Citation : 2010 Latest Caselaw 5508 Del
Judgement Date : 3 December, 2010
THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 03.12.2010
+ CS(OS) No.415/2006
DDA .....Plaintiff
- versus -
M.S. SATNA CEMENT WORKS & ORS. .....Defendants
Advocates who appeared in this case:
For the Plaintiff: Mr. Bhupesh Narula, Advocate.
For the Defendant: Mr. Rakesh Mukhija, Advocate.
CORAM:-
HON'BLE MR JUSTICE V.K. JAIN
1. Whether Reporters of local papers may
be allowed to see the judgment? No.
2. To be referred to the Reporter or not? No.
3. Whether the judgment should be reported
in Digest? No.
V.K. JAIN, J. (ORAL)
IA No.6410/2006 (by defendant No.1 under Order VII Rule 11 CPC)
1. This is an application under Order VII Rule 11 CPC
for rejecting the plaint.
2. The plaintiff has filed this suit for recovery of
Rs.33,65,599/-. It is alleged in the plaint that the
defendant No.1, which is a Unit of defendant No.2 entered
into an Agreement with the plaintiff for supply of 75,000 MT
of non levy cement with 10% deviation. Under the
Agreement, the supply was to commence on 10.5.1985 and
was to be completed by 9.11.1985. It is further alleged that
the defendants, however, commenced supply only in July,
1985 and the last supply was made in February, 1987.
3. Clause 2 of the Agreement between the parties
provides as under:-
"The time allowed for carrying out the supply and the dates of delivery of the materials mentioned in the tender shall be strictly observed by the contractor and shall be deemed to be of the essence of the contract and the contractor shall deliver the materials on or before the dates mentioned in the tender. Should the contractor fail to delivery the materials on or before the stipulated dates, he shall pay as agreed liquidated damages, and not by way of penalty, an amount equal to one per cent or such smaller amount as the Suptdg. Engineer, DDA (whose decision in writing shall be final) may decide on the amount of the estimated cost of the whole work as shown in the tender for every day that the contractor shall exceed the time of the delivery and the delivery of the materials may be in arrears. Provided always that the entire amount of liquidated damges shall not exceed 10% (ten percent) of the estimated cost of the work as shown in the tender."
4. The legal proposition in the matter is well- settled.
The Court while considering an application for rejection of
the plaint can look into only the averments made in the
plaint and the documents filed by the plaintiff. The defence
taken by the defendant is not to be considered while
examining such an application and validity of the
documents filed by the plaintiff also cannot be examined at
this stage.
5. Admittedly, the plaintiff invoked arbitration clause
contained in the Agreement on 18.3.1991 and an Arbitrator
was appointed on 1.5.1991, to adjudicate upon the disputes
between the parties. During pendency of the arbitration
proceedings, the Executive Engineer of plaintiff/DDA
referred the matter to Director (Material Management),
whose decision was to be final and binding between the
parties in terms of Clause 2 of the Agreement, to decide the
amount of liquidated for late supply of the cement. The
Arbitrator vide order dated 21.9.2005 took a view that the
claim pertaining to Clause 2 of the Agreement was beyond
the purview of arbitration. The Director (Material
Management) had, in the meanwhile, vide his decision dated
31.8.2004 decided to levy compensation amounting to
Rs.924615 on the defendants.
6. Now, the plaintiff has claimed the aforesaid
amount of Rs.9,24,615/- along with interest thereon from
18.3.1991 to 1.2.2005 at the rate of 18% per annum,
amounting to Rs.24,40,984/-.
7. The case of the defendants in the application under
consideration is that the case of the plaintiff being barred by
limitation, the plaint is liable to be rejected. Their
contention is that since the supply of cement according to
the plaintiff was required to be completed by 9.11.1985, the
cause of action for filing the suit arose on that date and the
plaintiff could have filed the suit within three years from
that date or at best within three years from 23.2.1987 when
the last supply of cement was made by them to the plaintiff.
Having been filed as late as on 17.1.2006 the suit, according
to the defendants, is clearly barred by limitation.
8. The case of the plaintiff with respect to limitation is
two-fold. Its first plea is that they had no cause of action to
file a suit for recovery of liquidated damages before
31.8.2004 when the damages were determined by Director
(Material Management), the authority designated for this
purpose vide Clause 2 of the contract. Its second
contention is that since it had referred the claim for
liquidated damages to the Arbitrator appointed on 1.5.1991,
in terms of the arbitration clause contained in the
Agreement, it had been prosecuting the proceedings before
the Arbitrator, with due variance, in the belief that he had
jurisdiction to entertain the claim for levy of compensation
and therefore, it is entitled to benefit of Section 14 of the
Limitation Act and the period during which the proceedings
were pending before the arbitrator is required to be excluded
while computing the period of limitation. This is also their
case that it were the defendants who had delayed the
arbitration proceedings by first obtaining stay of the
proceedings from the Civil Court at Satna, then by filing an
appeal before the High Court of Madhya Pradesh and
obtaining a stay order and thereafter by filing a petition in
this Court for appointment of an Arbitrator.
9. A careful perusal of Clause 2 of the Agreement
between the parties would show that the amount of the
liquidated damages to be paid by the contractor to DDA was
to be decided by the Superintending Engineer of DDA whose
decision in this regard was to be treated final. The amount
of liquidated damages could be one per cent, of the
estimated cost of the late work, which in this case would
mean price of the cement to be supplied by the defendants,
for each day the contractor exceeded the time of delivery or
such smaller amount as the Superintending Engineer might
decide. However, the total amount of liquidated damages
was not to exceed 10% of the estimated cost of work, which
in this case would mean 10% of the price of the cement to
be supplied by the defendants to the plaintiff.
10. Till the designated authority adjudicated on the
amount to be paid by the plaintiff as liquidated damges,
there could have been no cause of action for the plaintiff to
file any suit against the defendants for recovery of liquidated
damages. It is not as if the quantum of liquidated
damages was fixed in the Agreement between the parties.
Only the upper limit of the damages which could be
awarded to the plaintiff was fixed under Clause 2 of the
Agreement and the Superintending Engineer would have
been well within his right to fix an amount smaller than
10% of the price of the goods to be supplied by the
defendants to the plaintiff. In fact, in this case, the amount
of liquidated damages, fixed by Director (Material
Management) of DDA was only 10% of the price of the goods
to be supplied by the defendants, though it could have been
up to 10 times that amount.
Since the decision by the Director (Material
Management), deciding the amount of liquidated damages
payable by the defendants to the plaintiff was rendered only
on 31.8.2004, the prescribed period of limitation is to
commence only from that date. The suit having been filed
on 17.1.2006, within three years from that date is,
therefore, well within time.
11. One plea taken by the defendants is that even
Director (Material Management) of DDA could not have
levied liquidated damages on 31.8.2004, more than three
years after the last date stipulated in the Agreement for
supply of cement by the defendants. However, while
considering the application under Order VII Rule 11 of CPC,
the Court is not called upon to decide this question and
therefore, the question as to whether the suit has been filed
within the prescribed period of limitation or not is to be
decided on the assumption that Director (Material
Management) was well within his right to levy liquidated
damages on 31.8.2004.
12. The learned counsel for the defendants states that
since the defendants vide letter dated 13.2.1985 had written
to DDA that they would not be responsible for any damage
due to late supply of cement, due to non-availability of
wagons and movement restrictions imposed by Railways
and also due to natural calamity, labour strike and other
constraints, they are not liable to pay any amount to the
plaintiff towards liquidated damages. He further states that
this letter was also made a part of the agreement between
the parties.
13. At this stage, the Court cannot examine the
defence taken by the defendants. For the purpose of
deciding this application, the allegations made in the plaint
are to be taken as correct and on their face value. The case
of the plaintiff, based on Clause 2 of the supply agreement
is that time was the essence of the contract as expressly
agreed by the parties and in the event of delay in supply of
cement by the defendants, they would be entitled to
liquidated damages not exceeding 10% of the price of the
material agreed to be supplied to the plaintiff. This is not
the case of the defendants in the written statement that
delay in supply of cement occurred on account of non-
availability of wagons, movement restrictions imposed by
Railways, any natural calamity or labour strike. The case
set up by them in the written statement is that the plaintiff
was required to make 100% to the defendants and since it
failed to make payment, accordingly that led to delay in
supply of material. In any case, the cause for the delay in
supply of material is a question which can be adjudicated
only during trial.
14. Since the plaintiff had no cause of action to file any
suit for recovery of the amount of liquidated damages before
31.8.2004 when the decision of the Superintending
Engineer came to be rendered, I need not go into the
question as to whether the plaintiff is entitled to benefit of
Section 14 of the Limitation Act on account of the
proceedings which were pending before the Arbitrator from
May, 1991 till 21.9.2005 and in which the plaintiff had also
raised claim for liquidated damages against the defendants.
15. I find no merit in this application and the same is
hereby dismissed.
16. CS(OS) No.415/2006
List for framing of issues on 10.3.2011.
IA No.6409/2006
The learned counsel for the defendants does not press
this application.
Dismissed as not pressed.
(V.K. JAIN) JUDGE
DECEMBER 03, 2010 vk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!