

Commonwealth Games Village was highly appreciated by everyone,

including the media, and the negative media reports turned positive.

The petitioner also relies on the letter dated 07.10.2010 addressed by

the Lt. Governor of Delhi to the Prime Minister in support of its case

that the petitioner was not guilty of breach of the agreement.

20. After the completion of the Commonwealth Games, the

petitioner received a letter dated 16.10.2010 from the DDA on

20.10.2010. In this communication, the DDA alleged that the project

had not been completed even till 16.10.2010. The DDA by this letter

demanded liquidated damages amounting to ` 83.70 crores on account

of the alleged delay in achieving of milestone nos.8 and 9. The DDA

also threatened that, in case the said amount is not deposited by the

petitioner, the performance bank guarantees submitted by the

petitioner would be encashed to the extent of the aforesaid amount.

21. The petitioner sent a reply dated 20.10.2010 to the DDA

denying that there was any delay in the achieving of any milestones

and repudiated its liability. It was also alleged that the DDA was

seeking to unjustly enrich itself, and that it was acting in an illegal

manner.

22. The respondent DDA invoked the performance bank

guarantees of the petitioner on 23.10.2010 for the entire amount of `

183 crores, i.e. ` 150 crores from the State Bank of India and ` 33

crores from the State Bank of Patiala. The petitioner submits that,

even without waiting for a week from the date of receipt of the letter

dated 16.10.2010 (which was received by the petitioner on

20.10.2010), the said bank guarantees have been invoked.

23. The petitioner submits that the respondent/DDA has played a

fraud of an egregious nature on the petitioner by invoking the said

bank guarantees, in as much as, even though nothing was lacking from

the side of the petitioner, and the petitioner has fulfilled all its

contractual obligations within the stipulated time, the two bank

guarantees have been invoked by the DDA. This is despite the fact

that it is respondent No.1/DDA and other agencies, who have not

fulfilled their obligations within the stipulated time. The petitioner

states that due to the delays and defaults of the DDA and the other

agencies involved in the development work, "the entire landscaping

work, dependent on such performance by respondent No.1 and its

other agencies, could not be completed in time". It is further

submitted that respondent No.1, for its own breach, cannot levy any

liquidated damages on the petitioner. It is yet to be determined as to

who is in breach and in default. It is submitted that respondent No.1

has no right to invoke the bank guarantees for recovery of liquidated

damages.

24. It is further submitted by the petitioner that the Occupancy

Certificate in terms of the Delhi Building Bye-laws has been issued by

the respondent/DDA. Therefore, it is not open to the DDA to contend

that the project, or any part of it, is not complete. The petitioner

submits that respondent No.1 is entitled to retain the bank guarantees

in the sum of ` 17 crores in terms of clause 6.2(d) (e) and (f) of the

Project Development Agreement, including a guarantee of ` 5 crores

towards performance security for rectification of defects. The petitioner

submits that, even if there are any so-called defects in the works done

by the petitioner, the same would not justify the invocation of the

performance bank guarantees for the amount of ` 183 crores.

25. It is further argued that the invocation of the bank guarantees

by the respondent/DDA has been done at the behest of the Ministry of

Urban Development, Government of India. The petitioner has placed

on record a letter dated 20th October, 2010 issued by the Ministry of

Urban Development, Government of India to the Vice Chairman, DDA

stating that the DDA may, inter alia, proceed to invoke the bank

guarantees furnished at the instance of the petitioner. The petitioner

submits that the DDA is an independent entity and it is the DDA which

is a party to the Project Development Agreement. The Ministry of

Urban Development, Government of India has no role to play in the

matter and the invocation of the bank guarantees has been done, not

on account of an independent application of mind by the DDA but,

under the influence of the Ministry of Urban Development. It is argued

that this also shows that the invocation of the bank guarantees is not

bona fide but is fraudulent.

26. Learned Senior Counsel for the petitioner Mr.P.V.Kapur in his

submissions has argued that in their communication dated 16th

October, 2010 the respondent/DDA had primarily made complaints of

"defects" allegedly existing at the site. He submits that the

respondent/DDA had sought to quantify the liquidated damages on

account of the alleged non-completion of milestone Nos.8 and 9, and

quantified the sum at ` 83.70 crores. In this communication, the

demand made by the respondent/DDA was for deposit of ` 83.70

crores only, and it was stated that in case the amount is not deposited

within seven days, "the amount shall be realized after encashing the

performance guarantee equal to the above amount." He, therefore,

submits that, in any event, the invocation of the bank guarantees to

the tune of ` 183 crores is wholly unjustified and fraudulent. He

submits that a party who is aware of the fact that he is not entitled to

recover the entire amount for which the bank guarantee has been

furnished, but still proceeds to invoke the bank guarantee for the

entire amount, acts fraudulently. He refers to the reply filed by the

respondent/DDA in support of this submission. In their reply the DDA

has given a "preliminary estimate" of the amount that the petitioner is

allegedly liable to pay. The said "preliminary estimate" reads as

follows:-

i. Liquidated damages upto 15.10.10 Rs.83.70 crores

ii. Liquidated damages from 16.10.10 till 15.11.10 (filing of this Reply) (@ Rs.20 lakhs per day x 2) Rs. 12.40 crores

iii. Liquidated damages from 16.11.10 @ Rs.20 lakhs per day x 2 till the completion of the project

iv. Amount spent by Answering Respondent as payment to various authorities for different permissions/ services, which were otherwise the sole liability of Petitioner (provisional) Rs. 49.11 crores

v. Amount spent by Answering Respondent to make the Project area operational for the Commonwealth Games (Provisional) Rs.20.80 crores

v. Damages for loss of goodwill and reputation of Answering Respondent due to Being the acts, omissions and breaches of determined Petitioner.

      vi.    Other damages and losses                      Being
                                                           determined


27. He submits that the aforesaid estimate shows that as on the

date of invocation of bank guarantees, i.e. 23rd October, 2010,

admittedly, the amount of ` 183 crores was not due as liquidated

damages, even if the computation made by the respondent DDA were

to be accepted for the sake of arguments. He submits that even if the

specific figures stated in the aforesaid tabulation are added up, the

same fall short of ` 183 crores. He further submits that the Heads (v)

and (vi) above are not even covered by the performance bank

guarantees furnished at the behest of the petitioner.

28. Mr. Kapur submits that the Monitoring Committee constituted

in terms of the agreement is the authority empowered to certify the

completion of the works under the Project. Till date, the Monitoring

Committee has not returned a finding that there has been a delay on

the part of the petitioner in achieving milestone Nos.8 and 9. In this

regard, he refers to the minutes of the 31st meeting of the Monitoring

Committee held on 6th May, 2010. In this meeting, the Monitoring

Committee constituted a Sub Committee for assisting it in recording

the Completion Certificate as per Clause 3.11 of the Agreement. This

Sub-Committee has two representatives of the DDA and two

representatives of the petitioner. He also refers to the minutes of the

32nd meeting of the Monitoring Committee held on 31st July, 2010. The

Monitoring Committee clarified that the Sub Committee constituted, as

aforesaid, had been formed to submit the report of completion on

milestones 8 and 9 and not for recording completion certificate under

Clause 3.11 of the Project Development Agreement. He also refers to

the minutes of the 33rd meeting held on 25th October, 2010 to submit

that the Sub-Committee did not meet due to preoccupation of the

officers of the DDA. He submits that the 1st meeting of the Sub-

Committee constituted, as aforesaid, was held on 28th October, 2010.

Even on that date, the meeting remained inconclusive. By reference to

letter dated 10th November, 2010 stated to have been issued by the

petitioner to the respondent/DDA, the petitioner submits that it is the

officers of the DDA who did not turn up for the meeting of the Sub

Committee scheduled for 9th November, 2010. The submission of

Mr.Kapur is that until and unless the date of achievement of milestone

Nos.8 and 9 is finalized, it cannot be said that the petitioner has not

achieved the said milestones in time. Consequentially,

respondent/DDA cannot invoke the performance bank guarantees as

done by it.

29. Mr. Kapur submits that the respondent/DDA has never

demanded any damages for loss of goodwill or loss of reputation or on

any other account. No notice in this regard was issued to the

petitioner prior to invocation of the bank guarantees. He, therefore,

submits that the aforesaid tabulation prepared by the respondent is an

afterthought to somehow come as close to figure of ` 183 crores as it

could.

30. Mr. Kapur submits that the petitioner communicated the fraud

being played upon by the respondent/DDA to respondent Nos. 2 and 3

banks on 23rd October, 2010. (I may note that the said communication

is contained in the compilation of documents tendered in Court during

the course of arguments). He, therefore, submits that the respondent

Banks had notice of the fraud sought to be played by the respondent

DDA upon the petitioners.

31. Mr. Kapur submits that to permit the respondent/DDA to

encash the bank guarantees in question would also lead to

irretrievable injustice to the petitioner inasmuch, as, under Clause 6.2

of the Project Development Agreement, in the event DDA invokes the

performance security, the petitioner shall have to furnish a fresh

performance security for the invoked amount from a scheduled

commercial bank, failing which, the DDA shall be entitled to terminate

the agreement. Consequently, upon the invocation of the bank

guarantee of ` 183 crores, the petitioner shall become obliged to

furnish a fresh guarantee for the said amount and upon failure to do

so, the agreement may be terminated by the DDA. He submits that if

the agreement is terminated by the DDA, the petitioner would not be

able to enforce its right to sell a part of the total number of flats

developed by the petitioner on its own. He submits that the invocation

of the bank guarantee would be highly unjust and will cause ruination

to the petitioner. Mr.Kapur submits that the petitioner has been made

a scapegoat by the respondent DDA for its own failure in carrying out

its works and responsibilities in completing the works undertaken by it

for holding Commonwealth Games.

32. Mr. Arvind Nigam, learned Senior Advocate has also made his

submissions in support of the petition. He submits that under the

Unified Building Bye-Laws, there is no such thing as "temporary",

"interim" or "conditional" Completion Certificate. He submits that once

the Completion Certificate is granted, the same is final and conclusive

of the fact that the building works have been completed in accordance

with the sanctioned plans. He submits that the notice of completion of

the works had been given on 29th March, 2010 and the respondent

DDA had issued a so called temporary Occupancy Permit on 3rd

September, 2010. On the same day, the Occupancy Permit was issued

by the DDA, valid till completion of Commonwealth Games, 2010. He

submits that under Bye-Law 7.6 of the Unified Building Bye-Laws, the

completion certificate is deemed to be granted after period of sixty

days, unless the application seeking completion certificate is

specifically rejected. He submits that in this case, the said application

had not being rejected.

33. Mr. Kapur has relied upon the following decisions in support of

his submissions:-

(i) Humboldt Wedag India Pvt. Ltd. v. Dalmia Cement Ventures

Ltd., (2010) 4 Arb. L.R 11;

(ii) Regional Manager, Central Bank of India v. Madhulika Guru

Pradad Dahir & Ors., AIR 2008 SC 3266;

(iii) Bhaurao Dagdu Paralkar v. State of Maharashtra & Others,

(2005) 7 SCC 605;

(iv) Hindustan Steelworks Construction Ltd. v. Tatapore & Co.,

AIR 1996 SC 2268.

34. Upon invocation of the aforesaid two bank guarantees on

23.10.2010 of ` 33 crores and ` 150 crores respectively issued by State

Bank of Patiala and State Bank of India, on the same day, the State

Bank of India issued two pay orders in faovur of the respondent DDA

for ` 90 crores and ` 60 crores, and the State Bank of Patiala issued

one pay order for ` 33 crores.

35. When the matter was taken up by this Court on 25.10.2010,

the aforesaid position was brought to the notice of this Court. At that

stage, the Court did not grant any interim injunction in respect of the

pay order of ` 90 crores issued by State Bank of India. However, in

respect of the pay order for ` 60 crores issued by State Bank of India

and the pay order for ` 33 crores issued by State Bank of Patiala, the

following operative order was passed:

"In case the said pay orders have already been encashed, it is made clear that there would be no interim order.

However, in case the pay order of Rs.33 crores has not been encashed and the amount not credited to the account of the respondent/DDA, status quo shall be maintained in respect thereof.

In relation to the pay orders issued by State Bank of India aggregating to Rs.150 crores, as aforesaid, in case the amounts have not been credited to the accounts of DDA, status quo shall be maintained in respect of the pay order for Rs.60 crores bearing no.764469 dated 23.10.2010. However, the pay order for Rs.90 crores may be encashed".

36. Ms. Indira Jaisingh, learned Additional Solicitor General

appearing on behalf of the respondent DDA, firstly, submits that this

petition has become infructuous as the two bank guarantees issued by

State Bank of India and State Bank of Patiala stood encashed on

23.10.2010 itself.

37. She submits that the encashment of the said bank guarantees

meant that the proceeds were taken out of the bank accounts of the

petitioner, and the petitioners bank accounts were debited by the

concerned bank. In support of her submission, she places reliance on

an order dated 30.04.2010 passed by this Court in Cont. Case (C)

No.281/2010, ACG Hospitality Pvt. Ltd. v. R.K. Sharma & Anr. In this

case, when the matter was taken up for hearing in W.P. (C)

No.696/2010, the Court had granted an interim injunction in favour of

the petitioner by directing that in case the bank guarantee had not

been encashed, the encashment of the guarantee by kept in abeyance

till the next date of hearing. The writ petition was adjourned to

10.02.2010. On that date, counsel for the DDA as well as the counsel

for the bank had submitted that the bank guarantee of the petitioner

stand encashed. On the basis of these statements, the writ petition

was dismissed as infructuous.

38. Thereafter, the writ petitioner preferred the aforesaid

contempt case by placing reliance on the communication dated

16.02.2010 issued by the Bank to show that payment of invoked bank

guarantee had been put in clearing on 13.02.2010, which would show

that on the date of hearing, i.e. 10.02.2010, a false statement was

made. The Court dismissed the contempt case as it was shown that

the bankers cheque in favour of DDA had been prepared on

01.02.2010 by the bank, however, the same was cleared on

13.02.2010. The Court accepted the submission of the bank's counsel

that on preparation of the bankers cheque, the bank guarantee stood

encashed.

39. I would have agreed with the aforesaid submission of learned

ASG, had the order dated 25.10.2010 merely stated that " in case the

bank guarantees have already been encashed, it is made clear that

there would be no interim order". However, while passing the order

dated 25.10.2010, I was conscious of the fact that so far as the

petitioners bank accounts were concerned, they had already been

debited on 23.10.2010, as respondent nos.2 and 3 banks had already

prepared pay orders in favour of the DDA. Details of these pay orders

were also recorded in my order dated 25.10.2010. Pertinently, I had

directed that "in case the said pay orders have already been encashed,

it is made clear that there would be no interim order".

40. The "encashment" referred to by me in the order dated

25.10.2010 pertained to the encashment of the pay orders into the

account of the respondent DDA. The purport of the said order was that

if the monies covered by the bank guarantees/pay orders have already

been credited to the account of the DDA, there would be no interim

order. The aforesaid aspect becomes clear upon reading of the latter

part of the order. The Court had clearly observed that "in case the pay

order of Rs.33 crores has not been encashed and the amount not

credited to the account of the respondent/DDA, status quo shall be

maintained in respect thereof". A similar order was made in respect of

the pay order of ` 60 crores issued by State Bank of India.

41. The aforesaid order was passed on 25.10.2010, whereas the

pay orders had already been made and delivered to the DDA by the

respective banks on 23.10.2010. It was, therefore, not clear at the

time of passing of the order, whether the monies covered by the pay

orders had, or had not, travelled into the account of the respondent

DDA. I may note that on 25.10.2010, upon a query raised by the Court

as to whether any advance notice of the petition had been served on

the respondent DDA, the learned counsel for the petitioner had shown

to the Court a copy of an email communication stated to have been

issued to a standing counsel of DDA. Despite the said advance notice,

there was no appearance on behalf of the DDA on 25.10.2010 before

the Court. Therefore, the aforesaid aspect was not clarified before the

Court. As it transpires, the pay orders had not been encashed into the

account of the respondent DDA on 25.10.2010. I, therefore, reject the

aforesaid submission of learned ASG. It cannot be said that the

present petition has become infructuous, as the pay orders of ` 33

crores and ` 60 crores had not been encashed into the account of the

respondent DDA on 25.10.2010.

42. During the course of hearing, another grievance raised by the

learned ASG was that the respondent no.3 State Bank of India had

acted in collusion and connivance with the petitioner. The grievance is

that when there was a single bank guarantee of ` 150 crores issued by

respondent no.3 State Bank of India, there was no justification for

making two pay orders of ` 90 crores and ` 60 crores. She submits

that the State Bank of India should have prepared only one pay order

of ` 150 crores in response to the invocation of the bank guarantee by

the respondent DDA on 23.10.2010.

43. She had submitted that the respondent DDA had deposited

both the pay orders issued by the State Bank of India for ` 90 crores

and ` 60 crores simultaneously. However, only the pay order for ` 90

crores had been encashed and credited into the account of the

respondent DDA, and the second pay order for ` 60 crores had not

been encashed and credited into the account of the respondent DDA.

44. Upon the aforesaid grievance being raised, vide order dated

11.11.2010, this Court had directed the State Bank of India to file a

specific affidavit to explain its conduct in issuing two pay orders for `

90 crores and ` 60 crores upon invocation of a single bank guarantee

of ` 150 crores, and also to explain as to how the pay order of ` 90

crores was credited into the account of the DDA, whereas the second

pay order of ` 60 crores was not so credited, even though both of them

had been deposited at the same time.

45. Sh. Dinesh Chandra Mamgain, the Chief Manager, State Bank

of India, B.O. Overseas, STC Building, Janpath, New Delhi has filed his

affidavit dated 16.11.2010 in compliance of the said order. So far as

the aspect of issuance of two pay orders of ` 90 crores and ` 60 crores

is concerned, it is explained that the computer software of State Bank

of India does not permit issuance of a single bankers cheque in excess

of ` 99,99,999.99. Therefore, a single pay order for ` 150 crores could

not have been issued. Accordingly, two pay orders for ` 90 crores and

` 60 crores were issued on 23.10.2010. It is further explained that the

court order dated 25.10.2010 was served upon the State Bank of India

on 25.10.2010 itself. By that time, neither of the aforesaid two pay

orders had been cleared for payment in the normal course of business.

Accordingly, upon receipt of the Court order, the State Bank of India

had marked "stop payment" in respect of the bankers cheque/pay

order of ` 60 crores, while the other bankers cheque/pay order for ` 90

crores was cleared in due course of banking business on 26.10.2010. It

was further stated that the account of the respondent DDA was

credited with the proceeds of the pay order of ` 90 crores on

26.10.2010. The respondent State Bank of India has, therefore, stated

that it has acted in compliance of the court order dated 25.10.2010. It

has further been disclosed that the amount of ` 60 crores is still lying

outstanding in the bank office account, pending further instructions

from this Court.

46. The affidavit filed by the Chief Manager, State Bank of India

has not been disputed/controverted by the DDA. Therefore, the

explanation furnished by State Bank of India is accepted and the

grievance made by the respondent DDA in this regard is rejected.

47. The submission of the learned Additional Solicitor General Ms.

Indira Jaisingh is that the petitioner had not completed the project

within the specified time. She submits that in its communication dated

16.10.2010 the respondent/DDA had not only complained about the

defects existing at the site but had specifically stated that "the

basement flooring at the places and waterproofing of the lift wells have

not been completed till date." It was further stated in this

communication that an amount of ` 83.70 crores "....has become due

to be paid to DDA on a/c of non-completion of milestone No.8 and 9."

She submits that the contention of the petitioner that the only stand of

the DDA is with regard to existing defects, and not with regard to non-

completion of the work is incorrect.

48. She further submits that liquidated damages have been

provided under the PDA in Annexure-3 as extracted hereinabove.

These liquidated damages accrue on day-to-day basis. The respondent

had earlier quantified the liquidated damages in its communication

dated 9.6.2010 at ` 13.45 crores. Since then, with the passage of time

and non-completion of the works under the Project Development

Agreement, further liquidated damages had accrued and,

consequently, on 16.10.2000 the respondent/DDA had made a demand

of ` 83.70 crores. She submits that even thereafter, liquidated

damages have been accruing at the rate indicated in Annex 3.

49. She further submits that under clause 1.1.20 of the Project

Development Agreement, the project completion date is required to be

certified by the Monitoring Committee constituted under the said

agreement. The Monitoring Committee has representatives of the

petitioner, the respondent and independent members. The Monitoring

Committee has till date not recorded the project completion date, even

though, the project had to be completed by 1.4.2010. The Sub-

Committee referred to by the petitioner, as per the petitioners own

showing, is not concerned with the certification of the project

completion date. She further submits that even the achievement of

the 8th and 9th milestones as per Annexure-3 has not been recorded by

the Monitoring Committee.

50. She submits that the petitioner has admitted the said position

in its letter dated 20.10.2010. By reference to the tabulation filed by

the petitioner as Annexure P-18 which tabulates the dates on which

the towers were delivered to the DDA, she submits that Tower no.T-34

was delivered by the petitioner only on 24.07.2010, even as per its

own showing. However, in terms of Annexure-3 of the Project

Development Agreement, the same should have been delivered by

1.4.2010. She points out that in its rejoinder the petitioner admits that

only the residential flats have been delivered by it, and that too

belatedly. However, the definition of the expression "Project"

contained in the Project Development Agreement is much wider to

mean complete construction and development of the ready-to-use

residential facility at the project site (see clause 1.1.19). "Residential

Facility" means all use, building blocks, common areas, parking base,

roads, parks, landscaping etc. and other associated facilities like

sewerage, water, power, internet, telephone arrangements etc. at the

project site (see clause 1.1.22).

51. She submits that the temporary occupancy permit granted by

the respondent/DDA on 3.9.2010 cannot be used by the petitioner to

contend that the works under the project had been completed. She

submits that perusal of the letter dated 3.9.2010 issued by the DDA

granting temporary occupancy permit itself shows that according to

DDA "the completion certificate cannot be issued at this stage due to

non-compliance of the provisions of the Building Bye-Laws, 1983".

However, with a view to facilitate use and occupation of the flats

during Commonwealth Games 2010, temporary occupancy permit was

granted which was to remain valid till Commonwealth Games Village

was handed back by the Organizing Committee after the

Commonwealth Games, 2010. This communication made it clear that

the temporary occupancy permit was being issued without prejudice to

the show cause notice dated 22.7.2010 and the sealing-cum-

demolition order dated 20.8.2010 issued under Sections 30 and 31 of

the Delhi Development Act, 1957 and other communications issued in

that regard. The issuance of temporary occupancy permit expressly did

not create any right or basis whatsoever for processing of completion

certificate under clause 7.6 of the Building Bye-Laws.

52. She submits that the nation was faced with a serious situation

due to delays and defaults on the part of the petitioner in failing to

complete the project on time. There was immense adverse publicity

for the DDA and for the nation as a whole in India, and abroad. The

respondent/DDA had no option at that stage but to carry out some of

the works which the petitioner was obliged to undertake under the

Project Development Agreement. Thousands of athletes and officials

who were scheduled to attend the Commonwealth Games, 2010 had to

be put up in the Commonwealth Games Village, and it was necessary

to issue the temporary occupancy permit even though the project was

not completed by the petitioner. She places reliance on the

photographs filed along with the reply of the DDA to show the state of

affairs as existing at the site as on 7.8.2000. These photographs show

that there was large scale collection of garbage/malba at the site

which had not been cleared. No landscaping work had been

undertaken and there was collection of water in the basement floors of

the Apartment Blocks. She submits by reference to these photographs

that the water had collected in the basement floors of the Apartment

Blocks as the petitioner failed to carry out water proofing work and the

said situation has continued even till after the conclusion of the games.

Photographs taken as late as on 29th and 30th October, 2010 by the

respondent DDA of the apartment blocks have been placed on record

in support of the aforesaid submission.

53. Ms. Jaisingh submits that the present is not a case of a fraud

being played upon by the respondent/DDA upon the petitioner or the

issuing banks. She submits that the existence of disputes between the

parties with regard to the breach of the contract by one or the other

party, and the invocation of the bank guarantee in said circumstances,

does not tantamount to a fraud by the beneficiary. The allegations of

the petitioner do not relate to a fraud committed by the DDA in the

making of the bank guarantee or in its invocation. The allegation is

merely that it is the DDA which is in default. She submits that the

issue relating to default of one or the other party is an arbitral dispute.

However, the right of the respondent/DDA to invoke the performance

bank guarantee/security cannot be interdicted merely because the said

issue has not been resolved as of now. She further submits that the

fraud should pertain to the making of the bank guarantee. It is not

even the petitioner's case that the said bank guarantees were

obtained by the respondent by playing a fraud on the petitioner or

respondents No.2 and 3 banks. She submits that neither respondent

No.2 nor respondent No.3 have found the invocation of the bank

guarantees in question to be fraudulent, and this is evident from the

fact that they have honoured the said invocation and prepared pay

orders in favour of the respondent/DDA for the amount of the bank

guarantees and delivered the same to the DDA.

54. She submits that it is not even the petitioner's case that the

project is complete as per the Project Development Agreement. Even

if it is partially incomplete, it cannot be said that the same is complete.

55. With regard to the grievance of the petitioner that the bank

guarantees had been invoked even prior to expiry of seven days from

the date of receipt of the notice dated 16.10.2010, she submits that

the respondent was justified in invoking the said guarantees upon

receipt of the communication dated 20.10.2010 of the petitioner. In the

said communication the petitioner had denied any liability whatsoever,

and had even gone to the extent of demanding return of the bank

guarantees. The petitioner did not admit any part of the liability

towards liquidated damages or other damages, and repudiated the

right of the respondent to impose liquidated damages and invoke the

performance securities/bank guarantees. She also submits that the

petitioner, from the very beginning, was in default and did not even

have the resources to complete the works under the Project

Development Agreement. The petitioner had been pleading that due

to economic slowdown and the existing court cases they were not able

to raise the required funds for the completion of the project by

selling/booking their share of the apartments. They sought financial

assistance from the respondent/DDA to complete the project. To bail

out the petitioner and to ensure that the project is completed before

the Commonwealth Games, 2010, the respondent/DDA had agreed to

purchase a large number of flats which fell to the share of the

petitioner. She places reliance on the minutes of the meeting called by

the Lt. Governor on 24.4.2009, where the decision to purchase the flats

from the petitioner was taken. She further submits that disputes had

arisen between the petitioner and its sub-contractors during the

execution of the works, which also resulted in delays and defaults on

the part of the petitioner.

56. Ms.Jaisingh submits that right to invoke the performance

security is available to DDA upon the occurrence of an event of default.

It is not limited only to the non-compliance of the milestones or

persistent delays by the Project Developer in implementation of the

project. It can be invoked for other reasons as well. She places

reliance on language of Clause 6.2 in this regard which uses the

expression "including but not limited to ........" while dealing with the

reasons for which the Bank Guarantees may be invoked. The said right

to invoke the performance security is not limited to the four specific

instances mentioned in Clause 6.2 as extracted hereinabove as those

instances are mere illustrations. She points out that under Clause 12.1

the failure to achieve completion within the time period set out under

the agreement is an event of default.

57. Without prejudice to the aforesaid submissions, Ms. Jaisingh

also submits that the bank guarantee of ` 150 crores issued by the

State Bank of India could not have been successively encashed for

varying amounts. She submits that the DDA was, therefore, entitled to

invoke the same for the entire amount of ` 150 crores, as invoking the

said guarantee for a lesser amount would have resulted in the bank

guarantee for the remaining balance amount lapsing.

58. She further submits that the balance of convenience is in

favour of the DDA, as DDA is a statutory corporation and its solvency

cannot be doubted. In case the petitioner succeeds in the arbitral

proceedings that may be initiated between the parties, the respondent

would restitute the amount. She further submits that so far as the

petitioner is concerned, it bank accounts have already been debited

and, therefore, no prejudice would be suffered by it if the amounts are

credited to the account of the respondent/DDA. She further offered

that this Court may subject the respondent/DDA to such terms and

conditions as may be deemed just and equitable in relation to the

amount covered by the bank guarantees.

59. In support of her submissions she has placed reliance upon

the following decisions:-

(i) Dwarikesh Sugar Industries Ltd. v. Prem Heavy Engineering Works Pvt. Ltd., 1997 (6) SCC 450;

(ii) BSES Ltd. (Now Reliance Energy Ltd.) v. Fenner India Ltd. & Anr., 2006 (2) SCC 728; and

(iii) U.P. State Sugar Corporation v. Sumac International Ltd., 1997 (1) SCC 568

60. In his rejoinder, Mr. Kapur has submitted that since the bank

guarantees in question are valid till 31.12.2010 and they can be

invoked for an amount upto ` 33 crores and ` 150 crores respectively,

the respondent/DDA is wrong in contending that if the said guarantees

had been invoked for lesser amount, the same could not have been re-

invoked in parts for the remaining balance amounts during their

currency. He further submits that if that was the apprehension in the

mind of the respondent/DDA, then the invocation of the bank

guarantee of ` 33 crores furnished by the respondent No.2/Bank can

not been explained, as the amount claimed in the communication

dated 16.10.2010 was only ` 83.70 crores. He also submits that the

learned ASG is not right in her submission that the fraud has to

necessarily pertain to the making of the bank guarantee, and does not

relate to its invocation. He further submits that the petitioner should

not be required to furnish a fresh bank guarantee in terms of clause

6.2, as it would cause irretrievable injustice to the petitioner.

61. Having heard learned counsel for the parties, considered their

respective submissions, and in view of the settled position of the law

on the subject, I am of the view that the petitioner is not entitled to

seek a restraint on the encashment of the bank guarantees in question

for the amount of ` 183 crores, or to any other relief as prayed for.

62. I may first deal with the submission of learned ASG that the

bank guarantees in question could not have been invoked partially and

repeatedly, and that if a partial invocation had been resorted to by the

respondent DDA, the same would have lapsed for the remaining

balance amounts even before the expiry of the period of currency of

the said guarantees.

63. On this submission being made, learned counsel for the

respondent State Bank of India was asked by the Court to specifically

take instructions as to the normal banking practice in such situations.

Learned counsel for the State Bank of India has stated that a bank

guarantee, unless there is a limitation contained in its terms that it

could be invoked only once, could be invoked repeatedly during its

currency, partially, so that the aggregate amount invoked by the

beneficiary does not exceed the maximum amount payable under the

bank guarantee.

64. A perusal of the bank guarantees in question dated

12.06.2008 (issued by State Bank of Patiala), the validity whereof was

extended vide extension dated 27.09.2010; and the bank guarantee

dated 11.06.2008 (issued by State Bank of India), the validity whereof

was extended vide extension dated 27.09.2010 upto 31.12.2010, does

not support the submission made by Ms. Jaisingh. The said bank

guarantees, inter alia, state that the said banks "do hereby

unconditionally and irrevocably undertake to pay to DDA an amount

not exceeding ... ... without any demur or merely on a demand in

writing from DDA, received by the bank on or before ... ... stating that

the amount claimed is due and payable by project developer. Any

such demand received by the bank on or before ... ... shall be

conclusive as regards the amount due and payable by the bank under

this guarantee. However, the banks liability to this guarantee shall be

restricted to an amount not exceeding ... ... ...". The bank guarantees

further recite "our liability under this agreement shall not exceed ... ....

..." It further states "we shall be liable to pay guaranteed amount or

any part thereof only and only if you serve upon us a written claim or

demanded on or before ... ... ...".

65. From the aforesaid language used in the bank guarantees in

question, it cannot be inferred that there is any limitation therein that

they could be invoked only once. The upper limit of the amounts for

which these bank guarantees were furnished, have been indicated in

the respective guarantees. Therefore, up to the upper limit/ceiling

fixed in the said bank guarantees, the beneficiary could invoke the

guarantees repeatedly during their currency, such that the total

amount invoked/drawn on the bank guarantees does not exceed the

upper limit/ceiling amount for which they are furnished.

66. Therefore, the alternate submission of Ms. Jaisingh that the

DDA had no option, but to invoke the entire amount of bank guarantee

of ` 183 crores cannot be accepted. As pointed out by Mr. Kapur, if the

apprehension of the DDA was that partial invocation was not

permissible in respect of the two bank guarantees in question, the DDA

should have invoked only one bank guarantee issued by State Bank of

India, which was for an amount of ` 150 crores, and there was no need

to invoke bank guarantee issued by State Bank of Patiala for ` 33

crores.

67. I may now deal with the submission of Ms. Jaisingh that it is

only a fraud in the making of the bank guarantee that would justify the

grant of an injunction against its invocation, and that the fraud in the

invocation of the bank guarantee would not justify the grant of

injunction against its invocation. The aforesaid submission of Ms.

Jaisingh is not supported by the case law placed on record. In

Hindustan Steel Works Construction Ltd. (supra), the Supreme

Court observed as follows:

"A demand by the beneficiary under the bank guarantee may become fraudulent not because of any fraud committed by the beneficiary while executing the underlying contract but it may become so because of subsequent events or circumstances. We see no good reason why the courts should not restrain a person making such a fraudulent demand from enforcing a bank guarantee."

This argument has also been rejected by the Division Bench of

this Court in Humboldt Wedag India P. Ltd. (supra) in paragraph 18.

Therefore, the aforesaid submission of Ms. Jaisingh cannot be

accepted, and is rejected.

68. The law with regard to enforcement of an irrevocable and

unconditional bank guarantee payable on demand without demur, and

the circumstances in which the courts may grant an injunction against

the encashment of such a bank guarantee has been the subject matter

of various decisions of the Supreme Court from time to time.

69. I may first refer to the decision of the Supreme Court in U.P.

State Sugar Corporation v. Sumac International Limited, 1997

(1) SCC 568. In this case, the appellant corporation entered into a

contract with the respondent company for setting up a complete sugar

plant. The contract contained the stipulation regarding time for

completion of the work. The respondent was also required to furnish

bank guarantees for due delivery and for advance price to be paid by

the appellant to the respondent. The guarantees were irrevocable in

nature, payable by the guarantor to the appellant beneficiary on

demand, without demur. It was provided that the appellant shall be

the sole judge of whether, and to what extent, the amount had become

recoverable from the respondent, or whether the respondent had

committed any breach of the terms of the agreement. The bank

guarantee further provided that the right of the appellant to recover

from the guarantor any amount shall not be affected or suspended by

reason of any disputes that might be raised by the respondent as

regard its liability or on the ground that proceedings were pending

before any tribunal/arbitrator/court with regard to such dispute.

70. The contract was terminated by the appellant on the ground

of the respondents failure to complete the work within the time

granted under the contract as extended. The appellant also invoked

the bank guarantees furnished by the respondent. The respondent

filed a petition under section 20 of the Arbitration Act, 1940 for

appointment of an arbitrator and also filed applications for interim

relief under section 41(b) of the Arbitration Act, 1940 to seek stay

against encashment of the bank guarantees. The Civil Judge dismissed

the application, but in revision, the High Court allowed the same and

granted injunction restraining the appellant from enforcing the bank

guarantee. The Supreme Court allowed the appeal preferred by the

beneficiary, UP State Sugar Corporation.

71. The Supreme Court in this decision referred to its earlier

decisions and observed as follows:

"12. The law relating to invocation of such bank guarantees is by now well settled. When in the course of commercial dealings an unconditional bank guarantee is given or accepted, the beneficiary is entitled to realize such a bank guarantee in terms thereof irrespective of any pending disputes. The bank giving such a guarantee is bound to honour it as per its terms irrespective of any dispute raised by its customer. The very purpose of giving such a bank guarantee would otherwise be defeated. The courts should, therefore, be slow in granting an injunction to restrain the realization of such a bank guarantee. The courts have carved out only two exceptions. A fraud in connection with such a bank guarantee would vitiate the very foundation of such a bank guarantee. Hence if there is such a fraud of which the beneficiary seeks to take advantage, he can be restrained from doing so. The second exception relates to cases where allowing the encashment of

an unconditional bank guarantee would result in irretrievable harm or injustice to one of the parties concerned. Since in most cases payment of money under such a bank guarantee would adversely affect the bank and its customer at whose instance the guarantee is given, the harm or injustice contemplated under this head must be of such an exceptional and irretrievable nature as would override the terms of the guarantee and the adverse effect of such an injunction on commercial dealings in the country. The two grounds are not necessarily connected, though both may coexist in some cases. In the case of U.P. Coop. Federation Ltd. v. Singh Consultants and Engineers (P) Ltd. [(1988) 1 SCC 174] which was the case of a works contract where the performance guarantee given under the contract was sought to be invoked, this Court, after referring extensively to English and Indian cases on the subject, said that the guarantee must be honoured in accordance with its terms. The bank which gives the guarantee is not concerned in the least with the relations between the supplier and the customer; nor with the question whether the supplier has performed his contractual obligation or not, nor with the question whether the supplier is in default or not. The bank must pay according to the tenor of its guarantee on demand without proof or condition. There are only two exceptions to this rule. The first exception is a case when there is a clear fraud of which the bank has notice. The fraud must be of an egregious nature such as to vitiate the entire underlying transaction. Explaining the kind of fraud that may absolve a bank from honouring its guarantee, this Court in the above case quoted with approval the observations of Sir John Donaldson, M.R. in Bolivinter Oil SA v. Chase Manhattan Bank [(1984) 1 All ER at p.351).

"The wholly exceptional case where an injunction may be granted is where it is proved that the bank knows that any demand for payment already made or which may thereafter be made will clearly be fraudulent. But the evidence must be clear both as to the fact of fraud and as to the bank's knowledge. It would certainly not normally be sufficient that this rests on the uncorroborated statement of the customer, for irreparable damage can be done to a bank's credit in the relatively brief time which must elapse between the granting of such an injunction and an application by the bank to have it charged."

This Court set aside an injunction granted by the High Court to restrain the realisation of the bank guarantee.

13. The same question came up for consideration before this Court in Svenska Handelsbanken v. Indian Charge Chrome [(1994) 1 SCC 502]. This Court once again reiterated that a confirmed bank guarantee/irrevocable letter of credit cannot be interfered with unless there is established fraud or irretrievable injustice involved in the case. Irretrievable injury has to be of the nature noticed in the case of Itek Corpn. v. First National Bank of Boston [566 Fed. Supp. 1210]. On the question of fraud this Court confirmed the observations made in the case of U.P. Coop. Federation Ltd. and stated that the fraud must be that of the beneficiary, and not the fraud of anyone else.

14. On the question of irretrievable injury which is the second exception to the rule against granting of injunctions when unconditional bank guarantees are sought to be realised the court said in the above case that the irretrievable injury must be of the kind which was the subject-matter of the decision in the Itek Corpn. case. In that case an exporter in USA entered into an agreement with the Imperial Government of Iran and sought an order terminating its liability on stand by letters of credit issued by an American Bank in favour of an Iranian Bank as part of the contract. The relief was sought on account of the situation created after the Iranian revolution when the American Government cancelled the export licences in relation to Iran and the Iranian Government had forcibly taken 52 American citizens as hostages. The US Government had blocked all Iranian assets under the jurisdiction of United States and had cancelled the export contract. The Court upheld the contention of the exporter that any claim for damages against the purchaser if decreed by the American Courts would not be executable in Iran under these circumstances and realisation of the bank guarantee/letters of credit would cause irreparable harm to the plaintiff. This contention was upheld. To avail of this exception, therefore, exceptional circumstances which make it impossible for the guarantor to reimburse himself if he ultimately succeeds, will have to be decisively established. Clearly, a mere apprehension that the other party will not be able to pay, is not enough. In Itek case there was a certainty on this issue. Secondly, there was good reason, in that case for the Court to be prima facie satisfied that the guarantors i.e. the bank and its customer would be found

entitled to receive the amount paid under the guarantee." (emphasis supplied)

72. The Supreme Court also quoted from its decision in State of

Maharashtra v. National Construction Company, 1996 (1) SCC

735 the following passage:

"The rule is well established that a bank issuing a guarantee is not concerned with the underlying contract between the parties to the contract. The duty of the bank under a performance guarantee is created by the document itself. Once the documents are in order the bank giving the guarantee must honour the same and make payment ordinarily unless there is an allegation of fraud or the like. The courts will not interfere directly or indirectly to withhold payment, otherwise trust in commerce internal and international would be irreparably damaged. But that does not mean that the parties to the underlying contract cannot settle the disputes with respect to allegations of breach by resorting to litigation or arbitration as stipulated in the contract. The remedy arising ex contractu is not barred and the cause of action for the same is independent of enforcement of the guarantee."

73. After referring to the aforesaid decision, the Supreme Court,

in para 16, observed as follows:

"16. Clearly, therefore, the existence of any dispute between the parties to the contract is not a ground for issuing an injunction to restrain the enforcement of bank guarantees. There must be a fraud in connection with the bank guarantee. In the present case we fail to see any such fraud. The High Court seems to have come to the conclusion that the termination of the contract by the appellant and his claim that time was of the essence of the contract, are not based on the terms of the contract and, therefore, there is a fraud in the invocation of the bank guarantee. This is an erroneous view. The disputes between the parties relating to the

termination of the contract cannot make invocation of the bank guarantees fraudulent."

74. Pertinently, in UP State Sugar Corporation (supra), the

appellant/beneficiary was a sick industrial company in respect of which

a reference was pending before the Board For Industrial and Financial

Reconstruction (BIFR) under the Sick Industrial Companies (Special

Provisions) Act, 1985 (SICA). It was contended that if the appellant

were to encash the bank guarantees and receive the amounts, and the

respondent were to eventually succeed in the arbitration proceedings,

it may still not be able to realize its claim from the appellant. The

Supreme Court, however, rejected the said submission by observing

that the mere fact that a reference under SICA is pending before the

BIFR is not sufficient to bring the case in the ambit of "irretrievable

injustice" exception. The Supreme Court held that merely because the

case of the appellant was before the BIFR, it could not be presumed

that the appellant will, in no circumstance, be able to discharge its

obligations. The Supreme Court further held that this was not a

situation of the kind envisaged in the case of Itec Corporation, where

there was no possibility of recovery of any amount from the purchaser.

75. A comparison of the terms of the bank guarantee considered

by the Supreme Court in the case of UP State Sugar Corporation

(supra), with the terms of the bank guarantees in question (as

extracted herein above) shows that there is marked similarity between

them. In the present case as well, the bank guarantees in question are

unconditional and irrevocable and the respective banks have

undertaken to pay to the DDA without any demur, merely on a demand

in writing from DDA, stating that the amount claimed is due and

payable by the petitioner project developer. The banks have further

undertaken to pay the amounts under the bank guarantees in question

notwithstanding any dispute raised by the petitioner in any manner

whatsoever. The banks have clearly held out in their respective

guarantees that their liability under the guarantees is absolute,

unconditional, unequivocal and irrevocable.

76. A perusal of the petition and the submissions of the learned

senior counsels for the petitioner shows that the petitioner's primary

grievance is that the default has been on the part of the DDA and other

agencies which had led to the present situation, and that the

respondent DDA is unfairly seeking to put the blame on the petitioner

and making the same as a ground for invocation of the bank

guarantees. This is a dispute arising under the PDA, which would have

to be determined in arbitration. The invocation of the bank guarantee

by the DDA, merely because the petitioner raises the aforesaid

disputes, cannot be said to be fraudulent. On their very terms, the

bank guarantees do not require the respondent nos.2 and 3 banks to,

in any way, get embroiled in the claims and counter claims of the

parties with regard to the breach of the PDA by one or the other party.

77. I had the occasion to deal with the law on the subject in CDS

Money Exchange Bureau Pvt. Ltd. v. Thomas Cook & Others,

2007 (95) DRJ 369. In this case, the buyer had got the documentary

credit furnished in favour of the seller. The analysis of the law on the

subject contained in the said decision may usefully be reproduced:

"21. The law with regard to grant or refusal of injunction on encashment of bank guarantees, at the instance of the party at whose behest the bank guarantees have been issued, is well settled. In Federal Bank Ltd. v. V.M. Jog Engineering Ltd. and Ors. (2001) 1 SCC 663 the Hon'ble Supreme Court, after reviewing the earlier decisions, observed that courts ought not to grant injunction to restrain encashment of bank guarantees or letters of credit. There are, however, two exceptions to this rule, viz, fraud and irretrievable damage. The contract of bank guarantee or letter of credit is independent of the main contract between the seller and the buyer. In case of an irrevocable bank guarantee or letter of credit, the buyer cannot obtain injunction against the final payment on the ground that there was a breach of the contract by the seller. The bank is to honour the demand for encashment if the seller prima facie complies with the terms of the bank guarantee or the letter of credit, namely, if the seller produces the documents enumerated in the bank guarantee or the letter of credit. If the bank is satisfied on the basis of the documents that they are in conformity with the list of documents mentioned in the bank guarantee or the letter of credit and there is no discrepancy, it is bound to honour the demand of the seller for encashment. It is not permissible for the bank to refuse the demand on the ground that the buyer is claiming that there is a breach of contract. This obligation of the bank under the documents has nothing to do with any dispute as to breach of contract between the seller and the buyer.

22. The Supreme Court also observed that in order to obtain injunction against the issuing bank, it is necessary to prove that the bank had knowledge of the fraud. Hon'ble Supreme Court relied on the observations of Kerr, J. in R.D. Harbottle (mercantile) Ltd. v. National Westminister Bank Ltd. (1978) QB 146 : (1977) 2 All ER 862 to state that

irrevocable Letters of Credit are "the lifeblood of international commerce" and also observed:

Except possibly in clear cases of fraud of which the banks have notice, the courts will leave the merchants to settle their disputes under the contracts by litigation or arbitration.... Otherwise, trust in international commerce could be irreparably damages.

Quoting from the several other English decisions, the Hon'ble Supreme Court observed:

Denning M.R. stated in Edward and Owen Engg. Ltd. v. Barclays Bank International Ltd. that "the only exception is where there is a clear fraud of which the bank had notice". Browne, L.J. said in the same case: "but it is certainly not enough to allege fraud, it must be established and in such circumstances, I should say, very clearly established". In Bolivinter Oil S.A. v. Chase Manhattan Bank AII ER at p. 352, it was said

where it is proved that the bank knows that any demand for payment already made or which may thereafter be made will clearly be fraudulent. But the evidence must be clear, both as to the fact of fraud and as to the bank's knowledge. It would certainly not normally be sufficient that this rests on the uncorroborated statement of the customer, for irreparable damage can be done to a bank's credit in the relatively brief time 'before the injunction is vacated.

Thus, not only must "fraud" be clearly proved but so far as the bank is concerned, it must prove that it had knowledge of the fraud. In United Trading Corporation S.A. v. Allied Arab Bank it was stated that there must be proof of knowledge of fraud on the part of the bank at any time before payment."

78. In the facts as pleaded by the parties, it cannot be said that

the fraud pleaded by the petitioner is an established fraud, or even a

prima facie established fraud to the knowledge of the issuing bank. It

certainly cannot be said to be a fraud of an egregious nature, i.e. a

fraud which can be said to be outstandingly bad or shocking.

79. The same issue rose before the Supreme Court in BSES

Limited (supra). On a reading of para 2 of the said decision, I am

reminded of the submission made by Mr. Kapur that the invocation of

the bank guarantee is not in good faith and that the petitioner has

been made a scapegoat by the DDA. Para 2 of the decision reads as

follows:

"2. This is one more instance of an injunction being sought against a beneficiary seeking to enforce his/her rights under a bank guarantee, albeit with a novel averment that "lack of good faith" or "enforcing with an oblique purpose" constituted further exceptions to the general rule against intervention."

80. In this case, the appellant and the respondent entered into a

"wrap-around agreement", under which the respondent undertook to

perform the contractual obligation of the appellant in relation to the

contract awarded to it by M/s Godawari Sugars Ltd. on a turn key basis.

Clause 4 of the agreement provided that in case of any material

breach of any or all the contracts, BSES shall have the right to embark

upon the retentions and encashment of bank guarantees of all the

contracts. The bank guarantees were encashed and the respondent

invoked the arbitration agreement contained in the work/purchase

orders.

81. A petition under section 9 of the Act was preferred to seek a

declaration that the appellant shall not be entitled to invoke the bank

guarantees. Eventually, the matter travelled to the Supreme Court.

The Supreme Court, inter alia, held as follows:

"26. Accordingly, we are prima facie not satisfied that performance had been duly and satisfactorily certified. Under the terms of the "wrap-around agreement", the appellant was entitled to encash all or any of the bank guarantees for breach of the first respondent‟s obligations under any one of the contracts. In our view, it is the case of the appellant that there was no satisfactory performance of the contract, as a result of which, the appellant was justified in encashing the bank guarantee concerned. Indeed, as per the terms of the bank guarantee itself, the appellant is the best judge to decide as to when and for what reason the bank guarantees should be encashed. Further, it is no function of the second respondent Bank, nor of this Court, to enquire as to whether due performance had actually happened when, under the terms of the guarantee, the second respondent Bank was obliged to make payment when the guarantee was called in, irrespective of any contractual dispute between the appellant and the first respondent. Indeed, in similar circumstances, this Court in General Electric Technical Services Co. Inc. v. Punj Sons (P) Ltd.,[(1991) 4 SCC 230] held:

"The Bank must honour the bank guarantee free from interference by the courts. Otherwise, trust in commerce internal and international would be irreparably damaged. It is only in exceptional cases that is to say in case of fraud or in case of irretrievable injustice, the court should interfere. ... The nature of the fraud that the courts talk about is fraud of an „egregious nature as to vitiate the entire underlying transaction‟. It is fraud of the beneficiary, not the fraud of somebody else."

29. There is no dispute that arbitral proceedings are pending. In fact, we were shown that one of the disputes referred to arbitration is whether the bank guarantees are null and void. Further, one of the substantive prayers in the arbitration made on behalf of the first respondent, is to make an award declaring the four bank guarantees unenforceable, illegal, void and liable to be discharged. Further, there is also a prayer for permanent injunction to restrain the appellant from encashing the bank guarantees. Therefore, since this prayer is already pending before the Arbitral Tribunal, we see no situation of "irretrievable injustice" if, at the present moment, the appellant is allowed to encash the bank guarantees. For justice can always be rendered to the first respondent, if it

succeeds before the arbitrators. Nor do we see any special equity in favour of the first respondent, when there is in fact a dispute that performance was prima facie not satisfactory, which enabled the appellant to encash all or any of the four bank guarantees." (emphasis supplied)

82. In the light of the aforesaid decision, the submission of Mr.

Kapur that neither the monitoring committee, nor the sub-committee

have till date returned a finding with regard to the attainment of

milestone nos.8 and 9, is neither here nor there. The respondent

banks, under the terms of their respective guarantees, are not

concerned as to whether or not the said milestones have, in fact, been

achieved or not. Even if they have been achieved, as contended by

the petitioner, the invocation of the bank guarantees would not

tantamount to playing a fraud of an egregious nature by the

respondent DDA either upon the petitioner or the respondent banks.

The respondent DDA has been left to judge as to when, and for what

reasons, the bank guarantee should be invoked. It is not the function

of the respondent banks or even of this Court to enquire as to whether

due performance of the contractual obligations had actually taken

place or not, as, under the terms of the guarantees, the respondent

banks are obliged to make payment when the guarantee is called in,

irrespective of any contractual disputes between the petitioner and the

respondent no.1.

83. The submission of Mr. Kapur that the invocation of the bank

guarantees for Rs.183 crores is fraudulent because the respondent had

itself quantified its liquidated damages @ Rs.83.70 crores in its

communication dated 16.10.2010 also has no merit. Firstly, the said

communication shows that the demand for Rs.83.70 crores as

liquidated damages was made not only on account of defects, but on

account of non completion of the project.

84. As pointed out by the learned ASG, the liquidated damages

were arising on a day to day basis in terms of Annex III Schedule III to

the Project Development Agreement. The performance security could

be invoked by the DDA under clause 6.2, upon the occurrence of an

event of default. The exercise of the right to invoke the performance

security was not limited to an event of non compliance of the

milestones or persistent delays by the project developer in the

implementation of the project. The contract merely recites, as an

instance, that the performance security may be invoked, if the project

developer is unable to deposit the liquidated damages for delay in

achieving any milestone for the amount as computed under Schedule

III. Apparently, the communication dated 16.10.2010 was issued by

the DDA to the petitioner in the light of clause 6.2(i). However, the

respondent was entitled to invoke the said performance security to

claim not just the liquidated damages, but all other amounts that it

may claim.

85. The submission of Mr. Kapur that the DDA, on the date of

invocation of the performance security, was not entitled to recover the

sum of Rs.183 crores, by reference to the tabulation set out in the

reply of the DDA, misses the point that the said performance security

could be invoked upon occurrence of an event of default. The amount

that could be recovered from the said performance security was not

limited merely to the liquidated damages provided under the contract.

Even according to the petitioner, the delay in the completion of the

project (for which the petitioner holds the respondent DDA and other

agencies responsible) had indeed resulted in negative publicity for the

organizers including the respondent DDA. If, in the estimation of the

DDA, it was entitled to invoke the entire performance security

furnished by the petitioner, that is the business/commercial decision of

the DDA, with which the Court cannot interfere in these proceedings.

As the bank guarantees in question are unconditional; the banks have

undertaken to make payment of the amounts demanded

unconditionally; without any demur; without getting embroiled in the

disputes between the parties (including the dispute as to whether the

respondent DDA should have limited the invocation of the bank

guarantees in question to claim only the liquidated damages claimed

to have been suffered as on the date of the invocation), the court

cannot go into these aspects in these proceedings. That decision has

to be left to the wisdom of the DDA, as the parties have so agreed. If,

eventually, the arbitral tribunal finds that the invocation of the bank

guarantees was not partly, or wholly, justified, the arbitral tribunal can

always direct restitution of the amount with or without interest and/or

damages.

86. I may now deal with the judgments relied upon by Mr. Kapur

in the course of his arguments. In Humboldt (supra), the Division

Bench of this Court examined the various precedents on the subject of

invocation of bank guarantees/letters of credit and reiterated the

position that the fraud claimed to have been perpetuated by the

beneficiary upon the petitioner and the bank must be of an egregious

nature, meaning that the fraud should lead to gross injustice which

shakes the conscience of the Court, and that the fraud should be

known to the parties and the concerned bank. In this case, the

respondent beneficiary had cancelled the contract partly, and kept the

other part in abeyance. The terms of the bank guarantee, inter alia,

provided that the bank would pay the amount provided that the

beneficiary confirms to the bank at the same time in writing that the

supplier (at whose instance the bank guarantee had been furnished)

had not fulfilled all or any of his contractual obligations as stipulated in

the contract, including but not limited to, delivery of the agreed

quantity and/or the shipment of the product on the date agreed upon

with the purchaser. It further provided that "the liability of the bank as

contained herein shall automatically get reduced proportionately to the

value of such parts of the product (including all machineries and

equipments) that may have been successfully delivered as certified by

the purchaser based on which the advance or on account amount paid

by the purchaser have been adjusted in the corresponding invoices of

the supplier raised with respect to the contract".

87. The beneficiary/purchaser cancelled the order placed upon

the supplier. The reason for the cancellation was stated to be the

unforeseen financial crisis across the world, leading to difficulties in

financial closures of projects. Despite the aforesaid, the purchaser

respondent no.1 sought to invoke the bank guarantee by stating "we

confirm that the supplier has not fulfilled its contractual obligations".

The Division Bench, in view of the aforesaid position, observed "prima

facie, therefore, it was incorrect and fraudulent for respondent no.1 to

state to its banker/respondent no.2 that the appellant had not fulfilled

its contractual obligation".

88. The fact situation in the case in hand, as already discussed, is

starkly different from that dealt with by the Division Bench in

Humboldt (supra). The issue as to who is in breach of the contract,

and other related issues are matters which would need determination

by the arbitral tribunal. Prima facie, it cannot be said that the

petitioner is not in breach of the agreement. It certainly cannot be

said that the invocation of the bank guarantee is a result of a fraud

perpetuated by the DDA on the petitioner and the banks of an

egregious nature, meaning that the fraud would lead to gross injustice

which shakes the conscience of the Court. The decision in Humboldt

(supra) therefore, does not advance the case of the petitioner. I may

note that in paragraph 17 of its decision, upon analysis of the various

case laws, the Division Bench also conclude "that there is no room for

debate that the courts are not to interfere with the encashment of the

letter of credit or the bank guarantee unless the case falls within the

purview of the exceptions laid down by the Apex Court. The first

exception which has been carved out by the courts is that the fraud

perpetrated must be of egregious nature meaning that the said fraud

would lead to gross injustice which shakes the conscience of the court

and the said fraud should be known to the parties and the concerned

bank. If the said fraud is manifest or evident, the court can restrain

the encashment of the bank guarantee".

89. Mr. Kapur has relied upon Regional Manager, Central Bank

of India (supra) to emphasise that the conduct of the respondent, DDA

in invoking the bank guarantee for the entire amount of Rs.183 crores

is fraudulent, as, even according to it, liquidated damages suffered by

it were to the tune of Rs.83.70 crores. The Supreme Court in this case

in paragraph 13 observed that:

"13. ... ... ....

He who comes to the Court with a claim based on falsity and deception cannot plead equity nor the Court would be justified to exercise equity jurisdiction in his favour. An act of deliberate deception with a design to secure something, which is otherwise not due, tantamount to fraud. Fraud is a conduct either by letter or words, which induces the other person or authority to take a

definite determinative stand as a response to the conduct of the former either by words or letter. .. ... ..."

90. I cannot appreciate the relevance of the decision in Regional

Manager, Central Bank of India (supra). I have already held, prima

facie that it cannot be said that the respondent has played a fraud of

an egregious nature either upon the petitioner or the respondent bank.

Consequently, in my view, this decision has no bearing in the facts of

this case. For the same reason, the decision in Bhaurao Dagdu

Paralkar (supra), has no relevance.

91. Mr. Kapur has relied upon Hindustan Steel Works

Corporation Ltd. (supra). However, this decision does not advance

the case of the petitioner, except to the extent that it holds that the

demand made by the beneficiary under the bank guarantee may

become fraudulent not because of any fraud committed by the

beneficiary while executing the underlying contract, but it may become

so because of subsequent events or circumstances.

92. The submission of Mr. Kapur that it would cause irretrievable

injustice to the petitioner, if the bank guarantees are permitted to be

encashed in their entirety, as the petitioner would then be obliged to

provide fresh guarantees for the equivalent amount of Rs.183 crores,

or to face termination of the contract under Clause 6.2 of the PDA, has

no merit. The irretrievable injustice, the Supreme Court holds, should

of the kind dealt with in the case of Itek Corporation. That was a

case, where, if the letter of credit had been permitted to be encahsed,

would have made it impossible for the plaintiff to seek restitution

because of the hostility between United States of America and the

State of Iran, as a result of 52 American citizens being hostaged by the

Iranian Government. The US Government had blocked all Iranian

assets under the jurisdiction of United States and had cancelled the

export contracts. The Court upheld the contention of the American

exporter that any claim for damages against the Iranian purchaser,

even if decreed by the American Courts, would not be executable in

Iran under these circumstances and realization of the bank

guarantees/letter of credit would cause irreparable harm to the

plaintiff. Reference may also be made to the quotation extracted

herein above from the decision in U.P. State Sugar Corporation

(supra).

93. The respondent, DDA is a statutory corporation and there can

be no doubt that in case the petitioner succeeds in establishing its

claims before the arbitral tribunal, the respondent DDA would be in a

position to restitute not only the amount of the bank guarantees, if and

when directed, either in full or in part, but also to pay the damages, if

any, levied upon it. Therefore, it cannot be said that merely because

the petitioner would be required to furnish fresh bank guarantees to

the tune of Rs.183 crores upon encashment of the bank guarantee in

question, the petitioner would suffer irretrievable injustice. The

enforcement of the contractual obligation against a party would not,

normally amount to "irretrievable injustice".

94. The submission that as the completion certificate had been

issued, the respondent is precluded from claiming that the project was

incomplete has absolutely no merit. A perusal of the communication

dated 03.09.2010 issued by the DDA shows that in the opening line

itself, it was stated that "the completion certificate cannot be issued at

this stage due to non-compliance of the provisions of the Building Bye

Laws, 1980 as already communicated to you earlier". The temporary

occupancy permit was granted only to facilitate the use and

occupation of the flats during the Commonwealth Games, 2010. This

was done due to the extraordinary situation, as the nation was faced

with the prospect of not being able to successfully hold the games as

thousands of athletes and officials who would participate in the games

could not have been accommodated, had the games village complex

not been granted the temporary occupancy permit.

95. I also find no merit in the submission of Mr. Kapur that the

invocation was at the behest of the Ministry of Urban Development and

that the DDA has not applied its own independent mind. Merely

because the DDA may have kept the Ministry of Urban Development

informed of the status and may have called for its advice, it does not

mean that the decision to invoke the bank guarantees in question is

not that of the DDA. Eventually, it is the DDA, who is the beneficiary

under the guarantees, who has invoked the guarantees. The

respondent Banks are not required to go behind these letters of

invocation to find out, whether or not, these have been issued at the

behest of another entity.

96. The submission that even seven days time was not granted by

the respondent in its communication dated 16.10.2010 also does not

have any merit. The petitioner in its communication dated 20.10.2010

had sought withdrawal of the letter dated 16.10.2010 issued by the

DDA and had also sought release of its bank guarantees. After the

stand of the petitioner had become known to the respondent DDA, that

the petitioner was not willing to deposit the amount of Rs.83.70 crores,

there was no need for the DDA to wait any further for the expiry of the

week, and there was nothing to prevent the DDA to invoke the bank

guarantees in question on 23.10.2010 itself.

97. The other reliefs prayed for by the petitioner are also not

made out as the petitioner has not even pressed for them, and the

petitioner has not been able to establish a prima facie case in its

favour.

98. For all the aforesaid reasons, I find no merit in this petition

and dismiss the same. It is, however, made clear that no observation

made by me in this order shall come in the way of either party at the

time of determination of the their inter se disputes, claims and counter

claims through arbitration.

Parties are left to bear their respective costs.

(VIPIN SANGHI) JUDGE DECEMBER 20, 2010 sr

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter